Agenda item 3 is evidence on the adequacy of the accompanying documents. We will hear from several panels of witnesses, so I ask the public and witnesses to bear with us, because people will move to and fro during the meeting. We will deal with that as efficiently as possible.
We do not wish to make an opening statement.
In that case, it will be in order for us simply to proceed to questioning. Section 70 of the bill refers to article 3 of, and class 29 in part 11 of schedule 1 to, the Town and Country Planning (General Permitted Development) (Scotland) Order 1992. So far as I understand it, by virtue of those provisions, planning permission will automatically be granted for development authorised by the bill, except for the erection of buildings and bridges and the formation, laying out or alteration of a means of access to any road, which must be subject to planning approval in the conventional sense and be dealt with by the local authority. Can you confirm for the record whether that is correct? It would be helpful if you could talk me and my colleagues through the types of work that will be subject to planning approval.
What you say is not exactly correct. It is true that, in general, development authorised by the bill will be given deemed planning consent, but the exceptions that you gave do not have to go through the full planning process; they require only an approval. If you are familiar with the planning system, you will understand when I say that it is a bit like the bill granting outline permission and then reserved matters—the detail—being agreed with the local planning authority, which is the council.
What would be the scope for someone to object?
The list that you gave is correct, and is as listed in the permitted development order. In section 70, for the avoidance of doubt, we deliberately clarified the definition of what is a building, so that people know in advance that particular items will be subject to final approval. For example, section 70(4) states:
Would you care to define "attachment"?
That is covered by section 15, which is on the power to attach cables and so on to buildings.
In section 15(1), you list various types of attachments. Could that include telecommunications masts, if you decide to install a system to enable your depot to be in contact with trams? If not, why not?
I do not think that it was envisaged that it would cover telecommunications masts.
I am not asking whether that was envisaged, but would such masts be included?
I am looking at the words. The categories are
Do you have any other questions, Alasdair?
Yes. The positions of tram stops are indicative at the moment. What further discussions will you undertake with the City of Edinburgh Council with regard to their final locations?
I will start with what the bill provides and hand over to Barry Cross to talk about how the system is being developed with certain locations in mind.
Stops are particularly important to the system, and in terms of the impact of the system on individuals and frontagers. For that reason, although the powers that will be conferred under the bill will enable stops to be located anywhere within the limits of deviation, the planning process that Angus Walker outlined effectively carries with it the detailed consent for those locations. The City of Edinburgh Council has, for its interest, already approved locations, which the team developing the project are not at liberty to move unless consent is sought from the council, both as the sponsor and as the planning authority. Effectively, three tiers of approval are required for stop location.
In other words, when the detail of tram stops appears, people in their immediate vicinity will be consulted and will have the opportunity to object.
Yes, they will have an opportunity to object.
How does that compare with the process that applies to bus stops? I am referring to bus stops that have a substantial shelter, not just those with a pole.
At the moment, there is no statutory requirement to consult frontagers on bus stops or on bus shelters. The council has a protocol that involves consulting frontagers, although it does not go beyond frontagers. If there are outstanding objections, they are taken to the appropriate local development committee. That is an extra process, which the council has put in place despite there being no formal statutory requirement to do so.
The promoter is very conscious that particular care needs to be taken with the design of stops and other apparatus and has produced a design manual, copies of which have, I believe, been given to the committee. The contractor building the system will be held to that. The design has been undertaken in discussion with Historic Scotland and other amenity bodies to ensure that it is of a high enough standard.
We turn now to the role of Historic Scotland.
You have gone a long way towards covering some of the questions that I was going to ask, and I am pleased to hear Barry Cross talk about the City of Edinburgh Council's protocol. How will the public be made aware of the protocol, so that they know what rights they have under the planning process? How will you ensure that the views of such agencies as Historic Scotland will be taken on board?
I will deal first with the question of Historic Scotland. Angus Walker has already mentioned the production of a design manual, which is the bedrock of the design. Historic Scotland was closely involved in the production of that design manual. I have outlined the protocol for the planning process following any granting of powers. Historic Scotland is involved in that process. The protocol is built around a series of routes involving a parallel system to that which would pertain if this process were an ordinary planning application. Applications appear on a weekly list, which is widely disseminated—it is available through the council portals. The process is then similar to that which applies for planning consents. For simple applications that conform to the design manual, a delegated powers route is proposed. For more substantive items that are defined or for items that differ from the design manual, there is a process that involves a planning committee.
Remember that the series of controls that Barry Cross outlined will apply to all attachments to buildings of whatever nature.
Thank you. We now turn to questions about the reasoning behind the use of the private bill procedure.
I want to dig down a bit into why the private bill procedure is being used. Some of the objectors suspect that the procedure could circumvent people's usual democratic rights to protest and that it could make things easier for the undertakers rather than give people genuine rights.
I will first give the general reasons why we chose the private bill route and then I will deal with compulsory purchase, if I remember about it—remind me if I do not.
Are you saying that the council could not use its existing compulsory purchase powers?
Not as I understand it. The council has such powers for regeneration, for example, but we are dealing with a specific transport system that is not covered by those existing powers.
I have a question for Barry Cross. Why is the council seeking powers to allow for the permanent stopping up of roads and to enable buses to share roads with trams, given that it already has those powers?
