Item 4 is the first evidence-taking session in the committee's inquiry into the rail industry in Scotland. To aid us with the inquiry, I welcome Gary Backler, executive director of regional networks, and Graham Sibery, director of regional networks (north), from the Strategic Rail Authority; Michael Beswick, director of infrastructure regulation at the Office of the Rail Regulator; and Richard Clifton, director of the directorate of railway policy, and Gerald Kerr, principal inspector, both from the Health and Safety Executive.
I will set out briefly the SRA's role in the rail industry. The SRA was set up by the Transport Act 2000, which set out the authority's three purposes: to promote the use of the railway network for passengers and freight; to secure the development of the railway network; and to contribute to the development of an integrated transport system for passengers and freight.
The regulator's role is the regulation of the monopoly and dominant elements in the railway industry, particularly Railtrack. The key jurisdictions are: setting Railtrack's charges; monitoring delivery of Railtrack's outputs and other licence obligations; Railtrack's relationship with its customers; access to the network for train operators; and appeals on matters such as timetabling and standards. The regulator's focus is very much on the sustained network. It is an appeal body for enhancement but it is up to funders to negotiate enhancements with Railtrack.
It might help the committee if I explain that the Health and Safety Executive—together with the Health and Safety Commission—is the safety regulator for the rail industry in Great Britain. We regulate health and safety at work for the railway industry. That responsibility covers the health, safety and welfare of passengers, workers and the public.
I advise witnesses that we tend to address groups of questions to specific organisations, but some questions might overlap. If you have something to contribute, I will try to draw you into the discussion.
Excluding the ScotRail replacement franchise, how much SRA funding is expected to be available for Scottish rail infrastructure improvements over the next five to 10 years? How will allocations to particular projects be determined? How do the present status of Scottish projects and their expected completion dates compare with the lists included in the SRA strategic plan?
There is an envelope of funding available to the SRA to deliver the 10-year plan targets. The strategic plan is structured around that envelope, and specifically against those targets. Within that, the funding is allocated to a mix of franchise support payments and to projects. It is drawn down against those factors across the rail network.
There is a wide range of Scottish projects. For example, the IOS projects are provided for in the existing control period and should be completed by 2006. Other individual projects are moving through development stages, so each of them will have a different time scale. For most of them, full funding, final specifications and so on have not been finally committed. They are moving through a design stage, which will get them to the point of final decisions. We will be happy to follow up any specific questions that the member has.
You say that the projects that are included in the IOS until 2006 are committed. Will the fact that Railtrack is in administration cause any difficulties in delivering those projects?
No. The projects are funded with a fixed price. The issues around a few of the more involved IOS projects are about securing matters such as signalling design resource, but all the projects should be progressing. The list of stations and projects that was in existence before Railtrack went into administration is still in existence. It is business as usual.
Could you tell me what IOS means, please?
I am sorry. It stands for incremental output statement. Essentially, the concept relates to relatively short to medium-term improvements that are enabled through the regulatory settlement, which would otherwise not have happened, including about 100 track and signalling schemes across the network, of which about 22 are in Scotland. IOS projects also include about 140 stations that are being given what is increasingly given the label of "modern facilities".
You talked about an envelope of funding. Could you give us a little bit more detail on that? How much is it? What are the sources?
There was an initial figure of about £60 billion, comprising a mix of private sector and Government funding. The Government's part of that was increased by about £3 billion when the strategic plan was issued. That means that slightly more than half comes from the Government and slightly less than half comes from the private sector.
How much of that will be spent in Scotland?
As Graham Sibery indicated, at one level, the money is linked to specific schemes. We have built up a general view of the funding requirement for the whole of the rail network in Britain, based on assumptions, with sensitivity analyses attached, about funding requirements for subsidies for particular franchises.
So you cannot give me a ballpark figure for how much of that is allocated specifically to Scotland?
The money is not allocated on a specific basis like that. For example, a large element of the funding is for support payments and franchise subsidy payments, which are built up at a network level. The true subsidy level for an individual franchise will be determined by a competitive process, so it is difficult to be specific about a figure for any individual franchise—in this case, for the ScotRail franchise.
When will that become clearer?
That relates to the franchise replacement process. We are working with the Scottish Executive and will be involving Strathclyde Passenger Transport Executive in developing the specification for the rail services, particularly passenger rail services, that Scotland wants. We will put that specification to the market and run the process to get the services delivered over the time frame of the franchise.
How much private funding does the Strategic Rail Authority anticipate can be levered into Scottish rail infrastructure projects through public funding?
