Skip to main content

Language: English / Gàidhlig

Loading…
Chamber and committees

Transport, Infrastructure and Climate Change Committee, 02 Feb 2010

Meeting date: Tuesday, February 2, 2010


Contents


Forth Replacement Crossing

The Convener (Patrick Harvie):

Good afternoon. I welcome everyone to the third meeting this year of the Transport, Infrastructure and Climate Change Committee. We have no apologies to record for today's meeting. As usual, I remind all present that mobile devices of any kind should be switched off.

Both items on today's agenda concern the proposed new Forth road bridge. Agenda item 1 is a project update. Under agenda item 2, we will hear evidence from the same witnesses on the public transport elements of the Forth Crossing Bill. I welcome the witnesses from Transport Scotland's Forth replacement crossing team: Frazer Henderson, who is the bill manager; John Howison, who is the interim project director; Mike Glover, who is the commission project manager; and David Anderson, who is the head of transport economics, analysis and research in the team. In addition, we are joined by Alan Duff, who is senior transportation adviser with Arup-Jacobs. Do the witnesses want to make any brief opening remarks before we begin the formal questioning?

John Howison (Transport Scotland):

Thank you for this opportunity. When I previously gave evidence to the committee on 23 June last year, I was able to give an informal summary of the scheme prior to the bill's introduction, which took place on 16 November. In addition to introducing the bill, we have made progress on securing procurement of the project, although completion of that will be subject to parliamentary authority. It should be noted that the project is to be delivered in three contracts. The bidding process has been started for the first of those contracts, for the new crossing and for the connecting roads, with invitations issued to two consortia, each comprising four major international contractors. The other construction contracts will be procured later this summer.

I can discuss in more depth how far we have got with the project if that would be useful at this stage.

It would be useful to hear whether there has been any change in the project milestones since our previous update in June. Is the timescale that was previously envisaged still the timescale to which people are working?

John Howison:

Yes. We published the bill on 16 November and started the procurement process for the principal contract on 4 December. Those dates are pretty much within a week of the timetable to which we have been working, so we are on target for delivering the project.

Assuming that the Parliament approves the proposals, are you still confident that 2016 will be the delivery date?

John Howison:

Yes, I am.

The Government is still giving a budget range of £1.7 billion to £2.3 billion. Are you confident that the project is on budget and that it will be delivered within that range?

John Howison:

Yes. I recall that there was a considerable discussion about costings the last time I appeared before the committee. I hope that the financial memorandum provides a lot of clarification. It says that we expect the work to cost around £1.345 billion at 2006 prices. We expect that the cost of the scheme that is the subject of the bill will most likely come out at £2.044 billion at outturn prices. On the uncertainties and particularly the inflation range, we are still working within a price range of £1.7 billion to £2.3 billion, which the minister announced on 10 December 2008.

How do you respond to the popular expectation that, in general, the figures for any large construction project will look much bigger by the end of the process than they look at the stage that the project we are discussing is at?

John Howison:

The critical time to reassess is when we get in the actual prices from contractors. That is what we are working to, and those prices will be submitted in December. Up to that point, we are simply looking at our expectation of the prices that the contractor will submit. Having said that, the form of contract that we are using has a very good history of delivering to the price that we receive for the tender. The normal range of pricing overrun for Transport Scotland road projects is around 3 per cent of the tender sum. That has been factored into the optimism bias.

The Convener:

Do you want to say anything about the current economic circumstances and whether they are impacting on the expectation of changed prices for such projects? It appears that we are now at the beginning of what might be a slow recovery, which will obviously impact on the prices for major projects. Is there anything that we should anticipate, based on how the economic recovery might progress, that will impact on the price of the project?

John Howison:

Our delivery partners and their experts, who have an audit role in relation to costs, have given considerable thought to the inflation range. I will make a personal observation. Civil engineering prices were fairly stable through the 1990s. In the first part of the past decade, there was a rapid increase in prices, but we are now going back to a stablish situation. We are looking at a very long cycle within which civil engineering prices have moved. I am fairly confident that, for the period for which we are tendering the job, our experts have made comprehensive allowances.