The answer is almost a subset of Angus Walker's answer. If the tramway requires certain measures, it seems appropriate that those should be dealt with as a single entity through the parliamentary process. If we took the alternative route of securing the minimum necessary powers through the bill and allowed traffic regulation and stopping-up powers to be secured using the means that the council already has at its disposal, it is not clear that we would not fetter the council in its assessment of objectives. We would have a bill that gave the council powers to build a tramline, although it could not do that because it would require other powers for some of the measures. When the council received a proposal to stop up a road, would it have any choice? How would it respond to objectors, given that it desired to build a tramline for which powers had been sought elsewhere? It is legitimate to consider in one forum the objections to each of the components that make up the tramway, because that allows due cognisance to be taken of all the objections.
If we needed a series of consents, another problem would be that we might end up in a catch-22 situation in which one authorising body would not authorise a piece of work until consent had been granted from another body, and vice versa. We might end up with bodies waiting for one another to give consent.
That is often the case in the planning process for major developments. Are you saying that it is simply more convenient for the promoter to deal with the issue through a private bill than to the powers that already exist?
No. I hope that I explained that it is necessary to have a private bill for the basic construction and operation of the tram. Although one or two other powers are being sought that could be obtained by other means, as Barry Cross said, some of the powers would come from the council—the promoter—so it makes more sense for a body external to the council to make the application for powers. That also means that the process is more transparent because the committee, the objectors and the promoter can understand the whole process.
I have no doubt that the process will be transparent. We acknowledge that the compulsory purchases that will be needed for the tramline require the Parliament's involvement. Have you estimated the time that it would take if the other powers were taken through the council's conventional planning mechanisms?
I have not estimated how long that would take, but it would take a long time.
If you have not considered the alternatives, why did you come to the conclusion that it would be more efficient to seek the required powers, other than the compulsory purchase powers for the tramline, through the parliamentary process?
We do not seek additional planning powers. We are using the existing legislation to which the convener referred in his first question, under which it is deemed that planning permission is granted for any act of the Scottish Parliament that specifies particular works. It is common sense that if we had to make a series of applications to many bodies, each depending on the other, that would take longer than a single process in the Scottish Parliament.
Marilyn Livingstone mentioned Historic Scotland, the evidence from which states that no monuments will be affected by the bill. Why do you seek exemption from section 2 of the Ancient Monuments and Archaeological Areas Act 1979?
You are referring to section 69 of the bill, which deals with ancient monuments. There is an ancient monument out at Gogar, which the proposed alignment of the tram skirts. We do not believe that the tram's route impinges on the ancient monument. If discussions with the engineers and Historic Scotland reveal that it is possible for the tramline to be constructed without scheduled monument consent—which would not normally be required—it may well prove to be possible to remove section 69 during the consideration stage. However, we are still in discussion with Historic Scotland and our engineers need to be satisfied that it is possible to build the tramline without affecting the monument.
In relation to Gogar fort and the surrounding enclosure and field system, Historic Scotland's evidence states clearly that
There was no prior discussion because we do not believe that the tramline goes near enough the fort at Gogar. However, we must be absolutely sure of that and when the bill was being drafted, we were not absolutely sure of that.
Historic Scotland is saying that they did not.
Yes, but Historic Scotland also says that it did not hear about the bill until six months after it was introduced.
As you know, Historic Scotland has a statutory role on behalf of ministers in the administration of the 1979 act, from which you are seeking an exemption.
Yes. In effect, by seeking an exemption, we are seeking the committee's authorisation for any works to ancient monuments that would be required. As I have said, if it turns out that no such works are necessary, we will seek to remove section 69.
Although the appendix to Historic Scotland's submission states,
Yes, certainly.
Does that not make it even more questionable that you are seeking exemption from section 2 of the 1979 act?
I do not think that it follows that it is questionable that an exemption is being sought. When it comes to the bill's consideration stage, we will certainly produce evidence to justify the use of section 69, if it is required.
You say that you are not clear about whether an exemption is being sought.
I am clear that an exemption is being sought.
You are clear that an exemption is being sought.
An exemption is being sought at the moment, but it is quite likely that it will be possible to remove section 69.
I will leave it at that. I am sure that we will return to the issue.
No doubt.
Yes—in all probability, we will revisit it.
I am aware of the Waverley issue but the tramline scheme is quite different because it is half rural and half urban. Looking at the Waverley project was very much part of the learning curve for this particular bill process; we have gone through that process on quite a few occasions and provisions have been made in the methodology—relating to the line-referencing issues that generate the notices—to ensure that the Waverley problems do not arise again.
I am obliged to you for that answer. Will you please explain LandAspects' role?
Certainly. LandAspects is the referencing contractor for the Edinburgh Tram (Line Two) Bill. That work involves identifying lands that are within the limits of deviation—the lands to be acquired or used—as supplied by the engineers. It also involves identifying the legal interests in those lands and ensuring that those interests are then served with the appropriate notices that describe the powers that are being sought.
I want to ask about the questionnaires that were used to gather information on property. Can you explain the contents of the questionnaires?