As I said, we are looking for a general mix of public and private sector funding. We remain optimistic about the scope for getting private sector funding through the franchise, but I cannot specify a figure because the funding is not built up in that way.
How optimistic are you about getting private funding into Railtrack?
We recently signed a 20-year franchise agreement with Chiltern Railways south of the border, which has significant private sector resources both for infrastructure upgrades and for rolling stock enhancements. We see no reason why such agreements cannot read across to Scottish services. In fact, we believe that there are many positive reasons why such agreements will read across.
Do you have any views on the directions and guidance for the ScotRail replacement franchise in advance of the Scottish Executive issuing the draft guidance on such matters as fares and service levels?
At the moment, we are discussing with the Scottish Executive the nature of the directions and guidance that it might want to issue. We see it as a two-stage process. There are the directions and guidance to us and then there is the franchise proposition that we put to the market to get priced. Our view at this stage is that the directions and guidance should probably be more general, to allow a clear framework. The detail of what the Scottish Executive, the passenger transport executives and all the stakeholders want for their passenger services—on issues such as fares, regulation and service frequencies—is probably best placed in the franchise proposition.
Most of the stations are leased under the present franchise. How will issues around how stations are run, whether they have left-luggage facilities and disabled access improvements mesh with the new franchise discussions?
Those issues would be addressed in the franchise specification, through schedules attached to the main contract. There is a schedule about station standards. The issues could be specified in the schedule and performance could be managed and monitored against that.
We are going ahead with the franchise on the assumption that all the stations will continue to be leased by the franchisee.
Essentially, yes. We are not proposing to change the structure of the franchise or the roles of the various parties in the franchise. We have considered the matter south of the border. We have attempted to lock parties into major infrastructure enhancements but it has proved difficult to do. It is mainly an issue of risk. From the market perspective, it is risky enough to price against a franchise proposition that will be good for 15 years. Getting parties to be firm about investment projects has proved difficult. We see the basic structure of the franchise remaining similar to the structure that is in place now, although obviously the requirements that are written in will reflect the particular aspirations and requirements of the Scottish Executive and the other parties.
Do you have a view on the notion of vertical integration, particularly when we are talking about the replacement ScotRail franchise taking over responsibility for track and stations?
In general, the SRA's view on vertical integration is that the priority should be stabilising the network and working to improve its performance, rather than undertaking structural reform. Fundamental structural reform would, to an extent, be a distraction from what passengers and freight operators are looking for, which is a reliable network. We are much more focused on that than we are on the issue of vertical integration.
Do the virtual boards encompass the train operating companies and those who are responsible for the track, signalling and safety? Do they include all the main players?
They do. From a train operating perspective, that links to the previous question. Although the ScotRail franchise accounts for more than 90 per cent of passenger services in Scotland, other passenger operators and freight operators are involved. They are represented on the virtual board along with Railtrack, the regulator and the other main parties.
Okay. I can visualise the concept of the virtual boards—I understand where you are going with that. What progress do you hope the virtual boards might make in the medium to longer term? Do you have in mind a pooling of budgets and investment or joint development of policy and practice? What initiatives do you hope will result from the potential success of the virtual boards?
It is early days. The virtual board for Scotland met for the first time last week. The main focus, certainly in the short term, is on improving performance. We anticipate that addressing performance will be the main thrust for a year or two. That is a key priority for the Strategic Rail Authority and for customers. Beyond that, progress will depend to an extent on what issues emerge, apart from performance, and on how the process develops.
I want to press a little further. I presume that virtual boards are in operation elsewhere in the United Kingdom. The first meeting of the virtual board for Scotland has only just taken place and I assume that the other virtual boards are a little further on in their work. You say that the first target of the Scottish virtual board will be to improve performance. Will you give us concrete examples of ways in which the boards might work co-operatively to do that?
The virtual board for Scotland is one of the earlier virtual boards. Scotland is one of the first places where the concept is being piloted. The other early virtual board is the Great Western virtual board, which has met twice. The concept is in its early stages across the network. My colleague Graham Sibery can talk about last week's virtual board meeting, because he attended it. One of the main items on the agenda was the number of temporary speed restrictions on the network and the effect that those restrictions have on performance. Ways of removing or mitigating the effects of the speed restrictions were also discussed. That is a specific example of what the board is working on.
A speed restriction at Dolphingstone on the east coast main line is causing significant difficulty. Members may be aware that mining subsidence in adjacent fields has had a significant impact in that area. Railtrack has rightly imposed a substantial speed restriction for safety reasons. There is an issue about planning to do the necessary work, which will be a large engineering project. The virtual board has no contractual status. Its purpose is to get the relevant people in the same room; to get them to agree on the issues, the main focus and how to progress the work; and to help them to ensure that the work takes place without any contractual spats getting in the way. Purposeful co-operation is the thrust of the virtual boards. The Scottish virtual board has got off to a good start.
