Question

To ask the Scottish Government how much currently remains in outstanding private finance initiative (PFI) and public private partnership (PPP) payments across the public sector in Scotland.


Answer

The total estimated remaining unitary charge payments associated with PFI and PPP contracts including NPD (Non-Profit Distributing) across the public sector in Scotland from 2023-24 onwards are contained within the following table.

 

2023-24 onwards

 

(£m)

PFI

14,699

NPD (pre-2010)

1,299

NPD Programme

7,113

Total

23,111

Further information on these published figures as at 31 March 2023 can be found be at the Scottish Government website via the following link under the ‘NPD and PFI projects’ section: https://www.gov.scot/policies/government-finance/infrastructure-investment/#npd