There are several stages in the land referencing process. The first starts before the exact route alignment is known. Clearly, during the consultation process the route alignment varies as members of the public are consulted and are able to give their opinions. As the engineering develops, the corridor of the route will be refined. At that stage, the land referencing process involves the examination of certain documents that are available publicly. Those documents include, among others, the land register of Scotland, the Register of Sasines and the electoral roll. Following the consultation process, we will talk to landowners to be sure that they have established their land interests and that we have understood them. That process includes the land interest questionnaire, which I believe is the questionnaire that you refer to.
In how many areas was there uncertainty as to ownership of heritable land?
The land referencing process depends on the co-operation of the people being referenced. Generally speaking, we have had a great deal of co-operation. In one area that is geographically quite large we were not provided with the information that we asked for. However, I do not believe that that has prejudiced the landowners concerned. We knew who they were and, if anything, we have overnotified rather than undernotified by including people who may have no interest. If you like, we have overegged the pudding.
Have you covered owners of land or property that abuts the area of the scoped works?
Yes. We are obliged to notify people who have heritable interests in properties that would be affected by the works. As a result, we sent out landowners' notices and included in the book of reference the people whose properties are within the limits of the scheme.
After the discussions that were held with the promoter of the Waverley line, did you review your work on this project?
Yes.
Did you also review your procedures?
Yes. The procedures were revised at the commencement of this work.
Was the route of the line reviewed?
The route?
Well, your scoping work was effectively reviewed on the same basis as the supplementary work that you undertook on the Waverley project.
We have examined what we have done and are satisfied that reasonable inquiry was made. Just over 3,500 notices were duly served for the project. The Post Office returned some of them to us—I think that it was just over 300. The notices had been served by recorded delivery and the majority of those that were returned were not called for at the Post Office. We carried out further research to ensure that the notices had been correctly addressed, after which all the returned notices were duly re-served. They remain served in that they have not been returned to us.
So none of them was returned to you?
All the notices that were returned were re-served successfully.
There may have been an omission on my part, but I cannot trace our receiving a copy of your questionnaire. I am sure that you will appreciate that the papers are voluminous to say the least, but it would be useful if you could supply the clerk with a copy.
Certainly.
Your response of 20 September to the committee's questions contains a number of statements that the issues relating to individual objectors' comments on the accuracy of maps, plans, sections and the book of reference were "being investigated further". Can you provide us with an update on your investigations?
On certain occasions, we have been asked questions about the documents you describe and, where possible, we resolved the issues there and then. However, some of the questions related to what is, in effect, the engineering as it appears in the plans and sections and not to issues of notification. Those questions are matters for the engineers and the project in general.
Obviously, the committee is concerned that the documents are accurate. It would represent a significant failure on the ability of the promoter to depict exactly the impact of the development if documents were not accurate. Given that you said that matters were "being investigated further", could you write to the committee to give us more detail of what stage the investigation is at, or to give us the outcome, if the investigations are complete?
Certainly.
We would be interested to see the information.
The response also said that the project would have to do on-site inspections to check that the Ordnance Survey data were up to date. Can Ashley Parry Jones say anything further on the subject?
Yes. The project used the most up-to-date Ordnance Survey mapping available at the time. In certain areas we noticed that development had taken place since Ordnance Survey had carried out its survey. Where it appeared that such development was significant to consideration of not only what was within the limits of deviation but what could be adjacent to them—we are notifying people who are adjacent—local surveys have been carried out or alternative mapping has been sewn into the Ordnance Survey mapping, if you like, to present a more accurate picture on the ground.
On how many occasions was that done?
I think that, on line 2, it was done only two or three times.
Was that work undertaken along the entire route?
I believe so.
For example, there is an area at the end of the route at Newbridge where a lot of redevelopment is happening at the moment. New industrial units have been built but although they are not shown on the OS plans we have obtained details of them in topographical surveys and information from the planning process. That allows us to insert the buildings into the background plans.
On Crown consent, you are aware that under rule 9A.13 of the Parliament's standing orders, any bill that affects hereditary revenues or private interests of the Crown cannot be passed unless appropriate consent has been signified. Are you aware of any property that would come under that rule?
Not on the route of line 2.
We now turn to our next group of witnesses—Hazel Young and Jacky McKinney. Good morning and welcome to the committee. I am sorry that the meeting is taking so long this morning, but that is inevitable with such a complex matter. You represent the West Edinburgh Residents Tram Action Group—WERTAG for short. I will invite you to make a brief opening statement shortly, but it might be useful for you to know that last week the committee did a site inspection of the route and were in the area that you represent. Who is going to lead off?
I guess that I will. Hazel Young is our chairperson, but because of her circumstances she feels that it would be best if I were the opening speaker. I am not sure what you expect of us. We have never done this before, so it is all new to us. Our subject this morning is the consultation process. Our views about how the consultation experience was for us as a community are clear. We felt that the information given at the very beginning in the "Talktime" brochure, which was distributed city-wide—allegedly—was scant and sanitised. Residents of the three streets in the community that we represent did not even receive a brochure at the outset. At the beginning of the process three routes were up for selection by the public and could be voted on. I live in Whitson Road and I discovered that my property was on the routes that were being voted on when I visited my mum and saw the exhibition, rather than by getting the brochure through my front door. You can imagine that the experience of residents along the three streets that we represent was similar, so we were disappointed by the consultation initially.
We will give you the opportunity to amplify that evidence. Miss Young, do you have anything to say at this juncture?
There is nothing that I would like to add.
Right. We will proceed to questioning.