How do the processes work if a community wants an improved service? How does that community go about feeding into the tendering process? Do you consult communities about what they would like to be included in the tender? For example, the Caledonian MacBrayne tender was put out to consultation and when the draft specification is produced it, too, will go out for comment. How do you assess what should be included in the tender? What criteria do you use?
Mechanisms are in place and funding is available to enable individual, local schemes to go ahead. I am referring to the rail passenger partnership, which, in the 10-year plan funding envelope, has £400 million allocated to it across the whole network. Several schemes have been bid for and implemented through the partnership. If communities want specific schemes to be developed, they should not have to wait for the franchise replacement process to progress those schemes. The mechanism has existed for the past two or three years and we are still accepting and processing applications. There is funding and a mechanism to meet local needs.
Yes, but it would be different if a community wanted a scheme that impinged on services elsewhere.
The Executive carried out major consultation on aspirations for Scotland's passenger railway. I expect that the responses to that consultation will inform the directions and guidance that the SRA produces.
The consultation processes that the Scottish Executive chooses to adopt are obviously a matter for the Scottish Executive. It may be necessary to refresh the changes, but I understand that the consultation process was thorough and should form the basis of an informed proposition.
Can I take you back to vertical integration? We seem to be jumping backwards and forwards. What evidence did the SRA have, over the past two years, of virtual chaos in our rail network? On what evidence did it base its decision not to look more closely at vertical integration, to which Scotland seems especially geographically suited? The SRA has opted for virtual boards. If they prove to be a vehicle for ensuring that all the work happens—essentially a virtual vertical integration—would you recommend, two or three years down the line, that there is a full-scale move towards that system?
You refer to virtual chaos. The key issue for users of the network—freight shippers as well as passengers—is the way in which the network performs. When they want to make a journey or send freight, the train should go when it is supposed to go and it should get to where it is supposed to get to. We maintain that that is the real priority. The structure of the industry is a lot less interesting to passengers and freight shippers than the performance that the industry delivers. We have taken a view of what the priorities should be, which we think are performance and getting the network to do what it is supposed to do. That is what we are funding it to do.
How will rail track and signalling enhancements be achieved in Scotland? Since privatisation, there appears to have been a lack of training infrastructure for specialist engineers such as signalling design engineers. How will you tackle the problem of skills shortages in the industry?
In answer to your first question, a number of schemes are already being developed and firmed up, as Graham Sibery has pointed out. The outcome of that development and design work will shape the mechanism that is used to deliver the schemes. We are considering a range of mechanisms. For example, we have examined whether the franchise operator could take some stake in the funding of schemes and we are looking at the concept of special purpose vehicles, in which multiple investors come together to work up a scheme and then hand it over. Our choice of mechanism will depend on the nature of the particular scheme.
We have had one or two problems with projects in Scotland. I am thinking in particular of the Larkhall to Milngavie line, where the likes of Railtrack fell out of the picture. You are obviously aware of such problems, but how can we avoid them?
Each problem has its own story. With Larkhall, we had an early national case that allowed us to get the bottom of some of the performance benchmark issues that are still a problem for several schemes. However, we have made proposals about the Larkhall to Milngavie line through the Office of the Rail Regulator and are currently working through them. I think that we will reach a solution.
I should add that we have also announced a national rail academy, which is intended to lead the process of addressing a range of skills shortages in the industry. You have rightly identified signalling and engineering as a key area in that respect, although there is a range of skills shortages. The SRA intends to take a co-ordinated view of those shortages and of the mechanisms for addressing them. We see that as part of the task of getting the network performing and delivering what we are paying it to do and what users—passengers and freight operators—want. The national rail academy, which was announced in the strategic plan, is intended to address precisely the shortages to which you refer.
Will the academy have a Scottish division? Will it be based in one location or will there be delivery from a number of points?
The concept is being developed at the moment. So far the main focus has been on identifying the skills shortages that we face—an integrated view of those shortages has yet to be taken across the industry. When we have identified priority needs more clearly, we will be able to devise mechanisms for addressing them. It is not yet clear whether that will mean the establishment of one or more institutions. The concept is still at a formative stage.
I ask Adam Ingram to restrict himself to one more question, as I would like to move on to other areas of questioning.
