Official Report 322KB pdf
Good morning. I open the eighth consideration stage meeting of the Waverley Railway (Scotland) Bill Committee. The meeting is our seventh in 2006 and the sixth at which objectors will give oral evidence. I welcome the witnesses, their representatives and members of the public.
I could turn to my lawyer to answer that. If it is the committee's wish that we sharpen up some of those areas, we are open to doing that and will accept your opinion that it is woolly.
That is fine. Perhaps we shall explore those points further.
It is indeed, convener. Perhaps I might deal with that point. First, I should say that there is no intention to be woolly, in the sense of being evasive. The scheme is a colossal project, certainly for the Borders and Midlothian, which do not usually have projects of the size of the Waverley railway project. It will produce a lot of generic issues that will have to be dealt with generically as well as locally.
I do not find the response terribly convincing. The committee has made it clear that we would like the maximum protection to be put in place to reassure the public that work on the project, and the works surrounding it, will be done to the highest standard. Personally, I do not see any difficulty in putting as much detail as possible into the draft code. I fully accept that it will have to be signed off but, as an article of good faith—that is what I think the draft code of construction practice is—we need to see a bit more detail than the promoter is prepared to give at the moment.
I honestly do not think that there is any substantive issue between my client and the committee. It is simply a question of how the promoter can provide you with the assurance that you feel that you need in a way that makes it clear that the draft code will be adjusted to suit, should the need arise. The promoter is not trying to duck and dive, but it is difficult to produce the words in a way that is right for you.
I want to pursue the issue. I hope that you accept that there is an argument for having in part 1 of the draft code as much broad detail as possible. If I were a member of the public living in an area that was likely to be affected, the minimum that I would expect is a 24-hour hotline, no matter who the eventual contractor was. I hope that you accept that part 1 of the draft code is the place where that minimum standard should be set out.
I think that it might be in there.
I am one of the authors of the original document, which, as you will appreciate from reading it, makes reference to an emergency hotline. In answer to previous questions, we have also said that the hotline would be in operation 24 hours a day.
Thank you for reminding me of what is in the document, as I do not have my copy with me. I apologise for that.
I will address the question about the hotline. Local authorities are open all hours nowadays. Winter maintenance is a particular issue. Staff in our offices during the day cover all the phones, but we also have facilities at night. There is winter standby and summer standby. It is surely not beyond the wit of man for us to adjust our systems to suit the 24-hour response time that you are after.
Do you wish to comment on the possibility of having a freephone number?
We certainly do not have freephone numbers at the council's offices. Everybody who phones up tends to have to pay for their call. That tends to stop the hoax calls that can come through, which can be distracting and send our resources off in different directions. However, we can certainly consider the matter.
And the question on 48-hour response—
Earlier, you referred to the period of seven days. I am not sure whether I misunderstood the question, but in our response we mention the period of seven days, which relates to the period within which we will inform the member of the public—or whoever it is that gets in touch with us—of action taken. It does not relate to the time period for actually undertaking that action, which is a lot shorter. That approach will ensure that we get back to the person and fully inform them of what was done as a result of their raising the concern in the first place.
Is that the same as applies to the Edinburgh tramline 1 project, or have I got that period of 48 hours from—
We did not prepare the code of construction practice for the Edinburgh tram.
In that case, I draw your attention to the fact that a response time of 48 hours is being promised for the tram scheme, and I ask that you consider something similar for your code.
I will ensure that we look at that.
Have you looked at the code of construction practice for the Edinburgh tramline 1 project, which is slightly more advanced, to see what you might learn from it and adapt for use in your project?
To be perfectly honest, we have not. We prepare an awful lot of codes of construction practice. The people who prepared the Edinburgh tram code took ours as a model to build on, as our codes have been very successful in the past. Given that this is a unique scheme, and that it is similar to the Edinburgh tram scheme probably in some ways only, we wanted to develop the code in a way that we felt was appropriate to this particular project. Having said that, we would be perfectly happy to revisit the Edinburgh tram code. If it contains anything significantly better that the promoter would be happy with, we could take that on board.
The Edinburgh tramline 1 code will have been adapted as a result of evidence given to the Edinburgh Tram (Line One) Bill Committee. I welcome your undertaking at least to take a look at that code to see whether anything in it could be incorporated in the Waverley code.
I welcome some of the promoter's responses so far. We appreciate the fact that the situation is evolving, but at the same time we are trying to ensure that there is something in front of us at the end of the parliamentary process that is seen as reasonable and can give people some comfort.
In the local projects that we are running with in the Borders—one is not that far away from here, in Galashiels town centre—I believe that there are weekly reports. I would envisage that as a reasonable length of time for regularly reporting progress on how complaints are being dealt with.
What publicity will the log of complaints have and how often will it be updated? Will it be a public document?
It should be updated every time a report, comment or complaint comes in from a member of the public. The local authority or resident engineer staff can raise the issue at progress meetings and, if the contractor is not dealing with it quickly, the resident engineer staff or the local authority can use their influence to try to change the situation. We want to ensure that the public are dealt with fairly and properly.
Will the log of complaints be a public document?
That depends on how it is tied into the contract. Obviously, some of the contract documents between the authorising party and the contractor will be confidential. However, I do not envisage that the log will fall into that category. If a member of the public wanted to have a look at it, we would be open to that.
How will the workmen on the ground be made aware of the code of practice? Will you require contractors and subcontractors to ensure that all their workers are regularly informed about the code?
Potential contractors will not get the work unless they have good quality-assurance systems in place, part of which will be about the training of on-site operatives. The voluntary CCS scheme is a toolkit that is handed out to staff at various levels. In part, that will ensure that staff are aware that the COCP is in place.
Mr McKie, do you have any questions for the panel on the draft code of construction practice?
I have none at this stage but, during lunch, I will discuss the points that the committee has raised, particularly the request to sharpen up the document by reference to minimum standards. If I may, I will report back to the committee orally on that.
Thank you.
I am.
I am.
I am.
Similarly, I ask Mr McKie whether the promoter is content with that arrangement.
The promoter is content.
At our next meeting, I shall ask Gordon Jackson to state on the record that he agrees to the undertaking. I thank the objectors and the promoter for their assistance.
Nathan Edwards took the oath.
Mr McKie, you may invite one of your witnesses to give a brief outline of where matters stand and then you may ask questions of the panel.
First, I confirm that Nathan Edwards is standing in for Sam Oxley, who could not be here today. Nathan Edwards is a fully qualified and chartered member of the Landscape Institute.
In group 61, we have three main objectors. Objection 4 is from Mr Sandie, who resides at 30 Glenfield Crescent, a house that is within about 27m of the proposed route of the railway. The objector is concerned about the proposed height of the railway and its proximity to his home and about the loss of the amenity path, known as the black path, which runs along the length of the former railway through Galashiels.
Can I stop you there, Mr Rutherford? Is it your position, as the promoter, that the information concerning the potential coming of the railway was in the public domain during the critical time from March 2000 onwards?
Yes. The draft structure plan was available from 1998 onwards and, around 1999, there was about a year of consultation on the local transport strategy. I gave evidence on that issue during the preliminary stage.
Are the residents represented by a community council?
They are represented by the Galashiels and Langlee community council.
Is that the community council that you previously indicated was consulted on the project from 1998 onwards?
That is correct. All community councils were consulted.
Thank you. You may proceed.
The third objector in group 61 is Waverley Housing. Its objection was late—the objection was deposited with the committee clerks on 3 June 2005. The promoter met Waverley Housing on 26 September 2005.
Thank you, Mr Rutherford.
The evidence states that there will be tree loss along both sides of the black path. Specifically, there will be tree loss along the residents' side of the black path. Following the construction of the embankment on which the railway will sit, replanting will be possible along the side of that embankment to the toe of the slope.