The Convener:

Okay. Perhaps other members will explore related issues in their questions.

In our previous session, we spent some time discussing communication and consultation with local residents. There was a general feeling that making some improvement in that area was possible—some people might think that that is an understatement. What has been done about consultation and communication with residents to improve matters since then?

John Howison:

The consultation process as a whole needs to be considered. It must be recognised that we are running a consultation strategy that looks at engineering, design and the environmental impact analysis, and are consulting landowners, communities, interested parties and the general public. There are four aspects to the consultation; last time, it tended to focus on the latter.

After the minister announced the project in December 2008, we undertook a fairly comprehensive exhibition in January 2009. We got quite a lot of feedback and made changes, which we brought forward in the spring and summer. We republished our thoughts in a series of information displays in August 2009 and continued to consult local interests. That has resulted in further changes to the project. We have undertaken quite a bit of consultation with community councils and community groups, particularly in the South Queensferry area. We have gone to groups and heard what they had to say, and we have gone back to give them further information on the aspects on which they required it. We have gone through quite a comprehensive process.

In summary, consultation depends on the consultees being informed. The constructive observations are the ones that we find most useful. We have systematically introduced new ideas into the design to improve the product. The proof of the effectiveness of that is shown in the decisions that have been taken and the changes that have been made. Major adjustments followed the January 2009 exhibition both in the Ferrytoll region and at Queensferry. I can say more about that if you want. In the spring and summer meetings, we looked at a number of other refinements, but at that stage, because the design was firming up, that was more limited. We looked at relocation of the principal construction site. In autumn, as we were still continuing with discussions, we turned our thoughts to the construction haul road at the south end and how we use Society Road in South Queensferry. Discussions will continue throughout the bill process. At the same time, ideas have also been rejected where we felt that the local benefits did not warrant the impacts of the changes.

When we gave evidence previously, one of the areas that you were particularly concerned about was the quality of our telephone service. After that, we provided training to everybody who was going to be involved in the service so that they would have a script to refer to and would be able to give answers directly. Having said that, the number of telephone conversations held after that has been pretty small—there have been only one or two a month.

Can you identify any key concerns highlighted by residents and other interested parties since June 2009 and explain how you have addressed them?

John Howison:

The principal one was the issue of the construction compounds. The project will require three construction compounds for the works, which we are seeking to secure and provide to the contractors. One is at the north end of the scheme, adjacent to Ferrytoll roundabout. One is at the south end of the scheme, adjacent to junction 1A on the M9. The other is to be positioned in the vicinity of South Queensferry—it is to be the principal site for engineering works. There will of course be supplementary sites. For example, if the contractor decides that he wishes to undertake the erection and assembly of the bridge components locally, he will need to find accommodation for that. We have not covered that.

As I said, the controversial area is the one at South Queensferry. You are aware that we purchased land for a previous scheme at Echline fields. As the new scheme does not require tolls, the amount of land that is required is much less than the amount that we acquired, so we sought to place the construction compound on the ground that was left over, which was sandwiched between the new road and the housing at the Clufflats, Springfield and Echline.

Considerable concern was expressed about that proposal, notwithstanding the amelioration measures that we proposed to limit the environmental impact. We took on board that concern and examined whether an alternative site on the west side of the new road would be suitable. On an engineering review, we concluded that that would be more suitable, although it would not have the full range of benefits that the original site would have had. As a result, we decided to promote that alternative as our favoured option. We have included land in the bill for that and, subject to Parliament's granting us powers to acquire that land, we will proceed with that site.

As a consequence, the road that we originally proposed to provide access from the site compound to the site, which was to have been on the east side of the new road, was not suitable. We have therefore considered how the road might be aligned to run from the new site compound situation to Society Road, to give access not only to the road works that are immediately adjacent to the site, but to the bridgehead for constructing elements of the bridge at the south abutments and to the marine activities, to take staff to and from the marine sites.