There is a problem with the capacity of rail freight in Scotland. Recently, the ORR cut rail freight track access charges by 50 per cent. Does that have a cost implication for the SRA with respect to rail freight in Scotland? Is it sufficient to meet the SRA target of an 80 per cent increase in rail freight in 10 years or must we consider other measures?
We aim to hit the target of 80 per cent across the industry. It is important that we get the network to perform in such a way that it is possible to achieve that. The increase will be delivered by tackling the competing road freight market, which offers a high level of service. It is therefore essential that the rail network also performs to a high level.
At issue was simply whether we should allocate part of the common costs of the passenger and freight railway to freight. We discussed the matter with the SRA and agreed not to do that. Instead, the SRA indicated that it would pick up the common costs of the railway as part of the costs of the passenger railway. That meant that the costs to freight were halved.
Our second area of questioning relates mainly to the role of the ORR.
What are the variations in track access charges between different areas of Scotland and between Scotland and England? How are those variations arrived at? Can you supply us with a model or framework that makes sense of the current arrangements?
We have set access charges for five years—to 2006. We did that by working out the total cost of operating, maintaining and renewing the network over that five-year period. We also allowed for the significant efficiency savings that we believed Railtrack could achieve and for a fair return on capital investment. From our analysis, we concluded that Railtrack needed £15.9 billion, at current prices, to operate, maintain and renew the network up to 2006. That amount is split into £4.4 billion for operating, £3.3 billion for maintenance and £8.2 billion for renewals. The SRA said that it wanted to pay £4.9 billion of the £15.9 billion directly in network grants to Railtrack. After various adjustments in relation to property and freight, we concluded that £9.5 billion in access charges must be raised.
You did not comment on the differences between Scotland and England.
We did not carry out an exercise to discover what the railway in Scotland will cost and what it will cost in England. We took a figure for Great Britain and then allocated it essentially on the basis of the vehicle miles that are run in each area. As I said, we also took out of the calculation the large sum of money that was paid through the SRA network grants.
As I understand it, you made no weighting for sparsity of population in relation to track miles, although that obviously has an impact on profitability.
We considered the matter carefully and consulted on it. We believe that we found the best measure of the long-term cost allocation. If one examines Railtrack's network management statement for last year, one will see that its spending plans for Scotland involve around £400 million for maintenance and £900 million for renewal in the five years. That is £1.3 billion, which is a lot more than ScotRail pays in access charges, although a bit must be added for Great North Eastern Railway and Virgin Trains. Railtrack spends large amounts of money on the network in Scotland.
Is it possible to provide us with a model that will help us to understand the mechanism? The bottom line of the scheme seems to be what you think Railtrack will cost, from which the allocation of charges is worked out. From a regulatory point of view, surely there must be a better way of determining the charges.
In principle, it would be possible at a future review to use a different mechanism, which would begin by identifying the costs that are incurred in Scotland. Effectively, there would be a periodic review for Scotland and one for England. We would want to discuss such a system with the Scottish Executive, the Parliament and the SRA; it would be important that the funders were happy with it.
In many ways, the mechanism for allocating costs is not unlike the local government finance distribution mechanism in Scotland, with which no one is entirely happy, which no one entirely understands and which we review annually—or perhaps slightly less frequently—without coming to a particularly satisfactory conclusion. It is like the pursuit of the holy grail.
There was significant transparency at the time of the review, and we consulted extensively about how we should go about things. We suggested that, as a large chunk of fixed costs had somehow to be allocated, there should be different ways of doing that. In the light of the consultation, particularly of the views of the then franchising director, we took the view that it would be best to allocate the franchises on a long-term basis and that vehicle miles were the best available measure to use.
When was that?
The review took place during 1999-2000.
Could you explain in detail your reforms of the performance regime, dealing in particular with the concerns that people have expressed about the system of fines and incentives for punctuality, which seem to have been highlighted under the performance regime. Are we ending up with a Soviet-style system, under which things are driven towards performance and other relevant measures? It is all very well having a punctual rail service in Scotland but, if the trains are moving at only a snail's pace, that is not effective from the customers' point of view.
In the real world of operating a railway, train operators are faced with the fact that their revenues depend on their performance. Therefore, it seems fair that the revenue effect that is caused by poor performance by Railtrack should go from the operator through to Railtrack. The reality is that, if an operator performs poorly, it loses income, as has been the case post Hatfield.
I have some concerns about the performance not only of Railtrack but of the operators. That question should be addressed in the franchise.