Is there any potential for mitigatory planting at Glenfield Road East?
A level of planting might be possible at Glenfield Road East. I refer the committee to plan 14. The space available between the existing boundary and the noise barrier that is indicated on the plan is limited, so the planting there would not be as substantial as that in Glenfield Road West, but it would be enough at least to limit views between the properties and the rail line.
Whom would the promoter consult about replacement planting?
The promoter would consult Scottish Natural Heritage to agree which species would be appropriate in this particular location. That is particularly significant because of the proximity to Gala water and the type and level of planting already in this location.
Would it be possible to consult some of the objectors?
Indeed. A detailed landscape design would be required as part of the scheme and, in order to draw that up, the objectors would have to be consulted on the depth of the planting to the rear of their properties and on the species.
That completes the promoter's evidence on that chapter.
I have one or two questions on the objection. We visited this scene and I think that it is fair to say that our general view then was that this objection would be one of the most difficult ones to accommodate. My first question is at what height will trains pass Glenfield Crescent and Glenfield Road?
That question might be better put to Mr McCracken, our engineer, who is here but who is not on the current panel. I apologise for that. If that question could be deferred to the next panel, we would be happy to answer it.
That is fair enough. Mr McCracken's absence from the panel probably also impinges on my next question, which is about how the promoter intends to reduce the height at which the trains will pass. The feeling was that the promoter would try to do that. Perhaps we should leave that question too for Mr McCracken.
Correct.
Given what the promoter proposes, what impact would plant screening and/or noise barriers—even transparent barriers—have on the amount of daylight going into the ground floors and back gardens of the properties?
If we were to plant trees to the rear of Glenfield Road East that would be of significant height on maturity, the houses would lose a good percentage of the light to their back gardens. However, given the limited space that is available to us in which to plant and the fact that Network Rail does not accept certain species, particularly if the trees will be adjacent to embankments, the number of species available for us to plant in this location is limited. It is most likely that the species will include hawthorn and birch, for example, which do not gain a great deal of height and which have a more open canopy. It is acknowledged that they will not fully screen the train line, but they will soften the views and limit them. They will also permit a level of light to reach the back gardens and lower floors that full vegetation screening would not permit.
So the dilemma is that you cannot plant something that will be dense because it will obliterate the light totally but, with the trees that you suggest, the residents will still see the trains thundering by from their back windows.
They will have a limited view.
I have a couple of questions. I hate using the word "woolly", but I thought that what you said earlier was a bit woolly. You said that you could—or would—consult the residents on screening and the like. Can we get an assurance that you will indeed consult, rather than an assurance that you could do that?
We will do that, if the residents wish us to do so.
Thank you for that. This question is for Mr Rutherford or Mr Sandland. Is voluntary purchase being considered for these properties?
The voluntary purchase scheme is currently with the Scottish Executive, so it will be difficult for the promoter to say whether the properties will qualify until the criteria have been agreed with the Scottish Executive. However, as Mr Brocklebank has said, this is one of the worst sites along the length of the railway. I therefore suggest that there is more than a strong chance of the properties coming under the VPS.
As you know, we continue to correspond with the Executive. Also, the Minister for Transport and Telecommunications will be at our next meeting, when I hope he will answer questions about the voluntary purchase scheme.
Yes. My first question is simple: will Mr Sandland confirm that the existing path from Tweedbank to the west of Galashiels is a completely off-road amenity?
The path is off-road and will be off-road from Tweedbank to Anderson's Chambers in Galashiels—
No, I meant the existing path—the black path as it is just now.
I am sorry. The existing path is off-road from Tweedbank to Wheatlands Road.
This is a general question on the black path. The promoter states that the alternative amenity has been approved "in principle". Can you confirm the completion date of the path, and the commencement date? I am concerned about the words "in principle" and would like to know the hard and fast date when the path will be put in place.
As Mr Rutherford has said in evidence, the application for substantial funding for the work will be made to the board of SESTRAN and ultimately to the Scottish Executive. If the money is approved, the programme is for the work to be carried out during the financial year 2006-07. Obviously, there may be slippage, but the financial facility would be available.
Your written evidence mentions
That is extra to the Waverley funding.
Okay—it is extra to the Waverley funding.
The present expectation is that we can put a shared path on the south side of Ladhope Vale.
At the moment, we have a completely off-road section in the Ladhope Vale of 800m. It is proposed to put in a shared amenity that will go through one set of traffic lights, two road junctions—one of which will lead to the bus station—and perhaps three roundabouts. I cannot understand how the promoter can regard that as being anything like the existing path.
There is an aspiration to take a path adjacent to the Gala water through the centre of Galashiels. That is problematic, but I believe that the council intends to proceed with it—or to plan for it at least.
So the new path on the maps is not the path that will be put in place. The promoter hopes to put the path adjacent to the Gala water. Is that correct?
The plan shows what we believe can be achieved and delivered at the moment. Clearly, a number of landowners and other interests would be involved if we were to put a path adjacent to the Gala water. Nevertheless, that is an aspiration. It is not yet council policy, but we would be keen for the council to consider it.
In principle, the council would be happy to go down that line.
I cannot speak for the council, but I have no reason to suppose that it would not support that.
I do not want to harp on about the issue, but would the funding for this super-duper alternative next to the Gala water come from council funds as well as SESTRAN funds?
When we built the black path, which is off the roads, it became a huge facility for the whole of Galashiels. I use it regularly. We are trying to put something back that can be used immediately, and that is what Mr Sandland has touched on. It is an aspiration of the council to put back as much off-road track as possible over the next several years. Such things do not happen immediately, but we are genuinely trying to do that.
Further down the track, as they say, there was some confusion at our meeting about whether the path would go over or under the new Tesco bridge. The plans for the road that I have seen state that the path will go over the road; the plans for the railway show that the path will go under the road. Can you confirm whether you have managed to solve that problem?
I can confirm that the cycleway goes up on to the road and round the new roundabout.
Does it not go under the bridge, as the submitted plans state?
Convener, it may be useful if the witness could focus on the plans that have been submitted, which show the alternative alignment. It can be a little difficult to follow. It is shown on plans 4A to 4C.
This is the first time that we have seen those plans.
It is the first time that we have seen them as well, Mr Sandie. If you have any further questions, please continue.
The path will go over the road. That means that we will have to dismount and go round the roundabout to get back on to the black path.
It is anticipated that you will be able to cycle up on to a shared-use path round the roundabout. However, to cross the legs of the roundabout, you will have to dismount. I am pretty sure that these plans do not show the line of the path going either under or over the bridge.
I do not want to say that that is not correct, but I have seen a plan on which the facility was shown to go under the bridge.
That is right. That is part of the redevelopment for access to the Asda store.
Let us go further down the path to the Glenfield Road area. At our meeting, we discussed the positioning of the path on the flood plain, but we could not get an answer about what height the path would be on the flood plain. I realise that there are difficulties. If the path was too high, it would affect the flood prevention area; if it was too low, it would get washed away every time there was a flood. Have you managed to get some more information regarding the height of the path?
Mr Sandie, we are going to address the issue of flooding once we have dealt with the path.
This is about the path as well. The path is on the flood plain.
Okay. Continue for the moment.
It is anticipated that the path will be built at grade—at the same level as the flood plain—thereby avoiding any effect on the flood prevention area. I am assured that it can be built sufficiently robust to withstand reasonable flooding—that is the term that I would use.
So, in the Glenfield Road area, the track will not be raised up but will be built flat.
Yes.