That proposal was the subject of a couple of meetings with the Clufflats residents and a meeting with Springfield residents. We have modified our original proposals with a view to keeping them as far to the west of the communities as we can.

I will ask about the site compound, which you mentioned. What is your position on the site that you proposed initially? Is it still in the bill or has it been categorically ruled out?

John Howison:

If we are given consent to procure the land that is required for our favoured site, we will not consider the original site for construction purposes again. However, if Parliament decided that it did not wish us to have powers to purchase the land, the proposal would come under the heading of deemed planning consent.

People are concerned that the ability to use that land still appears to be on the table and in the bill.

John Howison:

The proposal was included in the environmental statement, but that statement is duty bound to include in its scope ideas that we considered and ruled out.

Our position is clear: provided that the land that we seek in the bill is made available, we will not use the land between the road and the community at Echline, Springfield and the Clufflats as a construction site.

Shirley-Anne Somerville:

The use of Society Road has raised great concerns. The communities have not yet been told how long the road will be used for access to any site compound and the estimates vary quite dramatically. Can further work be done to give people clarification on the use of that narrow road in the village?

Mike Glover (Transport Scotland):

Society Road will be used for the duration of the construction of the marine works, but only the section that adjoins the barracks will be used—that is the only part of the road that we will use during the construction sequence.

Access along the other parts of Society Road is limited purely to early mobilisation. For example, to be able to get to the area that adjoins the Clufflats, where the haul road will cut through, we will have to gain access along Society Road for the first few months of construction to be able to carry out modifications to utilities, drains and so forth. Apart from that, we will not use Society Road at all in that period. I think that we have explained that but, in case it is not clear, that is the position.

We are talking about Society Road being used for a few months for the haul road.

Mike Glover:

A few months—a number of months, yes.

It is increasing quite a bit—it could be quite a few months more.

Mike Glover:

I am sorry—I will explain. The works that have to be done are the early mobilisation works, which are to do with adjusting drains, breaking through certain areas and minor earth works. Such work takes no more than a few months but, because of its nature, things sometimes arise. The intention is not for it to go on for longer than a few months.

Shirley-Anne Somerville:

I have one last question on that. It might still be useful to allow the communities to sit down with Transport Scotland to discuss the transport modelling that has been done so that they can get an idea of how the figures have been developed for the different roads that you will use, which will be used differently after the bridge has been built. I know that the figures are available, but it is sometimes useful to drill down behind them so that people get an understanding of where they came from. Would that be a good sign of openness, in the spirit of the consultation with the community that you are now taking on?

John Howison:

Because of the refinements that we have made to the scheme and the progressive way that we made them, the information on traffic has come relatively late in the process, which we recognise. It first became available round about the late summer. As a result of that, at any time that we have gone to communities, we have made a point of demonstrating to them the flows that arise out of that information.

The derivation of the traffic flows is fairly complex and depends on three layers of modelling. I do not know whether it would be of much benefit for a lay person to try to grapple with that. I will test you out by asking Alan Duff to explain the complexity of the traffic modelling to you.

Shirley-Anne Somerville:

Perhaps I can save Mr Duff some of the bother. I suggest that, considering that it will have a large impact on the community, it would be useful if some way was found of explaining the information to lay persons, whether they are MSPs who are involved in the committees or members of the affected community. There must surely be a way of explaining it to people such as me and to the community—perhaps not today—in a way that allows them to ask questions about it.

John Howison:

The major concern rests in the South Queensferry area. I do not think that there is the same concern north of the estuary. Therefore, I undertake to approach the Queensferry and District community council and find out whether we can use its good offices to put something on.

I hope that you will approach other community groups as well.

I have a request for a supplementary question from Margaret Smith, whom I should have welcomed to the committee at the beginning of the meeting. I do that now for the record.

Margaret Smith (Edinburgh West) (LD):

I am here as the constituency member for Edinburgh West, which includes South Queensferry, Kirkliston and the surrounding areas. By the witnesses' admission, that is the area in which local residents are likely to face the most disruption as a result of the scheme.

