Current status: Initiated by the Scottish Government. Answered by Paul McLennan on 6 January 2025
To ask the Scottish Government whether it will provide an update on the priorities for cladding remediation work in 2025.
With the commencement of the Housing (Cladding Remediation) (Scotland) Act taking place on 6 January 2025, it is timely to set out a brief statement of our strategic priorities for action on cladding in 2025.
In particular, we will be:
• continuing to take forward our current programme of action
• taking action to increase both the pace and breadth of action on cladding
• seeking to develop a collective, national endeavour to address the risks of cladding.
On continuing action – completing work currently underway
We will deliver assessment and remediation for properties that have been part of our 'pilot' programme and for which the Scottish Government is taking responsibility in the absence of an identified developer:
• we will deliver assessment and if required remediation for an initial set of ‘pilot’ buildings for which the Scottish Government is responsible. 13 Single Building Assessments are underway at the moment. Based on their findings, we will set in train all necessary remediation action, putting interim safety measures in place where needed
• based on due diligence work currently underway, we will also take forward assessment and remediation for any additional pilot buildings within the scope of the Act for which it is confirmed that responsibility falls to the Scottish Government. Where responsibility falls to others, we will identify and communicate this to those parties and to residents.
We will complete implementation of the Housing (Cladding Remediation) (Scotland) Act 2024:
• we are commencing the Act in its entirety on 6 January 2025
• we will put in place practical arrangements for the long-term operation of the Cladding Assurance Register, building on the interim arrangements now in place
• we will develop, consider and consult on proposals for a statutory Responsible Developers Scheme
• as part of the response to the Grenfell Tower Inquiry phase 2 report, we will confirm our position on the use of Personal Emergency Evacuation Plans (including use of the powers provided by the Act).
We will enable the assessment and remediation of affected properties by the relevant larger developers:
• we will seek swift agreement with the larger developers on the ‘Developer Remediation Contract’, enabling them to take forward assessment and remediation on properties for which they have accepted responsibility
• as part of an ongoing process of engagement with the larger developers, we will track, assure and gather information on their remediation progress.
We will continue to improve communication with residents and owners affected by cladding:
• we will continue to produce a quarterly newsletter aimed at residents along with monthly updates, backed by up-to-date information on the Scottish Government website including ‘Frequently Asked Questions’
• we will fully observe the new statutory duties on communication with owners and residents in buildings for which assessment and remediation is being taken forward under the new Act.
On new action to increase pace and breadth
In parallel, we will work with partners to develop and deliver two new schemes of assessment and remediation:
More generally, we will bring partners together to seek to make action on cladding a national, collective endeavour:
We will publish a renewed plan of action in March, setting out how and when we will be delivering these priorities.
Interested parties can at all times sign up to receive our regular newsletter, and/or raise specific cladding issues with us on our website.