Okay. I find it very difficult to accept that, given the number of floods that we have had in the Glenfield Road area—it was between three and five in the year. I am pretty sure that Scottish Borders Council will find that it will cost it a lot of money to repair that part of the track, if it is laid on the flood plain.
I go down to the north-east of England quite a lot. There is a causeway that runs from the mainland to Holy island; it gives vehicular and pedestrian access to the island. Although the causeway has to suffer the tide coming in two or three times a day, it is still in place. Obviously, when the tide comes in, the causeway cannot be used. There are ways in engineering to safeguard a black path or causeway.
The last part of the black path that I want to mention is the Redbridge viaduct over the Tweed. At our meeting on 8 March, you said that you were unaware of the exact width of the bridge. Can you confirm the width now?
Our engineers have advised me that it is 8.2m from parapet to parapet.
The aspect of the black path that concerns me most is the cycle path that is to go on the bridge, adjacent to the railway line. You said that the width of the bridge is 8.2m. I understand that the minimum width of a path is 2m. That leaves 6m for the railway line. I was also informed that a safety barrier should be put in place and that any path has to be 3m from the barrier. Surely that does not leave much room for the railway line. What kind of path will Network Rail install on the Redbridge viaduct?
I refer Mr Sandie to drawing 16 in the set of drawings that we circulated this morning. The drawing, which is a cross-section of the Redbridge viaduct, was prepared following the meeting with Mr Sandie. It shows the outline of a train, the width of the track and the proposed cycleway. It illustrates the feasibility of installing the cycle path on the viaduct.
What speed will a train be running at when it crosses the bridge?
I think that it will be quite a low speed, but I cannot recall the exact speed. Mr McCracken may be able to give exact figures in the evidence that he gives later in the meeting.
Given that the bridge is owned by Network Rail, can you confirm that the path will be put in place prior to the reinstatement of the railway?
It will be constructed with the railway works in mind. Is the question whether that will be done before the railway line is built?
I believe that section 9(2) states that no stopping up can take place until an alternative is open to the public.
That is the case.
As I read it, if the bill is passed and the line begins to be built, the path has to be constructed before the work commences on the viaduct.
Yes, that is an undertaking that we would give.
Is the undertaking one that Scottish Borders Council or Network Rail can give? As I said, Network Rail owns the bridge.
From an engineering point of view, I think that there is no difficulty in building the path and in having it open and isolated from the construction works. We may have to give thought to the detail of how that is done.
But do you have confirmation in writing from Network Rail that it will put the path in place?
I do not have that.
You do not have it. So, Network Rail might turn round and say, "No, we are not going to put in the path."
Network Rail is aware of the proposal. It has reviewed it and has made no objection. I have received nothing from Network Rail to suggest that it has any difficulty with this.
I think that you can see where I am coming from—
Mr Sandie, we note the point that you are trying to make. Please move on to your next question.
I have finished asking questions on loss of amenity.
Mr Rutherford, you said that a decision on Scottish Borders Council's funding request is imminent. What is the process and when will the council find out whether it has funding from SESTRAN or the Executive? If funding is not granted, when will the council make a decision on what to do about funding?
The SESTRAN steering group will meet on Friday, so we will find out then whether funding has been approved. Early indications suggest that it will be approved. The decision must then be ratified by the Scottish Executive.
How long will that take?
I cannot tell you. However, about £9 million per year is available to SESTRAN during—I think—the next three years. We put in a bid for the first year and Midlothian Council made a similar bid and we are fairly confident that the money will be allocated. We do not anticipate that our bid will fail, but if it does, I will have to speak to councillors about how best we can fund the work. The costs of some of the work are included in the capital costs of the railway, but we have taken the opportunity to enhance the walkway and cycleway in other areas. We want to provide suitable access to Clovenfords and a link between that village and Galashiels.
How much capital is available for the Waverley project? How much more are you requesting from SESTRAN?
You will know about the vagaries of a council's capital programme. I would have to ask whether work could be accelerated, but the work must compete with every other priority that the council has set. As I said, the work is a high priority, but we would have to approach the council for additional money only if our submission to SESTRAN was unsuccessful.
I want to clarify a matter. I understood that your application had been made to Sustrans, the organisation that campaigns for sustainability in transport in Scotland, not to SESTRAN.
No, the application was to the south-east Scotland transport partnership—SESTRAN. The Scottish Executive made £9 million available over the next two or three years.
Thank you for that clarification. We are trying to distinguish between our Us and our Es.
I do not.
Andrew McCracken, Andy Coates and David Wright are the witnesses on flooding.
Mr McKie, do you want to invite one of the witnesses to give us a brief update on the current position with regard to flooding?
I do, convener. It might be useful if Mr McCracken interpreted for us the two plans that show the alignment that is proposed in the bill and the proposed realignment, and dealt with the question of the exact height of the railway bed at Glenfield Road East.
Certainly. On plan 11, we have shown in red the current alignment that is proposed in the bill. By way of background, I should explain what we have had to do to the alignment vertically, which has driven the height issue. In the middle of the plan, we show the line crossing Glenfield Road West. Scottish Borders Council's highways department has made it clear that as part of its roads strategy we have to maintain a full 5.3m high road clearance under the rail bridge. As a result of that, we have falsely raised the railway higher than its previous alignment. We have then applied a near maximum vertical gradient from that point. As we travel along Glenfield Road West to Glenfield Road East we have applied a falling gradient of 1:100.
Thank you, Mr McCracken. That moves us conveniently on to Mr Wright. Good morning, Mr Wright. Have you assessed the potential realignment shown on plan 13 from the point of view of flooding?
Yes.
Could you confirm to the committee what your findings have revealed?
Okay. Good morning. I have been asked to respond to the flood issues associated with the proposed rail alignment where it would run between Glenfield Road East and the Gala water. I have considered two aspects of that.
Are you satisfied that your questions have been answered?
I wish to clarify a little further the question of height. What is the maximum height that will be reached in the original alignment? How high will the line be behind those houses?
At the next stage of design, we could probably increase the gradient from the new bridge at Glenfield Road West to try to lower the line more quickly. A 1:70 gradient would normally be the maximum—it is the maximum gradient used elsewhere on the line. If we applied a 1:70 gradient, I reckon that we could probably lower the embankment at Mr Sandie's property by about 0.6m or 0.7m. I apologise for calculating that quickly and crudely—I can confirm it later. When the gradient is steepened, train performance can be compromised, so we would have to consider the timetabling, to ensure that we do not compromise speed too much. That is part of the iterative design process with operations.
You are saying is that there is no way of dramatically reducing the height of the embankment and that people will still be able to see virtually the whole of the train from their back windows?
Yes. Unfortunately, it comes down to train performance and traction of steel wheels on steel rails. That is the limiting criterion. A 1:70 gradient is approaching the absolute maximum on which rolling stock can accelerate and decelerate. That is the problem.
To confirm what Mr Wright said, it is not really feasible to change the alignment. You really have to stick where you are.
Horizontally, for the reasons given.
Did you consider flood prevention measures alongside the alternative alignment? Did you do any modelling on how much it would cost to do that?
No. The modelling that has been done assessed the quantum of change that would take place in one alignment rather than another. You are right: if you are proposing a scheme, you can consider offsetting elements to bring the flood levels back down to their existing levels. That can be done where there is more room to move and store flood water, but this area is rather like a funnel and little can be done to provide compensatory flood storage anywhere else to offset change.
I do not know whether we need to call Mr Rutherford forward for this one. How could the alternative alignment impact on the appropriate assessment issue?
I was going to put that to Mr Coates, who I think has had discussions with SNH on the issue.
How would you like to answer that, Mr Coates? Tell me about how the alternative alignment would impact on the appropriate assessment.