A lot of the questions that we were going to ask have probably been answered in your written evidence and in the brief introduction that you have just given. When did you first hear about the line 2 proposals and how did you find out about them?
My mum lives just next door to Saughtonhall United Reformed Church, which is one of the buildings where there was an exhibition about the trams project. I just happened to be visiting one day and popped in. There, I spoke to a supposed technician or expert who informed me—when I looked at the plans it was clear—that one of the options would have taken up a large part of my back garden. That came as quite a shock. When I pointed out that that could not be right, as that was my property and I lived there, he said, "No, it is right." When I pressed him about how much property he was intending to purchase compulsorily, should option B be selected by the public, he informed me that it would be 18ft. That ballooned to an alarming 36ft when I attended a public meeting a few days later.
So you heard about the development by accident and it came as a complete shock. When was that?
That was in May last year, when I visited the exhibition. I believe that the public meeting at Tynecastle was held in June.
My experience was the same. I am round at the church quite a lot, as my daughter attends things there. I noticed that there was an exhibition on and I went in to have a look. I was absolutely horrified when I saw the drawings. I spoke to the engineer who was present and was a bit worried by the information that he gave me—or, rather, having looked at the drawings, I did not feel that the information that he was giving me was complete or true. I had been used to looking at planning drawings and such things in the past. The things that he told me about the distances that were required, the space that would be left and so on just did not ring true when I looked at the drawings.
You may not be able to answer this question—it does not matter if you cannot—but do you know which of your neighbours had heard about the project? You said that a lot of them had not heard about it. Do you know how those who had heard about it found out?
The majority of them, like me, saw the exhibition at the church. The news was then passed on by word of mouth, by meeting people in the street and asking whether they had heard about the project. Most of them heard about it in that way.
Do you think that the promoter has made an effort to publicise the project and to ensure that residents are able to participate in the consultation?
The promoter has subsequently set up a community liaison group, through which people from the community or their representatives can participate, and we have been invited along to the meetings of that group.
You said that you attended an exhibition about the project. How many public meetings, roadshows and displays were held? How much information was available to you and how were your questions dealt with? What feedback did you receive from the promoter about how your group's views had been taken on board?
An exhibition was held for the wider community at Saughtonhall United Reformed Church. People from our area might also have had access to exhibitions at the Gyle and other places. The specific public meeting for our area was held at Tynecastle High School and the people I know who attended that meeting learned of it through the newspaper. After I talked to the technician at Saughtonhall Drive about what would happen to the side of Whitson Road nearest the railway line, I carried out a door-to-door because I was shocked at and exasperated by the implications.
I would like to narrow things down a little. The discussion is extremely interesting, but the committee will enter consideration stage further down the line, when that issue will be particularly pertinent. However, this morning we are considering the adequacy of the documentation.
The witnesses describe some of the consultation material and information as "misleading". Can you explain in what way you believe that to be the case?
A brochure was delivered in the various streets concerned—although I would have chosen to have it delivered citywide. It was indicated that, under option A, I would lose property and that, under option B, there would be an impact at the back of Hazel Young's property—those were described as having "some impact" and "slight impact". Under option B, 12 houses will have to be knocked down. At the back of Baird Drive, a tramline will be running at the foot of people's gardens. There will be noise and the embankment is to be wiped away, so the people who live there, who already suffer train noise, will have both tram and train noise with no barrier. We feel that, if ordinary householders like us had access to that information, they would think, "Crikey, would I like that at the foot of my garden?" and would say no and vote for option C, which would thread the project through an area of derelict ground, which would affect nobody.
Are you aware of the consultation report done by the consultants to the promoter, the public relations company, Weber Shandwick?
No.
So you have not seen it and you were not aware that it had been put together. You were asking before whether the assumptions about popular support had been challenged. In any case, you are not aware of the document.
I am not aware of it. The paperwork is voluminous, and—
I am sorry—I did not catch that. Could you repeat that?
The amount of paperwork attached to the process is huge. We might well have given something a scant reading, but I am not especially aware of the document to which Jeremy Purvis is referring.
I turn to the paper that you gave us and the subject of the community liaison group meeting involving Stenhouse community council. Have you had other links of that sort? I presume that that is your local community council.
It is my local community council. Hazel Young's area abuts Murrayfield, so people in her street are on the borderline.
Very early on in the discussions, were you in contact with your local councillor or with the local community council?
Yes. I attended my local councillor's surgery after I had spoken to a technician and had attended a meeting at Tynecastle. When I put all my specific concerns about Whitson Road to him, the information that I got back was quite astounding, which is why I have chosen not to have much to do with him during this whole process. He gave me a potted history of transport proposals through the ages. He rolled his eyes and said as much as, "This has happened before. Just you leave it with me. It will all blow over." When I pressed him and asked him whether he was saying that the project would roll on and on but would eventually come to nothing, despite all the money that had been spent, he just nodded and said, "Let's wait and see." I did not feel that that was a very constructive approach to the situation. Apart from anything else, if the proposals did come to nothing, a huge amount of time, effort, money and stress would still have been gone through, all for nothing; so, I circumvented him.
