Question reference: S6W-22487

  • Asked by: Willie Rennie, MSP for North East Fife, Scottish Liberal Democrats
  • Date lodged: 26 October 2023
  • Current status: Answered by Mairi McAllan on 9 November 2023

Question

To ask the Scottish Government, further to the answer to question S6W-12674 by Mairi McAllan on 14 December 2022, whether it will provide an update on which of the 42 formal flood protection schemes or engineering works are (a) under construction and (b) at the planning or other stage of development, broken down by (i) the expected completion date, including the reason for any date being beyond the 2021 timeframe, (ii) the number of properties that will be protected and (iii) the (A) initial forecast and (B) final expected cost of each.


Answer

Local authorities are responsible for the development and delivery of flood protection schemes. The 2015-2021 Flood Risk Management Strategies included 42 formal flood protection schemes. Local authorities were expected to start work on development of these schemes by 2021.

Flood protection schemes can have significant impacts on individuals, communities and the environment, and so require careful and detailed planning and consultation, it was recognised that construction work may not be completed within the 2015-2021 timeframe.

15 of the flood schemes have now been completed.

Schemes (a) under construction are as follows:

Scheme

(ii)

Properties protected

(i)

Completion

Date

(iii A)

Initial cost

(£ million) (1)

( iii B)

Estimated final cost

(£ million) (2)

Upper Garnock

600

2023

15.5

18.5

Hawick

970

2023

37.4

78.6

Campbeltown

770

2024

9.3

15.2

Millport Coastal

657

2024

12.1

48.6

Stranraer

350

2024

0.4

1.2

 

Schemes (b) under development are as follows:

 

Scheme

Stage

(ii) Properties protected

(iii A)

Initial cost

(£ million) (1)

( iii B)

Estimated Final Cost of Scheme (2)

Kilmacolm – Glenmosston Burn

Confirmed (3)

Not held

0.5

0.5

Comrie

Confirmed (3)

189

15.7

28.4

Quarrier’s Village

Confirmed (3)

60

0.2

0.4

Dumfries - Whitesands

Confirmed (3)

166

18.9

37.5

Water of Leith (Coltbridge, Gorgie, Saughton) Phase 3

Confirmed (3)

75

Not held

Not held

Mill Burn Millport

Confirmed (3)

124

1.1

1.7

Musselburgh

Under development

2500

8.9

97.9

Dumbarton - Gruggies Burn

Under development

370

14.5

20.0

Newton Stewart/ River Cree

Under development

270

7.5

18.5

South Kinross

Under development

Not held

3.2

3.8

Bridge of Allan

Under development

Not held

4.4

17.3

Callander

Under development

30

2.4

4.7

Haddington

Under development

320

8.5

8.5

Stirling

Under development

810

26.2

85.6

Grangemouth FPS

Under development

2980

111.5

420

St Andrews - Kinness Burn

Under development

133

3.2

3.2

South Fords

Under development

58

1.4

1.4

Scone

Under development

44

0.7

0.8

 

(1) Note: Initial costs as provided by local authorities in 2016-17.

 

(2) Note: Final Scheme costs are the latest estimates provided by local authorities. Differences between these latest estimates and initial cost estimates arise as a result of inflationary pressures and because flood protection schemes are put forward for prioritisation at various stages of their development to fit with Flood Risk Management Planning cycle set out in the FRM Act. Costs are revised over time as designs are finalised and more detailed investigations are carried out and as new information emerges.

Schemes will only be taken forward for construction if they receive the necessary statutory and regulatory approvals so the expected completion date is not yet known.

More detailed information on each of the schemes can be obtained from the relevant local authorities whose responsibility it is to develop and deliver flood protection schemes and who are best placed to answer specific questions on each of the schemes.

(3) Note: Formally confirmed under Flood Risk Management (Scotland) Act (2009).