We have spent some considerable time recently in discussion with SNH about moving the line further away from the edge of the watercourse. One of SNH's concerns is flooding. On the appropriate assessment, the alternative alignment would bring the line closer to the river. You can see from the plan that there is a pinchpoint that looks close to the edge of the river—probably closer to the river than SNH imagined. SNH has not yet been out to look at the area, so its comments relate purely to the plans.
I ask for your guidance, convener. In response to Mr Brocklebank's question about the height of the embankment, there was some discussion about the impact on the rolling stock's performance. Could we return to a discussion of any noise impact from that change?
We will come on to noise and vibration shortly.
Yes, I have a few. Much of the information that we are hearing now is new to us—as are many of the plans, which we have not seen before today. Has any consideration been given to closing off the underpass? No flood water would get through the underpass if it was closed off.
I will leave that to Andrew McCracken.
We always assumed that the underpass had to remain open. I think that that was to keep the existing right of way open, although I would have to refer that point to Mr Sandland.
So closing it off could be an option?
There is one other thing: I think that an electrical substation is located where there is a sign on plan 13 saying "flood plain". Access to that for maintenance, inspection and servicing is from Glenfield Road East through the underpass, so that might have to be addressed with the owner of the substation.
The 10m move was news to my colleagues, as the discussions that we had were about a move of 4m, but any number of metres away from the existing alignment would be of benefit. Is any work being done on moving the track less than 10m?
We considered the impact on flooding of moving the track 10m. I suppose that it would be possible to do a series of permutations from 1m up to 10m, but the flooding issues are generic. The point is that, if we slew to the south at all, we will encroach on the flood plain. Although the increase in flood water would be less if we moved the track less than 10m, the issues that Mr Wright discussed would apply generically and the concerns of SNH and Scottish Borders Council's flood prevention officer would remain the same.
The movement of the track would be of major benefit to us. Would it not be cheaper to improve the existing flood prevention methods in Dale Street and Nether Road if the track encroaches on to the flood plain?
Do you mean to offset the effects of moving the track to the blue line on plan 13?
If you moved the track to the blue line, what impact would it have on the existing flood prevention measures?
I could not give chapter and verse on how many millimetres the walls would have to be raised but, if such an alignment were in place, the frequency with which they would overtop would increase from once in 200 years—the level of protection is probably less than that; the walls were built some time ago and the flood standards were lower, so it is probably a one-in-100-year standard—to, say, once in 75 years. To regain the one-in-100-year level of protection, the walls would have to be raised. It is difficult to say how much they would have to be raised, but it would be millimetres not metres. Usually, a slice of material would go on top.
So it is a possibility.
It is, but I understand that the walls are quite old and we would not be able to add a bit of material. That is the case in other schemes that I am considering, in which the whole thing needs to be replaced just because an element is being added.
Andrew McCracken made an important point about SNH. Having been through several difficult meetings with SNH—which you do not have to hear about—we have been trying desperately to move engineering works away from the watercourse. From the meetings that I have attended and the feedback that we had on Friday, I think that we would have a real problem with SNH if we suggested pushing the track towards the watercourse at all.
I have a final question on flooding. The promoter's response states that
No. Were the surveys carried out by the promoter?
I believe so. They carried out surveys for two weeks.
Preparations for other flood prevention schemes are under way in the Galashiels area, but they are not part of what we are doing.
Work could also be done to improve the existing flood prevention schemes.
Does Mr McKie have any follow-up questions for his witnesses on flooding?
No.
I ask Mr Rutherford, who is not at the table, to confirm to the committee who carried out the work that Mr Sandie mentioned. We would appreciate a note being provided on the matter to the clerk to the committee.
Mr Rutherford has given the committee a lengthy statement about the level of consultation, so on that issue the promoter would wish to rest on its evidence, as it would with respect to the impact on property values. Mr Rutherford has said that the properties at Glenfield Road East might qualify for the VPS, but that we will not know the full answer until we hear from the Executive. I suggest that we leave those matters to one side at the moment, although if the objectors and the committee desire to ask questions about them, they can be answered.
I will briefly summarise the evidence and add to it where I can.
And in terms of vibration?
All those properties are sufficiently far away for me not to have a major concern about vibration. However, as I said previously, that will be reviewed in due course just to confirm that the targets that we set ourselves in the noise and vibration policy will be met. I expect them to be met, given a standard track form going through this area. It is probably worth reminding the committee that the approach to noise and vibration is through the policy targets.
Mr Mitchell, can you confirm whether the levels of vibration that you expect to emanate from the rail line once it is in operation would give rise to structural damage?
Yes, I can. The targets for vibration are to do with annoyance and disturbance to people who feel the vibration. Because we will meet those targets, we will meet the thresholds for damage by some margin. I would not expect a risk of damage to any of the buildings in this area.
Turning to Mr McCracken, on the issue of health and safety, are you—
You have moved on a bit too quickly.
Sorry.
I have a question for Mr Mitchell. You gave the figure for night-time noise thresholds for Glenfield Crescent, but you did not give a figure for Glenfield Road East. Can you give us that figure, please?
Yes. The night-time figure for Glenfield Road East is 48dB plus. It is right on the margin of needing noise mitigation, so we have provisionally outlined a noise barrier there at this stage. It is not a high one because we do not need a high performance there.
Thank you. I recall that when the committee visited the area and saw for itself the layout at Glenfield Road East, we were particularly struck by how close the railway would be to the backs of the houses and by its height, even with the mitigation of which you have spoken. Can you say how far the nearest track would be from the back of the houses in Glenfield Road East, rather than from the garden fence?
Approximately 15m. We are talking about the numbers up to number 52, which is the eastern portion.
Will you carry out structural surveys on those properties prior to the commencement of construction?
We have in the bill provision to carry out structural surveys or to gain access to do them. In chapter 13, I think, of the code of construction practice we say that we will draw up a schedule of properties that need the surveys. If it is felt that they are at risk of damage through the construction works, which is the main objective of this exercise, they will be surveyed. The properties are not as close to the track as are dwellings that we have seen elsewhere.
That is not a particularly clear answer, Mr Mitchell. The question was specific. Will you carry out structural surveys of these properties prior to the commencement of construction?
We have certainly given that undertaking for one or two properties that will be 6m or 7m away from the line. My personal view is that the construction work in the area concerned is unlikely to cause any damage. The distance may sound small, but the construction activity that will be undertaken will not be particularly high energy. Personally, I do not know whether the properties will fall into the category that the member mentions.
So if, at a later date, residents wish to produce evidence of an effect, they will have had to commission their own structural survey prior to the commencement of the work?
They certainly have that option.
Right. Mrs Gorlov, do you want to add anything?
I could give my client a hint that it might care to instruct its consultants on the issue. One option is to carry out surveys of the properties. When the time comes, it may be thought that an element of safeguarding is desirable for those properties. As the committee will know, the bill provides for pre-work and post-work surveys to be done. I do not know whether that is appropriate in the present case—the committee may have been told that we do not know the answer to that—but we will certainly consider the issues and give the committee more information on them.
The committee would welcome further information.
We undoubtedly would.
I will ask questions on noise. We are told that an ambient background noise measurement was taken in the Glenfield Road East area. If so, when and where was that done?
I am not sure that I said that.
The last time we met the promoter, nobody could tell us when the readings were taken.
If you give me a moment, I will look up the information. I did not say that to you, but I will check the paperwork. The reading in the Glenfield Road East area, at our receptor R55, was taken on 21 and 22 June 2004, between 11 o'clock in the morning and a similar time at night. That is reported in our supplementary memorandum of 23 August 2004.