I had the same experience. I, too, went along to Eric Milligan's local surgery and was given more or less the same information that Jacky McKinney was given when she met him. When I pressed him on the matter, he said that the corridor had been targeted again and again and that, even if the proposals did not go through, it was inevitable that it would be targeted yet again some time down the line, and that I must have been aware of that when I bought my property. Obviously, I came away from the meeting thinking that there was no support there and that I would certainly not turn to him for support in the future.
You have said in your note that you are going to have no further contact with TIE.
There is no point, as the community liaison group is on-going. At the moment, we want to participate in the parliamentary process and to find out whether the bill will go ahead. If it does, only then will it seem pertinent to spend our time having an input to the construction. The issue is not that we do not want the tram project to go ahead; it is that we want the embankment at the rear of Baird Drive to stay intact. TIE does not see any way in which that can happen, so there is no point in talking about that until we can become involved in the issue again during the various mitigation processes to limit the impact on residents.
Which community council area do you live in?
Whitson Road is part of Stenhouse, but Baird Drive is on the border between Stenhouse and Murrayfield, so it dips into both. Councillor Milligan, for example, is the councillor in the Stenhouse ward, but Murrayfield has an interest. There is a boundary line and a grey area.
But you must be on one side of the boundary or the other. Do you know which?
I think that there is a boundary on Balgreen Road, but Baird Drive would appear to come under Murrayfield community council, whereas Whitson Road does not. However, the councillor covers both areas.
In your submission, you say that you requested a hard copy of the environmental statement, but that the request was declined. From whom did you request a copy?
At the time, the stakeholder manager was a lady called Nicola Rainy-Brown, who I think has left TIE. We asked her for a copy of the environmental statement, because it is a huge document and it would have cost us £70-odd—she said—to get a hard copy of it. We are a small group with no funds, and to download it from our computers was an impossible nightmare, so we asked whether we could have a copy for the group. I think that she said that there were legal reasons for her being unable to supply it to us and that, if she supplied it to us, it would almost set a precedent for supplying it to other people. Eventually, we got hold of it in dribs and drabs from other people, but we were told at the beginning that we could not have it.
Did you have it on compact disc?
No. We managed to get it ourselves by allocating little bits of it to people to download from their computers.
Okay, but am I correct in saying that the problem was not that it was not available to you, but that it was not available to you at no cost?
Yes.
Obviously, we are just the ordinary Joe Bloggs in the street.
I understand that. I just wanted to be sure that nobody refused to give you the statement, even at a fee.
I thank the witnesses for coming—the session has been extremely useful.
I am a director of CGM (Edinburgh) Ltd, which is the owner of a new office block at Haymarket called Citypoint. The promoter's memorandum for the Edinburgh Tram (Line Two) Bill explains the consultations that were undertaken. Paragraph 28 states that "a widespread consultation" on the two proposed lines took place between May and July 2003. We have the leaflets that were distributed to the public as part of the consultation exercise, which showed the proposed alignment for the route of the tram, with alternative options at certain points. At Haymarket, the alignment was understood to be alongside the railway line. The leaflets asked whether the route in general was supported. Citypoint was unaffected by the proposed alignment and we did not respond to the consultation.
Thank you. You went beyond the terms of the question, but we would have got around to asking you for the further information that you supplied.
I will be speaking, if I may. We have a brief opening statement that we hope will assist the committee.
It might resolve our questions.
Indeed.
I must interrupt you, Mr Reid. What you say is useful, but you must appreciate that the purpose of today's meeting is somewhat narrow, so perhaps you could confine your remarks to the basic subject of today's meeting.
I am obliged, convener.
We are obliged for that statement, which has pre-empted a number of the questions that we might have asked. Do members have any questions?
From what has been said and from the written evidence, it is clear that the witnesses were not happy with the initial consultation. I ask the representatives of both NULLA and CGM (Edinburgh) Ltd how they feel that the continuing consultation is going. Following the consultation for line 2, the promoter's consultants, Weber Shandwick, produced a consultation report, which I think Jeremy Purvis referred to when we were asking questions of the previous panel. Has either organisation seen the document or been informed of its production?
My colleague Craig Wallace will answer that.
We are certainly aware of the document's existence and of the initiatives that Weber Shandwick undertook to publicise the scheme. As my colleague has mentioned, the key issue is the lack of a direct approach by TIE to Norwich Union prior to the bill's introduction. On the on-going consultation with TIE since the introduction of the bill, we have been contacted a number of times, largely as a result of the formal objection that we submitted as part of the bill process. We have had a couple of meetings with TIE to discuss the opportunities for further investigation of and change to the detailed route alignment in relation to Rosebery House. It is clear that we are dealing with a defined limit of deviation, which offers little room for manoeuvre around the building. We are faced with a single route to the front of the building, which, as has been highlighted, delivers many disbenefits as a result of the severance of the public road from the entrance to our building. It is our understanding that, at this point, there is limited opportunity to change that. That is why we are asking for a further opportunity to discuss the detail of the route with TIE so that we can come to an agreeable compromise.
Mr Mitchell, will you or Mr Walker answer that question for CGM (Edinburgh) Ltd?
We have heard nothing about the Weber Shandwick report. However, we have had extensive discussions with TIE mainly to resolve the car parking issue. Those discussions have taken a long time and are still on-going, but we hope that the matter will now be resolved very quickly.
We have no further questions. I am obliged to you, gentlemen, for your evidence.