The charges are fixed until the next review. There is a process for what is called an interim review, if holding such a review were felt to be appropriate. There has been a lot of discussion about whether a review should be held, given Railtrack's current situation. We want to get a better handle on Railtrack's efficient costs and continually to improve our knowledge of them. We also want to improve our knowledge of the extent to which track access charges could better reflect the costs on the network. It always grates that 80 per cent of those costs are fixed, which might not give out the right incentives. For example, on the freight side, we are working on encouraging track-friendly suspensions. That will give us a better understanding of how to incentivise the use of trains that do not do too much damage to the track, rather than vehicles that cause more damage.
I have a couple of supplementary questions, the first of which goes back to the performance regime and enhancements to the network. I do not expect you to be able to provide details in response to the example that I will give, but I want to highlight the problem. There is a proposal to develop a new station at Edinburgh Park on the outskirts of Edinburgh. From my discussions with many of the people who are involved in that proposal, I have learned of the problems that Railtrack has identified with a potential performance risk in the order of £1 million to £1.5 million to which it will be subject if the proposal goes ahead. That risk could act as a blockage to the development of the station. I want to ask the witnesses from the ORR and the SRA what can be done about a potential blockage around the performance regime when a project has widespread support and funding is in place for it.
It is important to understand the performance effects of new projects. It would be silly to implement a new project on a wing and a prayer without considering performance. It is important that proper analysis is undertaken, that realistic figures are generated and that proper modelling is carried out. Then the question of money arises. The reality is that performance regimes are a means to an end—they are about getting a better railway. If the performance regime creates perverse effects, because Railtrack is paying out a lot of money and therefore will not invest in new projects, it is important that we find ways of examining that regime. For example, we have suggested pragmatic solutions in the case of Larkhall and, with Edinburgh Park, we want to work on finding such pragmatic solutions. That may involve changing the parameters of the performance regime in order to reflect the circumstances.
I have a couple of examples of how passenger services were delivered unsatisfactorily by GNER in Scotland. After the Hatfield accident, GNER needed diesel rolling stock for its loop, so it withdrew the service north of Edinburgh. Recently, it has withdrawn the service north of Edinburgh because of delays down south. Is GNER penalised for that? Does it have to ask for permission to do that? Why is GNER allowed to do that when it has guaranteed a service to Aberdeen?
Passenger services that are run by train operators are a matter for the SRA.
Yes. GNER discussed with us the alternative services that it wished to put in place in the event of major incidents, such as the two cases to which Nora Radcliffe referred. It is regrettable that both incidents occurred in similar places on the network and therefore had the same knock-on consequences for GNER.
GNER has chosen to react to those incidents in a certain way.
Yes, but given the rolling stock that it has on lease, its options are limited. We have stressed—we hope it has been achieved—that GNER and ScotRail, the two franchised operators, should co-operate. We also encouraged changes to the ScotRail pattern of services so that journey frequencies and available rolling stock could fill the gaps that might be left because of the way in which GNER responds to major incidents.
Do you monitor how effective those compensatory mechanisms are? Why should ScotRail have extra rolling stock to pick up the slack when it did not have it previously?
We monitor the operators individually and together, and we monitor the effectiveness of the responses. We encourage the operators to consult locally before they put contingency plans in place, in order to ensure that the plans are effective. We then review with them how effective those plans were. The plans evolve.
Do you think that the priorities might be slightly different if the SRA had a Scottish division that was responsible to the Scottish Executive?
I have two comments about that question. We have recently opened a Scottish office so that there is a presence in Scotland that works directly with Scotland's interests and ensures that they are related to the rest of the network. Secondly, after the current franchise expires in 2004, the new franchise will be specified locally by Scottish interests and it will be funded by Scotland. Given those changes, the management of that franchise will be more locally responsive than you might believe the current one is.
I would like to make some progress. We will move on to questions for the Health and Safety Executive.
My first question is on travelling safety. It is recognised that rail passenger safety has increased decade on decade since the 1950s. In view of that, is there a risk that setting even higher standards for rail safety might compromise overall safety? New safety mechanisms might necessitate higher fares, which might lead to an increase in car travel, which is a less safe mode of transport. Would public funds be better spent on things such as accelerating rail service enhancements, and accelerating small-scale but effective road safety measures, rather than on rail safety improvements?
I acknowledge the points about the safety of rail transport compared to other forms of transport. We are, of course, meeting in the immediate aftermath of the tragic railway accident at Potters Bar. Our objective is to try to ensure that we have safe railways and to encourage the duty holders to fulfil their responsibilities to achieve adequate and acceptable levels of safety on the railways. The public has high expectations of safety on the railways.
This question is rather more specific and it links in with Bristow Muldoon's question on Edinburgh Park. Given the low population density and light traffic on several Scottish rail routes, is the HSE willing to introduce greater flexibility in deciding on appropriate safety standards for Scottish conditions? The opening of Beauly station was delayed for six months because of safety concerns that were not raised when the short-platform station was first proposed. Can similar situations be avoided?