As our original objection points out, the bill states that the distance from the boundary of our properties to the proposed track will be between 6m and 10m. Measurements made by our committee show that the actual distance will be 8m. We understand that the promoter intends to place a noise barrier between the railway and 32 to 52 Glenfield Road East. For safety reasons, the noise barrier must be at least 3m from the track and cannot be situated on sloping ground. However, the promoter's plan of the area shows the noise barrier on the slope.
I see no reason why it cannot be situated on the sloping ground; it just needs a slightly larger foundation.
We have been told that the barrier must be on solid ground, not sloping ground. We must also consider the safety aspects that arise from the height of the barrier combined with the volume of wind that comes down the valley. If the noise barrier were to take off, it could cause structural damage.
Mr Hegarty, do you have a document that suggests that noise barriers should not be on sloping ground?
We were told originally that the sound barrier had to be 3m from the track and on flat land.
Who told you that?
I think that that came from—
Convener, Mr McCracken is keen to answer the question.
Go ahead, Mr McCracken.
Putting a noise barrier on a slope is a fairly easy engineering matter. A slightly deeper side-bearing foundation would be required to resist the lateral wind load, but that is often done when building railway infrastructure.
So there is absolutely no reason why the barrier cannot be on the slope?
Absolutely none.
Mr Hegarty, do you have any further questions?
Yes. Will noise measurement be undertaken regularly after the trains start running? Will we be informed about the results?
Yes. The final chapter of the noise and vibration policy is about monitoring noise levels from the operation of the railway. There is a clear commitment to measure noise levels, to check that the design works as planned. There is a commitment to make the noise levels and recordings public.
If operational noise levels are severe, who or what will trigger mitigation and when will that happen?
The purpose of monitoring is to check compliance with the targets that we set ourselves, so noise levels will be judged against those targets, which might differ from your view of what is severe. If the targets are not met, we will take remedial action, if it is practicable to do so, to bring noise levels back into compliance with the targets.
Another concern is construction noise. We understand that the compulsory purchase orders on land at 52 and 32 Glenfield Road East have been rescinded. Will you give an undertaking that no rail construction traffic will use Glenfield Road East as an access route?
I am afraid that I cannot give that assurance. Perhaps Mr Rutherford can help.
The objection from Mr Scott and Mr McConnachie has been withdrawn and it is unlikely that we will need access. We told those objectors that we will not go through their gardens at any time. When work is going on to the structure at the end of the road near number 52, there might well be vehicles in the area and vehicles might occupy part of the verge, but the traffic between the two rows of houses at Glenfield Road East will be much less than was envisaged.
I appreciate that Mr Mitchell cannot come up with a definitive answer to this question at this stage, but can he give an indication of the likely impact of noise, particularly on Mr Sandie's property, if the gradient were steeper?
I will not attempt the back-of-an-envelope calculation that Mr McCracken just performed. I cannot do that calculation here—
I am disappointed.
The noise change would be very small. The railway will be on a gradient in any case and a change from 1:100 to 1:70 would not have a big impact on noise output from engines. Such a change would make only a slight difference. The anticipated noise levels on Mr Sandie's property are currently a few decibels under the threshold for mitigation and I suspect that it is unlikely that the change in noise levels would be sufficient to trigger a requirement for mitigation at that location.
Mr McKie, do you have follow-up questions for the witnesses?
I do not.
On health and safety, the witnesses for the promoter are Steve Purnell and Andrew McCracken. Mr McKie, before you ask questions, please invite one of the witnesses to summarise how matters stand.
Mr Purnell, will you describe how health and safety will be enforced during the construction phase of the project?
Certainly. I think that health and safety issues were raised in relation to construction traffic, principally in the Glenfield Road East area. Specific safety measures, noise levels and air quality arising from traffic movements are explicitly mentioned in the code of construction practice, which has been the subject of discussion during the meeting. As the committee heard, the code will be binding on the contractors. All safety measures that require to be put in place as part of the contract will have to be agreed with the local planning authority before any works can be undertaken.
Thank you, Mr Purnell.
As I have stated in previous evidence, we refer to a rail regulation policy paper that clearly outlines the safety procedures, approvals and so on. In previous oral evidence, I have referred to severe geometry and things like that. You will see on plan 11 the section of track from Glenfield Road West as the train clears the bridge. All the way along there is a section of straight track—there are absolutely no features on the route at this location that would cause me any safety concerns.
Okay. Can you confirm how rail safety will be enforced during the railway's operation?
The design and approval will have to comply with the policy guidance of Her Majesty's railway inspectorate.
Do you have any reason to doubt that approval will be given by HMRI?
No.
Thank you.
Having been on a site visit, I think that there is a general sense among committee members that the track is very close to, and will be very high behind, the properties that we are talking about. Would the promoter seek to install any kind of safety barrier at this stretch of track?
There is no design standard or approvals process that requires that a safety containing barrier be put in place there, so there are no proposals to put in such a barrier.
Can I play devil's advocate for a second? All things being equal, trains tend not to come off tracks. However, let us say for the sake of argument that some nasty little sod has decided to put a great big piece of concrete on the line. What would be the impact of that on a train that was travelling along a raised piece of track? Would the train manage to deal with that without derailing?
If there was such an obstruction on the track and a derailment was to occur, it would have occurred because of the concrete block. If the track was on a raised embankment there would be potentially more risk that the train would come off the tracks and go more to one side than the other. To answer your question, the derailment would probably have a worse consequence if that was to occur.
The derailment would have worse consequences if it were from raised track than it would from track that was on the level.
Correct.
Thank you. That is all I have on health and safety.
Mr Hegarty, do you have any questions for the witnesses on health and safety?
Yes—I hope that my questions are suitable.
I am sorry, but I must have missed the question. I heard your statement.
We are saying that the train will just have completed a tight curve on an elevated portion of the track. Should anything untoward happen, the train would topple one way or the other.
Is there a question there, Mr Hegarty? Are you asking Mr Cracken whether he agrees with you?
Not really. I am just asking for more clarification, but I think we have already got that.
Could you perhaps clarify matters a wee bit more, Mr McCracken?
As I said in my answer to Ms Smith, the train will be on a section of raised track. If the train were to come off that track, it is undoubtedly true that it would have height to lose. However, I reiterate that the train will be on a section of straight track. Once the train has cleared the bridge, which will be some distance from the train, it will enter a section of straight track. In infrastructure terms, it will be safe.
I have no more questions.
Does Mr McKie have any follow-up questions on health and safety.
Mr McCracken said that there will be no safety restraining fencing. Will any fencing be provided along the rail line?
Yes.
What will be the specification of that fencing?
The fencing will be the full specification because the line will be in a built-up area. It will be 1.8m high palisade or chain-link fencing.
The issues of acquisition of land and the impact on the viability of a letting business are raised in the Waverley Housing objection. Witnesses for the promoter are Andrew McCracken and Alison Gorlov. I ask Mr McKie to invite one of his witnesses to give a brief outline of where matters stand. He may then question Mr McCracken and Mrs Gorlov.
The promoter's position remains as outlined in its policy paper on compensation and compulsory purchase, which states that the existing law should be applied.
What is the up-to-date situation on the correspondence between the promoter and Waverley Housing? I think that Waverley Housing wrote to the promoter at the end of December, but had to wait a while for a response. In his earlier remarks, Mr Rutherford said that a letter had been sent to Waverley Housing at the beginning of March. What did that letter say and what is the up-to-date position?
Our letter to Waverley Housing confirmed our position on compensation, which Mr McKie has outlined. We thought that we had answered all the questions and we suggested the possibility that Waverley Housing might feel able to withdraw its objection. However, Waverley Housing has said that it will, on the advice of its lawyer, maintain its objection because it wishes to discuss further the terms of compensation.
Can you confirm that the distance between the proposed railway line and Waverley Housing's nearest property to the proposed line is about 40m?