The website, which was meant to introduce people to the concept of trams, was set up before the consultation began and its address was included with the freepost and freephone numbers in the initial documents that were issued pre-consultation. The website was updated throughout the process; when the consultation began, the consultation documents and other information were uploaded to it and documents were uploaded when the consultation ended. Indeed, as we have gone through the process, any publicly available documents that we have produced—such as the accompanying material to the bill or documents that were submitted to the council as part of the process—have also been uploaded. For example, the design manual, the environmental statements, the financial statements and all maps, plans and sections are available for viewing on the website.
How many hits has the site received?
During the consultation, the site received between 30,000 and 50,000 hits a week. I do not have any figures for the number of hits since then, but I can certainly provide those to the committee.
How did you actively encourage the public to provide information?
We used a number of different mechanisms throughout the consultation. At the very beginning of the process, we were asked to plan a consultation that would reach as many people as possible and give them as many mechanisms as possible for responding to us. As a result, we put together an integrated consultation in which people did not have to rely on one specific source of material for information.
That all sounds very impressive, so I presume that you were very disappointed to learn that, according to a lot of objections—I take it that you have a copy of them all—the consultation has been seen to be quite poor. Some people feel that they have had no initial consultation. Are you disappointed by that? Can you explain why that is the case?
The original objective of the consultation was to inform people and give them a mechanism by which to respond. The underlying objective is to create a public debate about the proposals, to encourage discussion and to encourage people to come forward for more information. I think that we succeeded in that.
My question is along the same lines. Were the leaflets that were delivered to households delivered through a commercial organisation?
The leaflets that were delivered to households and businesses along the route of the line were delivered through a commercial organisation.
I suspect that those who will have most interest are those whose properties abut one of the proposed routes. Was any particular effort made to ensure that the commercial companies that delivered the leaflets actually covered the streets concerned? Most of us know from our own history of delivering leaflets that it is quite easy to miss out streets if we do not know the area well.
The brief that we gave to the company that delivered the leaflets included all the council wards that the route went through. The commercial companies in the area were also given a copy of the detailed route.
Lesley Clark has given a detailed response on the consultation that has taken place. What actions has the promoter taken in consideration of the comments that have been made, taking into account all the feedback forms and all the different types of consultation? What action has been taken to address some of the issues that have arisen?
We took considerable regard of the responses that we received. In some cases, that resulted in the route being amended or stop locations being moved slightly. I will run through a list. One of the main cases was in the city centre, where it is technically achievable to build the line on George Street or Princes Street. There was huge public support for the Princes Street route and significant heritage organisations had great concerns about the route through George Street and Charlotte Square. Cognisance was taken of those opinions.
You say that the Haymarket rerouting came about as a result of the first round of consultation. If the new route affected somebody who did not think that they were affected by the first choice, did you not have an obligation to re-consult?
I will pick up the story about Haymarket. We have had two project managers for line 2. Geoff Duke is the project manager at present, but at the time of the consultation last year, I was responsible for that area of work and I am here to answer any relevant questions on that.
That was not really my question. My question was about somebody who did not object to the original plan because they thought that it would not affect them too much. They would not have been consulted when the new route moved the line in such a way that it did affect them. You say that the plan is just indicative and that we have to take account of full integration at Haymarket, but people could not reasonably have foreseen that the process of integrating the tramline with the railway would end up moving the tramline further away from the railway. There is no way that they could have thought that the line would move to the other side of Rosebery House.
At the first stage, we were not consulting on the route. We were consulting and seeking parties' views on the preferred route, which passed through the Haymarket yards. We were cognisant of the fact that we were receiving information in order to take matters forward. On the point about reopening the consultation, we would be concerned about being fair to everybody if we consulted on the results of the consultation. We had received the information and we made a recommendation on the preferred route. We were aware from the advice of our consultants that there was no other option and that any issues could be resolved, as indeed has happened. The bill has gone forward and we have entered into detailed consultation with people on the issues that have arisen.
Sorry—are you saying that there are no issues to be resolved? If so, I wonder why the objectors were in front of us half an hour ago.
There are issues to be resolved all around the line about trams passing in front of premises, but we are confident that those issues can be resolved and we are working with the objectors to resolve them.
Nonetheless, it is understandable that some of the objectors think that the goalposts have shifted.
We do not think that the goalposts have shifted. We sought views in the Haymarket area; we highlighted the development and it has been well publicised. It is known that there will be major redevelopment at Haymarket. It is quite clear in our brochures that that issue is being taken into consideration. Also, this is the only viable option with which to go forward.
That is what any developer says when they have a preferred route option. However, the people who were before us earlier thought that they should have been consulted on that option and it is clear that they have not been.
We and our advisers were confident that we had received all the necessary information to take that decision, which was then discussed with the council. At those meetings, other people made representations. There were council meetings that led to the final decision, on which we went forward.
How many one-to-one meetings have taken place between owner-occupiers and either TIE or Weber Shandwick on behalf of TIE? Were those meetings instigated by TIE or by requests from objectors?
In general, we would not have been having one-to-one meetings with householders. Jacky McKinney and Hazel Young referred to a meeting that we had with them at their request at a stage of the consultation when their concerns were growing. They asked us to go to their house to speak to them and it seemed appropriate to do so. At that time, they did not like the method of our public meetings, at which we stand before a crowd talking. They preferred the more intimate surroundings of a house because they felt more comfortable there. That is the only instance in which we had a one-to-one meeting with a household.
