There is no paper for agenda item 2, which concerns the bill notification arrangements. I want to update the committee on what has happened with the promoter's notification arrangements since our most recent meeting in Newtongrange on 21 March, when the promoter's witnesses appeared before us. At that meeting, the promoter said that the report on the assessment of its referencing process would not be available until 25 April. The clerk has now received that report and has distributed copies of it to members. A copy has also been put on the committee's homepage on the Parliament's website. Given that we did not receive the report until Monday, there has not been adequate time for us to consider it fully.
Further notices have been issued in the light of the referencing assessment by the promoter. Since the committee's most recent meeting on 21 March, about 180 more notices have been issued in two batches, which means in effect that two objection periods are running. The first objection period will conclude on 23 May, but the second will not conclude until Monday 20 June.
Thank you for that. What implications do the further failures to notify and the two objection periods have for our timetable for consideration of the bill?
Given that objectors have until 20 June to lodge objections, it has become virtually, if not totally, impossible to conclude the preliminary stage this side of the summer recess. The committee would need to consider any objections that are lodged up to and including 20 June, so a meeting would have to be held after that date. The committee would then have to write, agree and publish its report and have scheduled the preliminary stage debate in a plenary meeting. Bearing in mind how long the preliminary stage has taken, to squeeze all that into the short period that is available would not do justice to everybody, nor would it allow proper consideration of all the evidence. As a regrettable consequence, it seems that it is inevitable that the preliminary stage debate will have to be deferred until at least September.
What happens in that 12 to 14 week period?
The Edinburgh Tram (Line One) Bill Committee and the Edinburgh Tram (Line Two) Bill Committee are going through the process at the moment. The objectors will be invited to prepare and give evidence to the committee in support of their objections. If the committee chooses to take the same approach that the tram bill committees have taken, the process will become front-loaded on paper. First, there will be identification of the objectors. We could ask the committee to consider grouping objectors who have similar objections and who perhaps live in the same locality. Thereafter, the objectors will have to be briefed on how they will interact with the committee.
Will you remind me of the number of objections? What was the initial number of objections and how many subsequent objections have come to light during our evidence taking?
The original number of objections, following the original objection period after the bill was introduced, was about 126 or 127—I cannot remember the exact number. The current number of admissible objections is about 124 or 125. That number is the result of some objections having been withdrawn and of the committee's having rejected objections on the ground that no adverse effect was shown by them. The number of notices that have been issued since last September is around the 300 mark. The original 130 or so were issued back in September and 180 or so more have just been issued.
That is on top of the objections that were identified when we started to take evidence in Galashiels. Another 180 have subsequently been identified, which is considerably more than the 126 objections that were originally received back in September.
I referred only to notices that have been served, not to objections that may result from serving those notices. We will have to wait until 23 May and 20 June to see whether the objections actually come in.
Yes.
Do members have any further requests for clarification from the clerks?
I have just one question to ask about the impact of the delays on costings. Will the revision of the costings form part of the evidence that we receive, and will we ask the Executive what impact that will have on its capital investment plans?
It is a bit early to assess that. We will have some discussion with the promoter to see whether there is any significance in the delay; the net delay may not be as bad as I indicated. On the basis that the bill will proceed, my estimate—given a fair wind from now on—is that the net delay might be no more than a month or two from where we were before the recent batch of notices was served.
Okay—although you accept that members see the delays that we have experienced as perhaps being evidence of a lack of efficiency that might lead us to undertake much more detailed scrutiny of other aspects of the promoter's case.
Absolutely.
The committee could, under its next agenda item, in thinking about topics and witnesses, consider whether it wants to seek further reassurances from the Executive—as it did on 14 March—regarding the impact of the delays on the overall cost of the project.
That might be helpful.
The committee might alert the Executive in order to ensure that the Executive is aware of what is going on in the process.
I thank the clerks for giving the committee that clarification, and I invite comments from members in response to it.
I reiterate what I said previously. Frankly, I find it breathtaking that at this late stage we have found another 180 notices. Given what we have been through and what we have heard—including the various explanations, excuses and claims that it is not a perfect science and that we have never been down this road before—I do not think that any of us imagined that we would at the end of April be dealing with another 180 notices or objections. I cannot fathom how this situation can have arisen.
I share Ted Brocklebank's view. How many times do we have to say this? This amount of non-notification of people of what is a very important project indicates breathtaking incompetence of the highest order. The people of the Borders and Midlothian seem, for the most part, to want the project to go ahead, and we are all trying to do our best to come up with an answer, but we seem to be battling continually against the promoter's incompetence. There have been many delays to the project and I am disappointed that we do not seem to have any alternative but to allow the process to go on beyond the summer recess. That is highly disappointing for the people in the Borders and for members of the committee.
I do not disagree with any of what Margaret Smith has said. Today feels like groundhog day, because we have made the same comments at almost every meeting. The situation is disappointing. As far as I am concerned, many questions remain about how the project, especially the housing elements, will be supported. If I were asked today whether we as a committee could make a recommendation to Parliament on the bill, I would say that we could not; it is extremely disappointing that we will not be in a position to do so until September. However, if we are to do our duty by the project's supporters and objectors and keep in mind Scotland's interests, we have little choice but to accept what we have been told by the clerk and legal advisers: we will need to put up with the delay.
I add my voice to those of my colleagues in expressing disappointment about the position in which we have yet again been placed. Despite the evidence sessions in which we expressed our concern to the parliamentary agent for John Kennedy & Co, and despite the assurances that we have received all along, we now find that there have been another 180 failures to notify. I am sure that we will call the parliamentary agent to our next meeting, not least to ask about the memorandum that has been sent to us. I share members' concern and disquiet about the further delay.
Meeting continued in private until 11:43.