I will confirm that at a later date—I do not have the information with me.
Confirmation of the distance between the proposed line and the nearest Waverley Housing property would be helpful.
Does Mr McKie have any follow-up questions for Mr McCracken or Mrs Gorlov on this issue?
No.
We will now hear evidence on group 61 from witnesses Albert Hegarty, Thomas McCudden and Graeme Sandie.
We turn to loss of amenity—the black path, privacy, visual impact and reduced daylight. Mr Hegarty, as you do not have a questioner, perhaps one of your group would like to comment on whether you accept the promoter's evidence about where matters stand on those issues.
All three of us are here today as objectors in our own right. We also represent the residents of Glenfield Road East. I do not know what more I can say at the moment.
Do any of your colleagues have anything to say about privacy, visual impact and reduced daylight that has not been said earlier?
Everything has been said on my behalf. I am quite happy with that.
Do you have anything to add, Mr McCudden?
We are still concerned about the height of the track at the Glenfield Road West end. We understand that the height will decrease as the railway comes towards Glenfield Road East. The houses along Glenfield Road West are in darkness for 90 per cent of the day already. If the promoter is going to put trees of any magnitude on that embankment, the amount of daylight will be reduced even further.
Do any of you have anything to say about flooding? We will deal with all the issues surrounding loss of amenity together.
I am sorry, convener—I did not quite catch what you said. I am suffering from a head cold.
On the issues surrounding loss of amenity, I separated out the issue of flooding during the earlier session. Do you have any comment to make on loss of amenity and flooding and on where you see the issue going?
I do not think that we do.
Okay. Thank you.
I do not. The promoter stands by its evidence.
Do committee members have any questions for the witnesses?
No.
We turn to noise and vibration, consultation and impact on value of property.
We accept the promoter's evidence.
Thank you. Mr McKie, do you have any questions?
I do not.
Do members have any questions?
Mr Sandie, what is your view on what we have heard about potential changes to gradients and the knock-on impact that they might have on noise?
I heard what the promoter said about dropping the embankment's height by 0.6m. It is still going to be approximately 7m high, which is 4m on top of the existing embankment, plus a train on top. That will obviously drastically affect our privacy, as well as our natural daylight and so on. I do not know what more I can say about that. If the promoter is not able or willing to move the track even 4m further across, we will probably have to live with it.
Thank you.
I have a question for all three of you. If it was possible for a voluntary purchase scheme to include your houses, would you seek to have your house purchased?
I would not.
That question would have to be put to the residents of the 21 houses that are involved. Some might want to do that. I would not want to have to move if it were possible for me not to.
Are you of the same view, Mr McCudden?
It would depend on the circumstances. With house prices in the Borders, the question would be where to move to if the houses were purchased in such a way. Furthermore, a lot of old people have moved to the area on their retirement because it is on the flat and all the other houses in the valley are up the side of the hills. Where would they move to that is flat?
Mr McKie, do you have any questions?
I do not. The promoter stands by the evidence that has been given.
On health and safety, I ask the witnesses to comment on where they stand and to say whether they accept the promoter's evidence on where matters stand.
I accept the promoter's evidence.
Mr McKie, do you have any questions on health and safety?
I do not.
Mr Hegarty, Mr McCudden and Mr Sandie, do you have any further comments to add at this point, taking into account the questions that you have been asked on the various topics today? I remind you that, in a few moments, you will have the opportunity to make a five-minute closing statement.
We do not have any comments to add at this point.
Mr McKie, you have a maximum of five minutes in which to make a closing statement.
In my submission, there is extensive consultation of the objector groups, as Mr Rutherford has said. The objectors ought to have been aware of the scheme when it emerged from its embryonic stages through the publication of the draft structure plan and the council resolution in 2000, which Mr Rutherford talked about. The community council, which represents the whole of Galashiels, will have been consulted about those documents, which means that there will have been an early warning that the scheme might be coming.
Thank you, Mr McKie. Mr Hegarty, Mr McCudden and Mr Sandie now have a maximum of five minutes in which to make a closing statement. Any one of you may do so.
I have prepared a statement.
That concludes oral evidence for group 61. I thank the witnesses for coming to the committee to give evidence and for highlighting to us the problems when we visited them last year. We shall reflect on all that has been said today when we write our report. I can tell Mr McKie and Mr Rutherford that the committee is pleased that surveys are now to be carried out in Glenfield Road East. That is something that we wanted and expected, so I thank you for that.
Meeting suspended.
On resuming—
Welcome back everyone. Our second group of objections today is group 52, from Gala Fish Farming Ltd and Torwoodlee and Buckholm Estates Company Ltd. The group has chosen to rest on its written evidence.
Convener, would it be convenient if I were first to make a short statement from the promoter on the code of construction practice? It should take only a moment.
That would be fine.
The promoter takes very seriously the comments and questions from the committee this morning. It will examine the terms of the existing COCP and will assess the COCP for the tram schemes. It will take into account all the committee's comments on the COCP and will sharpen up the application of baseline minimum standards in that COCP. It will report on those matters with an iterative version of the COCP. The committee will appreciate that that code will still be in draft form, but it will be moved to the next level by 24 March.
Thank you for that statement, Mr McKie; it has certainly found favour with committee members, who I think were unconvinced by the draft that we had. We look forward to seeing the newer draft very soon indeed.
Mr Sandland, will you update the committee on where matters rest with group 52?
Mr James Pringle occupies Torwoodlee estate on the outskirts of Galashiels. His objection identifies two main issues of concern: the hitherto proposed purchase of four plots of land totalling just under 1.2 hectares, which it was suggested by the objector could be accessed via a grant of servitude; and the requirement for compensation for disturbance to the objector's fish farm, which is located adjacent to the proposed railway.
Are you optimistic or hopeful of reporting back to the committee shortly that the objection can be resolved?
Yes.
In the written evidence that it submitted in early December 2005, the promoter states that it is seeking the approval of Network Rail with respect to a servitude right of access. The promoter's objection report that was submitted on Thursday 9 March states that that approval has still not been received. Why is that?
It is not for the want of trying. The first thought was that we would write a deed of servitude and submit it to Network Rail for approval, hence the report in December. We then rapidly formed the view that, for all practical purposes, Network Rail would be satisfied with its own version—it has templates for such documents and we thought that it would not readily take to anything else. The company was approached in December—or perhaps in early January—and asked whether it would be good enough to produce something for us. We had thought that Network Rail might have something suitable on its back shelf. The person whom we contacted certainly thought that that was the case and I know that he has pestered his property people about it since—I have seen the e-mails. Every so often, I chase him and he chases them.
Has Network Rail been informed of the committee's often-stated view about the need to settle such objections and to make speedy progress?
I think that Network Rail is very well aware of that.
When did you last approach Network Rail to remind it of that?
If recollection serves me correctly, I last spoke to my contact on Wednesday of last week, when I saw the chap. If I did not mention the matter then, I certainly mentioned it at a meeting the previous week.
If the committee agrees, I will ask the clerk to write to Network Rail to pass on the committee's concerns about its failure to give the information that we need to allow consideration of the objection to be concluded.
Perhaps I might give Mr Cochrane the contact name.
That would be much appreciated. Thank you, Mrs Gorlov.
I do not. The promoter simply rests on its existing written evidence.
Do you wish to make a closing statement?
I will not trouble the committee with that.
In that case, that concludes the oral evidence for group 52.
I invite Mr Sandland to give an update for the committee's benefit. Plans have been lodged in relation to the group. Plan 1, which is drawing 5A, is the relevant document that shows all the objectors' properties.