Have meetings been requested but refused? I am talking not necessarily about one-to-one meetings, but meetings with small groups of residents.
Not that I am aware of. I cannot think of a reason why we would refuse to speak to someone. As Lesley Clark said, the purpose of the consultation process was to make people aware of the scheme and for us to receive their comments. It would have seemed wrong not to go along and meet them if they had requested a meeting.
I will ask the TIE witnesses the question that I put to Lesley Clark. Are you disappointed that people who will be directly affected by the scheme found out about it by accident? How did that happen?
We are disappointed. Given that we put a large amount of planning and resources into the consultation process for a significant scheme, it is disappointing that some parties have reason to complain about or object to the process. We dealt with the problem by immediately re-leafleting in the area and carrying out back checks to ensure that people had received the leaflet. Our objective was to ensure that people knew about the scheme and I think that we achieved a situation in which all the people whom we wanted to know about the scheme knew about it.
It is surprising that the Weber Shandwick consultation report was not more widely distributed. I think that I asked all today's witnesses whether they had received the report or heard of it. Some witnesses had heard of the report, but I do not think that anyone had received it. Why is that?
The report is not normally known as the Weber Shandwick report, which might explain why people have not heard of that. Weber Shandwick acts as a consultant to TIE. We asked the company to prepare the report, which was passed to City of Edinburgh Council, where it came before the planning committee at a meeting on 2 October. The papers for such meetings are made public in advance and the report mentioned the consultation process and its outcome.
Do the answers that the witnesses gave me just reflect confusion about the report's title? Are you saying that everybody has received a copy of the report—or heard of it—but that it has a different name?
There might be confusion. I cannot say whether the witnesses have seen the report. The report is quite large and we certainly did not distribute it to everyone along the route. However, the report was made to City of Edinburgh Council and the papers are publicly available. Indeed, there was a press release in advance of the planning committee meeting, to make people aware of the report.
For future reference, when the committee is taking evidence, how should I refer to the report to ensure that I receive answers to my questions?
I suggest that you refer to it as the consultation report that was produced for TIE and City of Edinburgh Council at the conclusion of the process.
That is snappy.
During the consultation, you put questions to City of Edinburgh Council's citizens panel and to focus groups. What did you ask and why did you think that those groups were the most appropriate groups to consult?
Lesley Clark might be able to help me on the detail of the questions. I presume that you are referring to the early meetings. We recognised that we needed to consult, for example, transport and disability groups and groups that represented heritage or environmental interests. We were aware of a number of groups in those sectors as a result of previous consultations on aspects of the tram scheme and other transport or planning projects, so we knew which kinds of organisations would be interested in the scheme.
You answered my question about how you considered the comments that were made, but I am still not clear about your response to Alasdair Morgan's question. When the route of the line was moved after consultation in a certain area, what was the process for consulting on the revised route? I think that the convener referred to moving the goalposts; I refer to moving the tramline.
For some of the locations further up the line—setting aside the Haymarket rerouting—the revised route remained within the interested parties' land boundaries. Those parties became aware of the changes through our consultations with them. When I gave a list of examples, I did not mention the route options around the airport and the Royal Highland showground, which were shown on the line 2 leaflet. The route in those areas changed significantly, but both parties were aware of the changes. There was no need for further consultation, because we were speaking to the parties.
If you had felt that there was a need for consultation, what process was in place?
We had had on-going discussions with some of those parties. For example, Edinburgh airport is a main destination of line 2, so we had already engaged in discussion with the airport management and with the management of the Royal Highland showground and had a contact mechanism set up to speak to them.
I congratulate Weber Shandwick on the PR award for its work on the project. What discussions did you have with the Scottish Executive on good practice for consultation?
We drew on a number of different areas to put together what we felt was the best form of consultation for the project. There are obviously guidelines, but it was more a case of speaking to the City of Edinburgh Council officers who work on public consultations and drawing from our experience of which methods of consultation and types of materials tend to reach the most people and be most effective. We were keen to ensure that it was an integrated consultation so that if somebody missed one of the tools that we used, they would pick up another. So, for example, if somebody did not see something in the Edinburgh Evening News, they might have heard about the consultation on the radio or have come across an exhibition or a public meeting. We strove to ensure that as many people as possible could be involved and that it was easy for them to be involved.
Did you have discussions with the Scottish Executive on the conduct of the consultation?
Yes. You may be aware that the Scottish Executive produced guidance on how to appraise the whole of a transport system. It is called the Scottish transport appraisal guidance, or STAG, as you may have heard it referred to. Part of that guidance is on public consultation, on which the Executive set out guidelines that suggest that the consulting body should make stakeholders aware of the study. That is what our integrated approach, to which Lesley Clark referred, did. It ensured that all stakeholders had the opportunity to put their views to the team, and we achieved that by using as many ways as possible for comments to be received. The guidance also suggests that we should ensure that the consultation and participation process is as inclusive as possible which, given the broad nature of the media that we used, we also did.
We have received evidence on one of the public meetings. If you have the promoter's memorandum available, perhaps you will let me tie it up with the evidence. We have been told that a week's notice was given before the public meeting at Saughtonhall United Reformed Church was held on a Friday evening at 6 o'clock, but I do not know the date of that meeting, so I do not know whether it was one of the seven public meetings mentioned in paragraph 28 of the promoter's memorandum.