I will focus on the construction period, which will be in excess of five years and will result in a great deal of disruption and loss of quality of life for a number of my constituents. I understand that, under the bill, it is intended to take environmental protection rights away from local councils. I have concerns that that will leave residents without statutory recourse to their council on concerns about, for example, the hours that the contractor and sub-contractors will be able to work under the code of construction practice, given the caveats that exist.

I have spoken to people at the City of Edinburgh Council about the issue, and most of us accept that an independent professional assessment of whether what a contractor was doing was acceptable would benefit residents. Can you explain the thinking behind your suggested approach of taking away those safeguards? Why is that necessary? Can you think of other projects in which such an approach has been taken?

The Convener:

Before the witnesses answer, I remind everyone that although there are perfectly legitimate questions about the practical aspects of the project, the purpose of today's session is not to undermine the Forth Crossing Bill Committee's work in scrutinising the bill itself, as responsibility for such scrutiny properly lies with that committee rather than this one.

John Howison:

I will relay my understanding of the matter; if I get it wrong, Frazer Henderson will correct me very quickly.

We have created an envelope of environmental situations that we propose to police, and—provided that we stay within that envelope—to take outwith local authority supervision. My understanding is that if we breach that envelope, enforcement would revert back to the local authorities.

The project concerns three councils. Our aim and incentive is to achieve consistency throughout the project, particularly with regard to the estuary and the marine work, which will involve different local authorities, but very similar operations. Frazer Henderson may want to add something on the issue of noise.

Frazer Henderson (Transport Scotland):

Noise is a good example. John Howison mentioned that any regime would be operated by three local authorities, each of which could have different policies, meaning that a consistent approach might not be taken. That could confound the delivery of the project—and certainly its delivery within the set timescale.

We have sought, under the bill, to place in the code of construction practice a particular noise threshold, which the contractor cannot breach without action being taken. If the contractor wishes to operate equipment at a higher noise level, an application will be made to the relevant local authority. The local authorities still have a role in the construction process, under section 61 of the Control of Pollution Act 1974.

We have not taken away all the local authorities' responsibilities—we have said that, in order not to confound the delivery of the project and the very tight timescale in which it will operate, we are setting thresholds in the code of construction practice that we believe are reasonable. If those thresholds, or some of the terms that are applied to the achievement of them, are breached, the local authorities can step in. Does that address the issue?

Margaret Smith:

That seems to cover a situation in which a contractor or subcontractor thinks they might breach the code of construction practice. The code has a lot of caveats: it does not say, "You will not do this," but, "You won't do this, but in certain circumstances you might be allowed to." What happens if the residents who are affected—as the people who live close to the haul road down on to Society Road will be for many years—consistently find that there is more noise than they were led to believe there would be, or that there are problems?

What rights does the local authority have to step in and act proactively? You give the example that a contractor who thinks that they might breach the code has the right to go to the local authority, but that is a different matter.

Mike Glover:

There are a number of aspects that one must take into account. The first is the interesting aspect that the code of construction practice sits underneath the environmental statement, which contains additional noise constraints. The code of construction practice is effectively a larger envelope within which there are other restrictions. At the Clufflats, for example, lower levels of noise constraint are offered.

Secondly, the contractor has to apply what are known as "best practical means". To the person in the street, that might just be a bunch of words that do not mean very much but, in the industry, they mean a lot—they mean that the contractor must exhibit certain aspects of noise control.

Thirdly, noise will be monitored at strategic locations. Appropriate positions will be used for that—obviously, there is no point having a noise monitoring station at a location where there is no construction, or deciding on a location for five years, because there might not be work there for all that time. That addresses the point that you were concerned about. If there is a complaint, how will it be recorded, and what mechanism will be used for involvement? There will be such a mechanism, as there will be monitoring of activities.

The final characteristic is that Transport Scotland will have advisers, who will review the contractors' submissions before the works are carried out. Transport Scotland will therefore be able to ensure, as far as possible, that the best practical means are being applied to the activities that are undertaken. A number of thresholds and protections are being overlooked, but they are already in the documentation.