Andrew Brown resides at Plumtreehall on Plumtreehall Brae, Galashiels, which is one of the houses that are closest to the railway. It has been found necessary to schedule a 172m2 area of his garden ground for acquisition. That will allow for temporary access for railway construction and a permanent link to the replacement black path, which will be provided separately and additionally to the proposals in the bill. Mr Brown has agreed to the sale, subject to price. He has been advised that compensation may be claimed if he believes that detriment has resulted from the railway. With that in mind, he advised us that he had had a valuation of his property.
Thank you. Mr McKie, do you have any questions?
I do not. It would be useful to deal with each objector, as the group contains quite a few objections. Each objector might have specific issues that the committee may wish to hear about.
Mr Sandland, for the sake of clarity, will you say whether the promoter intends to purchase all of Mr Brown's property or just the portion of the garden that is needed for the construction site?
Just the 172m2 that I mentioned are to be purchased.
On the impact on the value of properties, the witness for the promoter is Alison Gorlov. Mr McKie, will you invite Mrs Gorlov to comment on where matters stand and then question her?
It might be more useful to hear Mr Sandland's update on the other objectors. As I said, issues that relate to each objector are being negotiated separately. It might be useful to complete that before moving on to other issues.
Mr Sandland?
Sheila Campbell resides at Jasmine Lea in Wheatlands Road, Galashiels. Her house lies some 22m from the proposed railway track, but construction work will take place within 3m to 4m of her garden. Mrs Campbell is concerned about noise and vibration, the effects of the railway on the value of her property, health and safety and loss of privacy. She has been advised that compensation for physical factors such as noise and vibration could be claimed if those factors reduce the value of her property. At a meeting on 8 September 2005, Mrs Campbell said that she did not wish to continue to live in Jasmine Lea should the railway be built. The property has been included in a list of properties that could be considered for purchase under any voluntary purchase scheme that the promoter effected.
The promoter chooses to rest on its policy paper on the impact of the proposals on the value of properties.
Do members have any questions on that matter?
I would like to ask a general question about compensation. Would someone be eligible for compensation if their property insurance premium increased as a result of the railway?
I do not think so. I will come back to the committee. I ought to know the answer, but I am afraid that I do not.
Where do matters stand in relation to the promoter's discussions with the Executive about general property surveys?
I am afraid that I cannot answer that question. I will have to come back to the committee on the issue.
That is fine.
The maps are very helpful. As you deal with specific objections, could you indicate where the locations to which they relate appear on the maps? I have been hunting backwards and forwards. You know the subject better than I do.
I apologise.
We have finished discussing the impact of the railway on the value of properties. Mr McKie, would you like to move on to health and safety issues?
Yes. In its written evidence, the promoter deals at least partly with the question of increased insurance premiums. I direct the clerk to that evidence.
No. Generally, this is a section of straight track, so there are no particular infrastructure concerns in respect of safety.
Do you wish to adopt your earlier evidence on how safety will be enforced during the operation of the scheme?
Yes.
Will fencing be placed along either side of the track at this location?
Yes. It is an urban location, so the high-spec fencing to which I referred previously—palisade or chain-link fencing—will be used.
The committee has no questions on health and safety.
Some particular noise effects will have an impact on this objector group. I ask Mr Mitchell to move along the line from plan 1, which is headed "5A. Group 54", to plan 2. He should identify the objectors and those properties that we believe will be most affected by noise. He should also indicate what measures the promoter intends to implement, should the scheme proceed.
In his introduction, Mr Sandland indicated that four objectors in the area had expressed concerns about noise and vibration. I will not touch on the issues that were raised by the fourth objector, whose property is 50m away from the proposed route, but I will deal with the concerns of the other three.
Thank you. Could we go back to plan 5A and focus on Mrs Campbell's property? You told the committee that a noise barrier will not be required there, but one is shown on the plan. Is that an error?
I am afraid that it is an error. The barrier is shown next to the wrong property. A noise barrier should not be shown next to Jasmine Lea, but a barrier is required next to Mr Brown's property.
I think you said that noise insulation will be required at High Buckholmside at property numbers 109 and 127.
Yes, and also at numbers 123 and 125.
Will you confirm the nature of that noise insulation and tell us when it is likely to be installed?
The noise insulation will be a secondary sheet of glass located inside the existing window façade so as to increase the noise attenuation of the overall window set. It will be offered and installed before the railway is opened.
What is your professional opinion on vibration at the properties?
The properties that I mentioned on plan 1 are a little more distanced, but at High Buckholmside there will be a need to examine the track form because the properties will be 7m or 8m from the nearside track. There is a need to look carefully at the design of the track; as I have mentioned to the committee in similar situations, the track might need to be modified to meet the targets that we set in the noise and vibration policy.
Thank you, Mr Mitchell. That concludes my questions.
Can we be clear about the disappearing noise barrier outside Mrs Campbell's property? I assume that there is simply a genuine mistake on the map and that Mrs Campbell has not been advised that she is to have a noise barrier.
Yes. I believe that that is the case. It is the map, which was drafted last week, that contains the error.
Perhaps you could confirm that Mrs Campbell is not expecting a noise barrier, only to find out from reading the Official Report that it is to be whipped away from her.
I will check that.
Thank you.
I want to take you back to an answer that you gave this morning in relation to the promoter's noise and vibration policy. I am aware that the policy sets out the ways in which you will mitigate noise and vibration, but it is less specific about how the policy will be enforced. How will you ensure that any noise levels that you have worked out and mitigation that you have recommended will be enforced?
The noise and vibration policy commits us to using the best practicable means to achieve the targets that we have set ourselves. That form of words has been tested in similar situations in other projects.
You will set that out in detail, but I presume that the local authority will have a duty to ensure that the commitment is made good. If, subsequent to the railway being built and the barriers being installed, it is seen that what you hoped would be achieved is not being achieved, will it be incumbent on the local authority to ensure that that is redressed?
Yes.
I am sorry to interrupt, convener, but I believe that Mrs Gorlov has been considering the issue of enforceability, which is the nub of the question. It might be useful if she were to give us an update on her discussions with the committee's legal advisers.
There are two levels to enforceability. First, there is the practical level of what goes into the contract and how the contractor is tested to see whether he has delivered what the authorised undertaker is obliged to do. That is what Mr Mitchell has just described.
If it can be seen that best practicable means have not been used, is it up to the promoter to ensure that that situation is fixed?
That is right.
Will the revenue costs of the operation of the railway be adjusted to take account of the staff who will be needed to carry out that work?
You are talking about after the railway has been commissioned?
Yes.
I do not think that that has been addressed.
The promoter's noise and vibration policy paper says about monitoring and maintenance:
I am not saying that the scheme cannot be monitored—of course it can and will be monitored to find out what needs to be done. I am not considering the authorised undertaker, but the level of supervision by the local authority. The local authority and the authorised undertaker are unlikely to disagree—the scheme will either work or not work; it is likely that they will agree about what can be done about things. However, there is a theoretical question—I hope that it is theoretical: what will happen if they disagree? What I am saying does not depart at all from the noise policy. Monitoring will take place.
The obligation in question will be placed on Network Rail with several other obligations as part of the transfer deal. The issue will have to be dealt with as part of the agreement to take over the network.
I return to the earlier question. In respect of the annual operating case, components of annual costs that cover general maintenance and reviews have been added into the business case. Such costs should be priced into our annual review.
As no one else on the panel wants to have a stab at the issue, do you have any further questions, Mr McKie?
No.
Okay.
I simply invite Mr Purnell to confirm the position on the control of pollution at the location.