Our general view is that acceptable safety standards, and railway group safety standards, must be complied with. We are receptive to situations in which precise adherence to a particular safety standard is not practicable because of particular circumstances.
It is true that rail travel has increased dramatically. The landscape now is totally different to that which we had some years ago.
My final question might lead into questions that other people—particularly Fiona McLeod—might like to ask. Would you like to make general comments on problems that are caused by the present system of subcontracting maintenance work?
The Health and Safety Executive believes that one of the strengths that we bring to the regulation of safety on the railways is experience of regulating safety throughout British industry. Subcontracting is a fact of life in every industry. Subcontracting of processes creates additional safety problems and risks, because it involves additional interfaces and might involve questions about whether the right information has been given to the subcontractors. However, it is not true that that means that risks cannot be properly controlled. It is clear that they can be properly controlled, but that involves additional challenges to the duty holders to ensure that a safe system of work is in place and is followed.
Do you always reassess safety priorities? You mentioned unmanned level crossings that were considered safe in the past but which now, perhaps because of population changes, require re-examination. Sometimes, safety priorities seem a bit out of kilter. People thought that the Beauly station episode was amusing—the station's opening could not be advertised in case too many people turned up for it, which would prevent the station from opening. People were concerned not so much about the shortness of the platform as about the danger of that railway line where it runs through a housing scheme in Inverness and is not properly fenced off. Important issues sometimes seem to get pushed into the background; but perhaps that is a perception rather than reality.
Like any organisation, we have internal mechanisms to review priorities. We have an annual planning process. When there is a major accident—as there has been recently—people ask us serious questions about our priorities. At other times, people pick up on particular safety concerns that we have and tell us that we are being picky and difficult and that we attach disproportionate importance to some issues. Our organisation's aim is to ensure that in society there is proper appreciation and management of risk. Our aim is to enable people to manage risk proportionately. We do not seek Rolls-Royce solutions in every circumstance. Our concern is proper appreciation and management of risk on a risk-assessment basis. We review our priorities.
I want to pick up on a few of your earlier comments. You said that last month you went through a process with Railtrack of ensuring a safe system of working with contractors. Has that system changed greatly from the previous one?
I was not part of the team that assessed that safety case, so I cannot answer that question. Perhaps Gerald Kerr can do so.
I was not part of that team, but the overarching aspect is the Health and Safety at Work etc Act 1974. The point is that a safe system of work should always be in place. To pick up on the earlier point about Beauly station, we must remember that by far the greatest number of injuries on the railways are slip-and-trip accidents on station platforms. We must guard against human error. The 1974 act refers to a hierarchy of risk control, so we look for engineering solutions prior to engaging procedures. We have been following that hierarchy for Beauly station.
Can you send the committee information about the new safer system of working with contractors that will show how great the changes are from the previous situation? That information would be useful for us.
I can ask the team that undertook the acceptance stage of the process whether they could write to the committee describing the principal changes in the management of contractors.
On more general matters, is it feasible for the industry to move forward by taking the regulation of safety away from the HSE and giving to the ORR, for example? Is it appropriate for safety to be regulated by someone whose focus is economic regulation rather than health and safety at work?
Lord Cullen undertook an extensive and exhaustive public inquiry after the Ladbroke Grove disaster. He heard a great deal of evidence on the matter to which you referred. His report endorsed the role of the Health and Safety Executive as the safety regulator for the railway industry.
On that—
Will you please be brief, Fiona?
Yes. How will the rail accident investigation board work alongside the HSE?
There are similar models in the aviation and marine sectors and I expect that the relationship in the railways will work in much the same way. However, it will need close attention and the presence of agreements between the different organisations. If a major rail accident occurs, the railway accident investigation body will take priority in terms of accident investigation. That body will conduct an investigation with the aim of finding out what went wrong in order to learn lessons and provide answers.
I have one final, specific question, convener.
Okay.
I understand that the SRA favours the European rail traffic management system. Does the HSE agree that that system should be put in place as one of the overriding safety systems in the UK rail network?
Gerald Kerr might want to add something about the HSE's attitude towards that. There are automatic train protection systems in parts of the rail network. Following the publication of the Railway Safety Regulations 1999 and the recommendations of the Health and Safety Commission, the train protection and warning system is being introduced throughout the rail network. Through European directives, there is a commitment to introducing the ERTMS—the European rail traffic management system. That is a mandatory requirement of European directives; however, there is a question mark over the timetable for that, and implementation of the system will be relatively slow.