Does that help to address the point about safeguards?

Do you want an honest answer?

Mike Glover:

Actually, yes.

I would like you to pick up on the small question that I asked at the beginning. Is the way in which local authority powers have been dealt with in this instance typical of other transport infrastructure projects?

Mike Glover:

All projects are different. As you know, I was involved for 12 years with the Channel tunnel rail link. We exercised the sort of level of controls that I have spoken about today.

By inference, your previous involvement was not in Scotland.

Mike Glover:

No—I am sorry. My reference is down south.

We can perhaps explore those points with the Scottish Government, if it is able to provide further information.

Thank you for your indulgence, convener.

Alison McInnes (North East Scotland) (LD):

I want to explore further the matter of community engagement. Mr Glover spoke about monitoring this lengthy, five-year construction project. What plans have been drawn up to engage with and be accessible to local communities over the lifetime of the project?

John Howison:

We recognise that there should be some on-site facilities for that purpose, and we have been considering creating an education and training centre with a drop-in facility for local residents, so that somebody from Transport Scotland would be on hand, should something happen.

The communication requirements in the code of construction practice go much further in relation to the information that must be given to people in certain circumstances to provide them with a pre-indication or forewarning.

Mike Glover:

From previous experience, we know that it is vital to advise the community of things before they happen. Therefore, the role of the community liaison officer is important. Community liaison officers will be resident on site and will be the focal point for the community, and regular newsletters will be sent round the community.

For activities that are considered to be unusual, the local community will be given specific advice. Technology moves on, so that will be done electronically, by e-mail and so on, and not just by mail drop. However, although constant communication takes place, the most important thing is that there is an identifiable person who the community can always get hold of.

Alison McInnes:

In his introduction, Mr Howison talked about an education and training centre. That all sounds very one way. Good communication and engagement work both ways. What is in place to listen to the community and to react to any concerns that arise as the project develops?

Mike Glover:

I am glad that you asked that question. A key performance indicator will be attached to the response to communities' questions and queries. Those will have to be closed out within a certain period, depending on the severity of the concern. The KPI will be in the public domain and there will be some checks and balances. That is about outreach. It is not reactive; it has to be proactive, and the community is very much part of it.

What progress have you made on acquiring the land required for the project through voluntary agreements? To what extent will you need to exercise the powers of compulsory purchase that are contained in the bill?

Frazer Henderson:

We have not entered into any voluntary agreements on the taking of land. The book of reference and documentation associated with the bill set out the land that we wish to take compulsorily. Over the past year we have been in discussion with landowners about the taking of their land and what that might mean for them in terms of severance and the remainder of their land. At the moment, our presumption is that, subject to parliamentary approval of the bill, we will put forward a general vesting declaration in the spring of next year to acquire the land compulsorily. The advantage of taking land compulsorily over a voluntary process is that you get what is known as a clean title to the land, which means that any servitudes or encumbrances on the land disappear. If the land were acquired on a voluntary basis, such issues would have to be negotiated individually, which could be time consuming, frustrating—in terms of the delivery—and, potentially, costly. At the moment, our policy is that we will take all of the land required for delivery of the scheme on a compulsory basis.

Can I be assured that you have entered into dialogue with and contacted everyone who will be affected by that?

Frazer Henderson:

The book of reference details the land ownership that we are aware of. You will appreciate that there are pockets of land for which we have been unable to identify title. Those in the book of reference for whom we have title we have contacted. Where we have no title, we have put up notices on the land asking people to come forward. Rigorous checks have been undertaken in the register of sasines, with Companies House and so on to ensure that we have as great a coverage of ownership as possible.

The Convener:

You described compulsory purchase as an advantageous process, the advantage being, as many people will understand it, on the Government's, or Transport Scotland's, side. Is it not reasonable to recognise that the Scottish Government represents the interests of individuals? The Scottish Government is their Government, so should it not balance the interests of both sides instead of simply seeking the most convenient route?