The type of pollution that is being referred to is not clear, but we have assumed that it is air or ground pollution. In the past few weeks, I have answered questions on the number of trains that would be likely to pass any given point and the very low levels of pollutants that would be emitted to the air, which will readily disperse and not cause air quality or health problems. Modern diesel railway systems are not a source of ground pollution, so we do not believe that ground pollution is a concern. If a construction issue is being referred to, I spoke earlier about there being a specific part of the code of construction practice that deals with dust and air quality. Problems in that respect will be dealt with through the normal code of construction practice means.
Does Mr McKie have any further points to put to Mr Purnell?
No.
We will pause for a few moments to allow the witnesses to change over.
The two issues concerning access relate to the severance of Plumtreehall Brae and the alternative to the black path. Will Mr Sandland confirm what the impact will be of closing Plumtreehall Brae—as shown on drawing 5A, plan 1—by changing the bridge from a vehicular bridge to a pedestrian bridge?
The proposal is that Plumtreehall Brae will be closed to vehicular traffic but remain open to pedestrians and cyclists. At present, the bridge is steep and narrow. Some inconvenience would be involved for residents of Plumtreehall Brae, especially if they travel to and from Edinburgh, as they will need to go round the one-way system in Galashiels. We calculate that the maximum deviation for them will be approximately 3km. In our discussions with him, the lead objector, Andrew Brown, accepted that such a price would be involved in reopening the line.
Turning to drawing 6, plan 2, will you confirm that another pedestrian bridge will take account of the severance caused by the implementation of the railway?
The footpath that is marked "Footpath to be closed", which has steps going down from High Buckholmside to the existing amenity path, will be closed, but an alternative bridge is available 100yd to the right on the plan. Pedestrians will be able to walk across that bridge to gain access to the amenity path.
Convener, I will turn to the loss of amenity.
That is fine.
Loss of amenity may arise from the closure of the existing black path. Mr Rutherford gave evidence for group 61 on the alternative to the black path. Does he wish to adopt that evidence for this afternoon's purposes?
Yes.
Will Mr Edwards confirm when the promoter will discuss with the objectors issues such as tree and shrub planting around the black path?
I believe that some of those conversations have already taken place, specifically with objectors Mr and Mrs Fowler. I believe that the promoter has given a promise of some advance planting in that particular location. I cannot give an answer about planting around the alternative alignment, but I will provide an answer in due course.
Mr McKie now has a maximum of five minutes in which to make a closing statement on the objections in group 54.
I will rest on the evidence as given, but I want to put a question to Mr Coates, who is the promoter's witness on wildlife issues. Group 54 objectors expressed concerns about the impact of the line on the environment. Will Mr Coates give his professional opinion on the quality of the environment in the location and whether any natural regeneration will take place if the railway proceeds?
In certain areas along the route, there will be loss of existing trees. The small corridor alongside the black path provides some wildlife habitat, although it contains nothing of particular note either for the locality or for wider than that. Some trees will be lost on both sides of the path but there will be scope for additional planting in those areas. Particular loss of trees will occur only in one stretch. On most of the other parts of the route, the scope is quite wide so existing vegetation will probably be retained there. As the committee has heard, the additional planting that will take place will be discussed with locals. We will look to introduce native species so that, even in some of those areas where loss occurs, new habitats will be created to maintain the corridor in the medium and longer term.
We will now move on to group 57, for which we will hear evidence from Ian Wilkie, Alison Gorlov, Andrew McCracken, Bill Sandland and Steve Purnell. I suspend the meeting for a minute to allow the witnesses to come to the table.
Meeting suspended.
On resuming—
Group 57 relates to the objection on behalf of McLagan Investments Limited. The objector has chosen to rest on its written evidence.
I invite Mr Sandland to update the committee on new developments relating to group 57.
I refer the committee to plan 8. The Asda development will take place in the area of the heavy pink line on the left of plan 8. Asda intends to build a new store in Galashiels adjacent to the railway on land plots 726, 728 and 731. The area is initially scheduled to be acquired for temporary acquisition to facilitate railway construction.
Thank you, Mr Sandland. The promoter will simply rest on its written evidence on whether compensation is payable by applying the compensation code to the bill. The issues between the parties have narrowed considerably, although the new application has complicated the negotiations.
It seems to have done so. I wonder what the outcome will be if no agreement is reached in the near future.
We have to reach an agreement somehow. Crucially, the detailed design of the slope-stability works would enable us to determine the size of the plant and how work could be done. Undertaking those works in advance could be the best way forward, but that might be inappropriate with the committee still debating the issues.
Do you have a plan B?
Plan B is doing everything possible to ensure that we can build within the 5m, but at the moment we cannot say that that can be done. Building within the 5m could be much more expensive.
Thank you very much, Mr Sandland. Does anybody have any other points to make?
In the final analysis, if the bill as it is currently drafted is passed and issues with Asda have not been resolved, the scheme will provide what it currently provides for. We do not want to say that Asda will have to live with that, but whatever is in the bill is the bottom line.
That is exactly the point. Thank you very much, Mrs Gorlov—that is very helpful.
The promoter will rest on its written and oral evidence. However, it will obviously be able to let the committee have its consultation on the application, which may reveal a potential for joint working to bring the objection to an end.
Okay. We now turn to access. Bill Sandland and Andrew McCracken are the witnesses for the promoter. Mr McKie, do you want to invite one of the witnesses to provide an update on where matters stand in relation to access or are you happy to rest on what has been said?
The issues of access and health and safety as a result of increased traffic are largely covered by the promoter's proposal to ask for only the 5m strip. We are not taking the land for temporary works, so the issue is being resolved.
Okay. That concludes the oral evidence in relation to group 57. I will allow a few moments for the witnesses to change over.
Certainly, convener. I invite Mr Rutherford to give the committee an update on where matters stand with this objector group.
Group 59 consists of an objection from residents of Beechbank Place. The objection centres on the compulsory purchase of 14 properties that have six tenants. To date, we have had extensive correspondence with the owners and tenants. We have sent and received 53 letters and e-mails, had 10 telephone conversations and arranged four meetings. I refer members to drawing 10, which shows clearly our proposed alignment for the railway. You will no doubt have noticed that work on the new road proposals has started in the town centre. Those proposals and the alignment of the railway are a mirror image of each other, to ensure that whoever comes in first builds first. As part of the Asda development, work on the Gala inner relief road has started first.
Thank you, Mr Rutherford.
Given the volume of new housing that the promoter expects to come into the area as a result of the bill, do you think that it will be difficult or easy to find alternative accommodation for the residents of Beechbank Place?
There are two issues. The residents are a fairly disparate body, and it is not always possible to get everyone in the same room at the same time. There is a huge range of views. The residents asked us to examine a site similar to the one that they have within 100m of Tesco, the church and the cinema. The only such site that we could find is the one that they currently occupy. That was the starting point.
Is it possible to provide the residents with assistance in dealing with the affordability issues?
My legal adviser can tell you about the compensation packages that are available.
The compensation that landowners receive is the market value of their property, which of course is not the same as the price of what they regard as an alternative. I am not qualified to say what might be available through housing assistance more generally, which is outwith the compensation code. Mr Rutherford and Mr Wilkie might have more information on that.
I know enough about local authority housing to be able to guess what they might say.
Mr McKie, do you have further questions on acquisition of land?
I do not.
On loss of amenity, the witness for the promoter is Alison Gorlov.
The properties that we are considering are required because they are within the limits of the proposed railway, so they will have to be demolished and compensation will be paid. The promoter's view is that there will be a significant impact on amenity but that compensation will mitigate that impact. The promoter wants to rest on the position that has been set out in writing.
That concludes oral evidence for group 59 and indeed all oral evidence on objections to the bill—we should wait for applause for the committee. I thank all the witnesses and participants for their assistance in the smooth running of this and previous meetings. The committee appreciates your help.
Meeting continued in private until 14:35.