- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 14 January 2026
-
Current Status:
Answer expected on 28 January 2026
To ask the Scottish Government by how much the capital budget for colleges will increase in 2026-27.
Answer
Answer expected on 28 January 2026
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 14 January 2026
-
Current Status:
Answer expected on 28 January 2026
To ask the Scottish Government how much of the Just Transition Fund has been spent to date.
Answer
Answer expected on 28 January 2026
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 14 January 2026
-
Current Status:
Answer expected on 28 January 2026
To ask the Scottish Government how much of the £500 million committed to the offshore wind supply chain over five years has been allocated to date.
Answer
Answer expected on 28 January 2026
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 14 January 2026
-
Current Status:
Due to be taken in the Chamber on 21 January 2026
To ask the Scottish Government what the new Infrastructure Delivery Pipeline means for a replacement eye hospital for Edinburgh.
Answer
Taken in the Chamber on 21 January 2026
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Friday, 12 December 2025
-
Current Status:
Answered by Neil Gray on 23 December 2025
To ask the Scottish Government what discussions it has had with (a) NHS Lothian, (b) the City of Edinburgh Council and (c) housing developers regarding ensuring that new housing developments in the south of Edinburgh are supported by adequate GP provision, in light of reports that Edinburgh is short of more than 10,000 GP places.
Answer
NHS Lothian and Edinburgh Health and Social Care Partnership are responsible for planning primary medical services provision in Edinburgh and making appropriate provision for new housing developments.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 03 December 2025
-
Current Status:
Answered by Ivan McKee on 10 December 2025
To ask the Scottish Government, further to the answer to question S6W-40488 by Ivan McKee on 2 October 2025, and in light of the publication of the Sustainable Digital Public Services Delivery Plan 2025-2028, whether it will provide an update on the number of self-sufficient information and communications technology (ICT) structures with dedicated data centres and professional staff that exist within the Scottish public sector, including non-departmental public bodies (NDPBs), NHS boards and local government.
Answer
The detailed information requested is currently being collated from those bodies that fall within the responsibilities of the Scottish Ministers. I will write to the member as soon as the information is available and a copy will be placed in the Parliament’s Reference Centre (Bib number: 66325).
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Friday, 21 November 2025
-
Current Status:
Answered by Kate Forbes on 9 December 2025
To ask the Scottish Government what assurances it has received regarding potential further increases in construction costs for the Dunard Centre project in Edinburgh, and what assessment it has made of whether there is ongoing public support, in light of the operational costs.
Answer
As part of the due diligence required for the additional £20 million pledge, the Scottish Government continues to work with IMPACT Scotland to ensure all cost mitigation measures have been taken to reduce the risk of further increases in construction costs, in addition to assessment of the affordability of latest cost estimates and future sustainability of the organisation post-construction.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Friday, 21 November 2025
-
Current Status:
Answered by Kate Forbes on 9 December 2025
To ask the Scottish Government (a) how and (b) when it was made aware of the increase in project capital costs for the Dunard Centre in Edinburgh from £45 million to £162 million.
Answer
The Scottish Government was informally updated that the project capital costs for the Dunard Centre were expected to rise during the course of regular engagement with IMPACT Scotland, the Edinburgh and South East Scotland City Region Deal Programme Management Office and the United Kingdom Government. The Scottish Government was then notified of the scale of the increase in project capital costs for the Dunard Centre on 26 June 2025 as part of a discussion with IMPACT Scotland.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Friday, 21 November 2025
-
Current Status:
Answered by Kate Forbes on 9 December 2025
To ask the Scottish Government what communication it has had with the UK Government regarding the additional capital costs for the Dunard Centre project in Edinburgh through the Edinburgh and South East Scotland City Region Deal.
Answer
The Scottish Government maintains regular communication with the United Kingdom Government regarding the Dunard Centre, as joint funders of the project through the Edinburgh and South East Scotland City Region Deal. On the additional capital costs for the project, we have engaged regularly with the UK Government and regional partners through a range of interactions over a number of months.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Friday, 21 November 2025
-
Current Status:
Answered by Kate Forbes on 9 December 2025
To ask the Scottish Government what appraisal it has made of the options available to secure the provision of other suitable music venues in Edinburgh, in light of the rise in the costs of the Dunard Centre project in the city.
Answer
The Scottish Government supports music venues through Creative Scotland’s Multi-Year Funding which has increased by £20 million, providing a major boost to Scotland’s cultural sector. This investment provides stability for organisations to plan and deliver high-quality programmes in theatre, visual arts, literature, and music.
Forty-six music organisations now receive multi-year support which is more than double the previous number – with potentially three more in development for
2026-27. The Scottish Government has also put in place 40% non-domestic rates relief for Music Venues with capacity up to 1,500 for 2025-26.