Frazer Henderson:

Compulsory purchase is indeed a convenient way to acquire land. The fundamental issue is the requirement of the land in the first place. We have sought to draw the limits of deviation for the scheme tightly so that, in effect, we are taking only the land that is required to deliver the scheme and to provide some working room for the contractor. We have taken cognisance of the impact on landowners by reducing our land take. We looked very closely, and continue to do so, at whether we could mitigate the impact for a landowner by reducing the land take even further.

John Howison:

There is an element of benefit to the landowner. Under compulsory purchase provisions, once the land is taken, the owner is entitled to an advance payment of 90 per cent of the assessed compensation right up front. The two alternatives are that the landowner does not give access to the land until the deal is finally done, which could mean that we did not get it within the project's timescale, or that the landowner agrees to give early entry to the land and then has to argue about the level of compensation with the valuation office. The compulsory purchase scheme provides some security and cash up front for the landowner. It is a mutually beneficial arrangement.

If a particular landowner saw it as being in their interest, would there be any harm in offering them the opportunity to enter into a voluntary process of negotiation if they so chose?

John Howison:

On a few occasions we have gone through a process of voluntary acquisition in parallel with compulsory purchase. One such situation was the M74 completion. The amount of professional time taken up in pursuing legal completion of voluntary acquisitions is very onerous on landowners and on us. We would not normally go down that route, and we will not use it in this case.

Thank you. That answer was clear.

Given that the budget costings for the project have been widely known for some time and that only two consortia will bid to construct the Forth crossing, what are you doing to ensure competitive bids and best value for the public purse?

John Howison:

Two consortia seek to win this particular prize so there will be serious competition between them. One of the issues is whether we keep both consortia right up to the point at which they submit tenders. We have recognised that issue and have approached it in two ways. One is through the agreement of Parliament to a contingent liability, so that if something untoward and unexpected should happen that results in the competition not proceeding, we will pay the consortia a certain level of compensation. The second is that, on award of the contract, the runner-up will receive a different sum of money as a non-success premium. Therefore, there is an incentive for the contractors to carry on with the process competitively in the knowledge that the costs that will accrue to them during the process—and it will be an expensive process—are, to some degree, shared.

What will be the scale of the non-success premium, and has it been used before in projects, or are you going to use it because there are only two bidders?

John Howison:

I will answer the second part of your question first. The tender support regime was designed before we knew that there would be only two bidders, but it was done in the expectation that such a large contract would draw in consortia, so it would be likely that we would be soaking up a large proportion of the world's top contractors. However, we never believed that we would get more than three bidders, even in the best circumstances, and, as it happens, there are only two.

What is the sum of money for? It is a repayment of half the amount of money that the contractors have expended on estimates up to a limit of £5 million.

Alex Johnstone (North East Scotland) (Con):

A number of correspondents with varying levels of understanding of and expertise in this matter have expressed concerns about the eventual cost of the project. How confident are you that you will not end up with two bids that deviate significantly from the expected cost when compared with other similar projects that have been completed in recent years in other parts of the world?

John Howison:

I cannot add to what I said before about confidence in the price. The prices have been estimated by competent, world-class consultants and have been examined by quantity surveyors who are experienced in this type of project. The people who are involved in the estimating have built this type of bridge before—they built Øresund bridge and Stonecutters bridge—and are fully aware of the work that is involved. Therefore, I am relatively confident about the range of prices that we have put forward within a stable financial macroeconomic climate.

The Convener:

I want to follow up the issue of the non-success premium. This is a difficult time in the public sector, as Governments—not just the Scottish Government—talk about cuts in the coming years. Surely, there must have been some concern about how the payment might be perceived. At a basic level, a lot of households are probably familiar with the practice of paying a small amount of money for a quote when someone is going to do something to their property, so the basic principle might not be outrageous. However, given the scale of the payment to the unsuccessful bidder and the possible perceptions of that, did you not consider a different approach to your presentation of it?