That meeting was on 19 September and was held in response to the comments that were received at the initial, scheduled public meeting to which Jacky McKinney referred. Because some of the leaflets had apparently not been received, some people were not aware of the initial meeting, so we arranged the extra meeting to ensure that they had a fair chance of their say.
Are you satisfied that a week's notice was sufficient for that?
Yes. That meeting had the largest turnout of any of the public meetings.
You say that you had that meeting in response to claims that leaflets had not been delivered. What procedures and mechanisms did you have in place to investigate why the leaflets were not delivered in the first place? You mentioned back-checking.
The company that we use to deliver the leaflets to households and businesses gives us an average drop that it thinks that it will achieve, which is around 78 per cent. Throughout the process and to give us some confidence that it has been out delivering our leaflets, the company back-checks streets that it has been to. By back-checking, I mean that workers knock on doors and ask people whether they have seen the leaflet and whether they would mind signing to say that they have received it. We have done extensive back-checking throughout the consultations for both of the lines, but particularly in the area that we have mentioned today. When the back-checking showed that there were gaps, we asked the company to releaflet. In one case, the Weber Shandwick team also releafleted.
You mentioned that 45,000 leaflets were distributed. How many did you have to backfill?
I do not have the figures on me. We sent out 34,000 leaflets through the company. I estimate that we had to backfill 20 or 30 streets.
Streets can be as long as a piece of string.
I would need to check the figures.
I am not a techie, but I think that hits on the website are quite different from page impressions, which might give us a better idea of how many people have used your website. It might be useful if you could provide that information to the committee. How much did TIE spend on consultation?
We will have to come back to the committee with an answer to that question.
It would be helpful if you could provide that information to date.
It is not part of the same contract, but it is part of the same approach. The consultation that you mentioned referred to a broad package of measures, one element of which was the tram scheme. The consultation that we have undertaken is appropriate to the size of that project. There will be a similar but slightly different type of consultation, as appropriate, on some of the other projects in the package.
I am aware that elements of the agreement may be confidential, as you have sought to indicate, but Weber Shandwick is also a public affairs company. Within the overall work, is there a brief to garner support for both congestion charging and the transport choices that were presented in the consultation?
I understand that Weber Shandwick's brief is not to garner support but to assist us in the consultation process. That includes setting the tram scheme in the context of the broader package and showing where it fits in.
So none of the meetings that Weber Shandwick or others arranged between TIE and councillors, MPs, MSPs or community councils was intended to garner support for the choices programme and the tramlines. Were the meetings designed purely to provide information?
Yes.
Are you certain about that?
I am as certain as I can be.
TIE gave presentations on the trams and the status of the tram programme.
Was none of that work designed to gain support for congestion charging and the associated initiatives that could be funded from it?
There are no representatives of Weber Shandwick public affairs here, so I will speak for it. The meetings that it set up were intended specifically to allow TIE to speak about the tram project and to provide MSPs with enough information to allow them to pass on information to their constituents and to answer questions about the project.
So the public affairs side was not taken on to gain support for the initiative.
No. That is not to say that if the issue were raised at a public meeting, we would not have given an opinion on it. The issue was raised at some public meetings. However, you asked directly whether it was part of Weber Shandwick's brief to garner support for the project and the answer to that question is no.
Do you see that there is a potential conflict of interest when an organisation is carrying out consultation on a specific initiative and is paid directly by the initiative's promoter?
No.
Okay.
I will go back to the question that Jeremy Purvis asked about leaflets. As far as I am concerned, the most important part of consultation is initially informing people that something is going to happen. That gives them the maximum time and the maximum opportunity to make their views known and to have an impact. I understand that when leaflets are being delivered by a company it can guarantee only that a certain amount will be delivered; I suspect that if the company says 78 per cent, the actual figure might fall short of that.
No, there were not different levels of consultation of the sort that you describe. However, as we saw it, the consultation did not come down just to leaflets. On the first day of the consultation, the Edinburgh Evening News carried a double-page spread that provided all the information that was in the leaflet and more, plus the dates and times of all the relevant public meetings and so on that people could attend.
Somebody who might lose half their garden and does not or cannot watch the television or read a leaflet could be sitting in their house. Was any thought given to how people who have a sensory impairment could be informed? Usually if people are posted something, that is a way of ensuring that they are able to get the information. It strikes me that not enough effort was made to ensure that people who will be directly affected by the proposals were informed immediately. I know that information being provided on television, in leaflets and in a newspaper can be seen as consulting or informing fully, but a more direct approach to people who will be directly affected could have saved a lot of the criticism that you are now getting and a lot of the suspicion that is contained in some of the objections that we have received.
In response to your point about people who perhaps cannot see a leaflet, the leaflet was available from the council in a number of different formats—including Braille, large print and tape. It was also available in several different languages to ensure that it was available to as many people as possible.
If people knew about the proposals, they would be able to get those leaflets.
Yes, but I would also say that we made a decision that everybody should be treated in the same way and given the same opportunity to respond.
This is an important evidence session. Do any members have any final questions? As there are no more questions I thank the witnesses very much for their attendance.
Meeting continued in private until 12:20.