We are working closely with the HSE on the variance of safety schemes and the rate of progress, because it is clear that there are many implications for the rest of the network.
Members have a few more questions to address to you, but we have other items on the agenda. I propose that we put those questions in writing to each of the organisations and gather their responses as part of our evidence. If members have other supplementary questions, the clerks can include those.
Can I ask a question that requires a one-word answer?
Yes, if it will get a one-word answer.
Does the east coast main line terminate at Edinburgh or Aberdeen?
Aberdeen. The franchise services run to Aberdeen.
You have kept Nora Radcliffe happy with that answer. I thank the representatives of the Strategic Rail Authority, the Office of the Rail Regulator and the Health and Safety Executive for their evidence. It has been very useful and has given us a good basis for the inquiry in which we are engaged. I would be obliged if those organisations could respond to the written questions that we will submit to them in due course.
Meeting suspended.
On resuming—
I welcome Janette Anderson, the director of Railtrack Scotland. I am sorry that we are running a little late. I am sure that your evidence will be useful in our rail inquiry. I will give you the opportunity to make some brief remarks before we move to questions.
Thank you for inviting me to address this inquiry into rail. We welcome the inquiry, and the opportunity to give evidence. Before I make my opening statement, I would like to take a moment to reflect on Friday's tragic accident at Potters Bar. Obviously, our thoughts are with all those who were involved. It was a terrible accident, and one for which the whole industry is truly sorry.
Thank you for those opening remarks. All members of the committee echo the sympathy that you expressed to people affected by the Potters Bar accident. I understand why you do not want to go too deeply into the issues surrounding that.
You pre-empted my first question. I intended to ask which enhancements to the Scottish rail network continue to have active Railtrack involvement, and you have given us a comprehensive view of that. Are more projects likely to be added?
The SRA witnesses touched on a few of those projects, which are currently at the stage of incremental output statements. We have been asked to work up nine projects to final cost stage. Most of those projects relate to platform extensions that would allow longer trains to be run. That is a relatively quick and easy way of getting more people on to the railways. An increased, half-hourly service from Glasgow to Kilmarnock is also being promoted.
You may have heard me ask Michael Beswick about the performance regime and how it applies when a new station is opened. You do not have to comment specifically on the project that I mentioned, but how do you think the relationship between Railtrack and the Office of the Rail Regulator works to ensure that the performance regime does not stand in the way of new developments?
We are about to set some precedents with two schemes that are under way. The Larkhall to Milngavie scheme, to which the Scottish Executive has committed £25 million, is at a well-developed stage and will introduce a new service to a congested stretch of railway. Under the current rules, Railtrack will be subject to a performance disbenefit; that is how the money-go-round works. There are various ways of mitigating that. We could set aside the current rules, as the ORR suggested. That has not been done before now, but it would be a great solution. Alternatively, one could put in place performance enhancements, such as more signalling. That would cost money and require the £25 million that has been made available for the project to be increased. The problem is not insurmountable, and we are in discussions with the ORR about it. However, the process is bureaucratic and time consuming.
As a passenger, one of the things that I find irksome is the withdrawal of left-luggage facilities. Will that measure be reviewed?
Two services have been withdrawn—left-luggage facilities and bins, the disappearance of which the member may or may not have noticed. Those are national security issues. I do not decide that there are no longer to be bins or left-luggage lockers at stations. That decision is taken by the Home Office, as part of its responsibility for security throughout the UK. However, we keep an eye on such matters. I appreciate that it is horrendous for members of the travelling public if there is nowhere for them to dispose of a coffee cup or heavy luggage.
That is true, particularly given that neighbouring bus stations do not apply the same rules. It is also possible to find bins just outside station precincts.
I do not make the rules—I just try to comply with them.
Your submission states that Railtrack concentrates scarce resources on essential renewals, and we understand why that is the case. Is there a risk of track access charges that are levied on Scottish operations being diverted to fund schemes in other parts of the UK? Was the intention that track access charges should be available for use in the regions in which the charges arose?
On the danger that Scottish track access charges will be diverted to other parts of the UK, we do not produce sets of accounts for Scotland, as we are not a separate subsidiary. What I am about to say is therefore not publicly available. We are a net loss-making operation. In other words, the amount of money that we spend running, maintaining and enhancing the network in Scotland is in excess of the track access charges.