John Howison:

Yes, of course. The starting point is that estimates do not come free and firms must consider the amount of money that they are going to spend on estimates before deciding whether they can undertake an estimating process. If they agree to enter an estimating process and they are given no support, they must include within their tender for undertaking the work a sum of money that will allow them to recover the expenditure from the unsuccessful bids in which they have been involved. In other words, over the cycle of their business activities, they must, in one way or another, meet the cost of the tenders in which they are involved.

If the tenders are supported, the contractor does not have that sum at risk and, therefore, need not factor it into his winning tender. So, on the presumption that a tender will be awarded, it is not an extra cost to the project; it is simply a cost that is placed with the unsuccessful bidder rather than a risk premium that is repaid to the successful bidder. The effect should be cost neutral.

The second issue is whether the premium had to be set at the chosen level. When we first put out a call to interested contractors, we looked carefully at the level of payment that might be involved and suggested a lower level, but we got a very clear signal from the industry that a lower level would not attract bidders. On the basis that we would get only one shot at attracting contractors to a project of this scale, we took the view—having regard to the fact that a number of contractors told us that more support was necessary—that it would be in our interest to provide extra support. That is how the sum of £5 million arose.

The Convener:

So, the sum was determined through a process of asking how much the contractors wanted. However, even accepting the argument that the effect is cost neutral, there is the question of perception and presentation. Did you not think about calling the payment something different? "Non-success premium" sounds like a bad joke, does it not?

John Howison:

Forgive me, I have a history of having inadvertently unfortunate names for things, but I will leave that aside. The important feature is that there will not be complete reimbursement of costs, because it is important that bidders price to win the contract rather than simply a consolation prize. It is a bit late to consider whether another name would have been better; that is simply the name that I bring to the committee today.

How about "failure premium"? Failure is another word for non-success.

John Howison:

It is not a failure premium, because bidders' presence at the final tender will mean that we still have a competition and competitive attitudes to putting in prices. If that were not the case and the bidder withdrew prior to putting the bid in, we would be looking at a failure.

The design for the main structure of the new crossing has three towers, rather than the more usual two. Why is that? What impact will that have on the budget?

Mike Glover:

It is to do with structural mechanics and where we can place foundations. I looked at early civil engineering journals that go back a long way—pre-Forth road bridge—and it was interesting to learn that the route that we are taking is the route that people wanted to take, but it was beyond the technology of the day to do so, because the spans were much too large. As you know, the existing bridge has a very long span anyway.

There are very few locations in the Forth where we can place foundations. Beamer rock is the obvious location for a foundation, but the next one is a long way south, towards South Queensferry. Indeed, the foundation that we have located is in reasonably deep water. It is not in the shipping channel—it is a long way away from that—but the technology is well beyond the technology that was employed elsewhere. To answer your question, there is a need to find suitable locations at a reasonable distance. The distance from Beamer rock will be about 650m. Ideally we would make it less than that, but the depth of the water precludes our doing so, so 650m is about the optimum distance.

John Howison has reminded me that another reason is that Beamer rock is in the middle of two shipping lanes. A different approach would take us beyond the bounds of sensible spans. You will have read about proposals for a bridge across the Strait of Messina between the toe of Italy and Sicily; the proposal has never gone forward, because as the spans go up, the costs go up. We want to keep the spans as short as possible—that gets us to 650m as about the optimum distance.

The technology that we wanted, which earlier studies identified before we became involved, was a cable-stayed bridge rather than a suspension bridge. The political question was, "Why use the same technology on the new bridge as is used on the old one, when that technology has generated severe problems?" Therefore, we selected a cable-stayed bridge, which is at the forefront of technology and a great advantage of which is maintainability and replaceability. Each cable that you can see on the montage and diagrams that we produced can be recovered and replaced while the bridge remains operational. With a suspension bridge, the whole cable would have to be replaced, as you know. The answer is a combination of founding levels and structural mechanics—I hope that that makes sense.

Charlie Gordon:

Yes. That is a comprehensive answer, the second part of which anticipated my next question to a substantial degree.