I want to return to what you said about the Larkhall to Milngavie line. There is concern in Bearsden and Milngavie about the number of trains that go through danger signals at the Westerton junction. Has that situation improved? The single tracking of line there is a bottleneck in the utility of that line and in what we can achieve. For some time, proposals have been in the pipeline for a halt at Allander, which, I understand, single tracking prevents. Three weeks ago, I noticed that a double-track bridge had been replaced by a single-track bridge close to Milngavie. What is Railtrack's view on that? Is a line being built that cannot be used as effectively as it could be if there was proper investment right the way through to Milngavie?
There are two or three issues there. First, you mentioned the Westerton junction. That was a multi-SPAD signal—SPADs are signals passed at danger—that had been passed more than twice in its lifetime. We have done quite a lot of work not only at Westerton, but on a number of multi-SPAD signals in upgrading infrastructure and driver training with ScotRail, which is our key industry partner. Westerton is no longer a multi-SPAD signal and has fallen out of our top 22, so you can rest assured about that. I would be happy to provide exact details of the infrastructure and our work with ScotRail, if that would be of interest.
Before Nora Radcliffe asks another question, I congratulate Des McNulty on his opportunism. I appeal to other members not to make bids for pet projects in their neighbourhoods.
Janette Anderson will know that many rail improvement schemes have been held up by the lack of skilled signalling design engineers. Is Railtrack exploring tapping into outside sources to try to alleviate that shortfall?
Again, I have a few points to make in response to that. Why is there such a lack of signalling resources for enhancement projects? The priorities for signalling resources are, first of all, installing the TPWS throughout the UK, which was recommended following the Paddington disaster, and, secondly, the west coast main line upgrade, which has huge signalling implications. Enhancement projects, which this committee would be keen to have implemented, are fourth in the queue behind those projects and the project to renew existing signalling installations such as those at Edinburgh Waverley and Glasgow central, which are 30 years old.
I promise not to mention any of the Highland lines, as dealing with those would take forever.
A couple of developments that are in progress should help the situation. The Scottish Executive has set out its priorities in relation to the SRA. The bit of the jigsaw that is still missing is clarity around the financing, but I am relieved to see that the Executive's priorities seem to be aligned to the strategic plan. What is not clear is who is holding the cheque book for the schemes. I encourage the committee to seek clarity in relation to the funding mechanism and to find out how the money-go-round between the Scottish Executive and the SRA will underpin the projects. That is unclear to me.
So, you have the money—
We do not have it yet.
Let us pretend. Say that you had the additional finance and the virtual board system, what barriers would there be to the delivery of improvements in a short time scale?
We would have to find pockets of signalling resources and schedule them in an appropriate time frame, so that the key projects—the west coast main line, TPWS and other renewals—were not prejudiced by the enhancements. I do not think that you would expect us to put in enhancements that would jeopardise any of those three projects. It is not beyond the wit of man to do that—we can do it if the financing is sorted out.
So it is necessary to consider the knock-on effect on the rest of the network.
Yes.
What about planning procedures? Are they very time consuming?
It depends on what one wants to build. Rebuilding Edinburgh Waverley, which was subject to a public inquiry and full planning, took a long time. However, in my experience, incremental enhancements, such as loops, sidings and additional signalling, are not a big deal.
Would enhanced powers for the Scottish Executive be helpful in cutting through the problems that you have described?
The only issue that I face in that respect is parliamentary powers to rebuild the east coast main line. I do not know yet whether I need the powers, but I am trying to find out and as far as I am aware the Scottish Executive does not have such a power. Those powers rest with Westminster, but I understand that a bill will be going through during the summer that will confirm that the power to rebuild any bits of railway in Scotland will rest with the Scottish Executive after that time. I have a work in progress issue, which was mentioned earlier, called Dolphingstone, which means that I might need to rebuild a bit of railway. I have discussed that with the Scottish Executive and it has directed me to Westminster.
What do you see as the future role of Railtrack's successor? What are Railtrack's views on the concept of a Scottish Railtrack company limited by guarantee, with separate accounting?
As far as I know, the future of Railtrack will be something called network rail, which is likely to be a company limited by guarantee with an executive board comprising a variety of interest groups. Below that, it is likely that there will be an operating board where the real day-to-day operational responsibility will sit. In terms of accounting, we are not a subsidiary company, but we are a business unit with a profit and loss account and a balance sheet that is audited and then consolidated into the UK-wide accounts. I do not predict a big change in the financial structure and accounting regime.
As somebody who has a great interest in the west Highland line, which obviously depends on the length of the platform at Euston and on rail track going up through England, I think that I agree with you.
That brings us to the end of our questions for Janette Anderson. I thank her very much for her evidence, which has been useful. The information that we have got from all the witnesses this morning will aid the committee extensively in its inquiry.