Transport Scotland has advised that the design of the arrangement of the cables that will support the bridge deck of the Forth crossing is unique. You have explained why that novel design was chosen, but you will understand that there may be concerns or perceptions that it might, because of its unique aspects, be more expensive and subject to greater risks than a standard design might be.

Mike Glover:

I would not say that cable-stayed technology is common or garden technology, but it is the normal technology that is used for a bridge of this type. We have just finished Stonecutters bridge in Hong Kong; it has just two towers, but its span is much longer than the spans of the proposed bridge—it has a span of 1,000m rather than two 650m spans. There is nothing particularly unique about cable-stayed bridges. The characteristic of the proposed bridge that makes it slightly different from most other bridges is that it will have three, rather than two, towers, which has been referred to. We simply deal with that through the structural mechanics—it is not a huge risk item that is added into the mix. I would not like to use words such as "unique" about the technology; rather, I would like that word to be applied to the bridge's iconic nature.

You mentioned a bridge in Hong Kong, which seems to be a kind of comparator. How much did it cost?

Mike Glover:

The problem with cost is that it is shrouded in all sorts of numbers.

Indeed. How true.

Mike Glover:

The only way to answer the question that has been posed is by stripping away some of the numbers. All I can say is that the designers of the new bridge are the designers of the Stonecutters bridge, and they are now designing the Macau bridge, which will be the longest-span bridge in the world. The designers are the same, the technology that they are employing is the same, and the people who have arrived at the design estimates and so on are, by and large, the same. Therefore, the numbers that we produce must be relevant and must be given credence.

The cost of a bridge is different from the cost of a project. The figures that we are talking about are the costs of a project. The cost of the bridge, which is of the order of £550 million to £600 million, is included in the financial memorandum—I am sorry; I do not have the exact cost in front of me. That cost is modest; it is the sort of cost that we would expect for such a bridge. I hear figures of £1.7 billion to £2.3 billion being bandied around for the bridge and people asking where the big numbers are coming from, but such figures are not the costs of the bridge; rather, they are the costs of the project. The cost of the bridge is a small component of that. As I have explained, the designers of the bridge designed the other bridges that have been mentioned. Members must give credence to what we have put forward as having been put forward on a rational basis; it has not simply been plucked out of the air.

Charlie Gordon:

It remains to be seen whether saying "Trust me: I'm a structural engineer" goes down better with the public than saying "Trust me: I'm a politician."

I gather that when we talk about the cost of the bridge element of the Forth crossing project compared with the cost of the bridge element of the Stonecutters bridge project in Hong Kong, we might be talking about a ratio of 2:1 in comparative costs.

Mike Glover:

I am not the best person to talk about the cost ratios between China and here or to speak about different accounting practices in different countries. A comparison between Stonecutters bridge and the Forth crossing is inappropriate, as costs must be seen in their geographic and environmental contexts, and there are differences. However, the numbers that I have given are comparable.

John Howison:

I would like to provide some clarity. Mike Glover gave the price of the bridge, which is £500-odd million. That is not to say that that represents a quarter of £1.7 billion to £2.3 billion. To that price need to be added risk allowance, optimism bias, VAT, inflation and the cost of capital, for example. If we say that the whole project is the road works, those various other items and the bridge, what element is the bridge? The bridge represents about 70 per cent of the total cost. Mike Glover was saying what the basic cost would be if the bridge were built now, no VAT were paid on it and the optimism bias and risk elements came out favourably. That is the comparison with the bridges that have been built.

Do you have figures for how much building a two-tower cable-stayed bridge would cost, even if that required the use of thicker cables and was less aesthetically pleasing?

John Howison:

We have not designed a two-tower cable-stayed bridge, which would be more expensive.

Mike Glover:

Such a bridge would be beyond the bounds of what is being built in the world—it would go beyond the technology that we could reasonably apply and would involve taking enormous risks for a cable-stayed bridge. Such a design would involve missing out Beamer rock. The span would be more than 1.3km—people would gulp.

John Howison:

The cost of a bridge comprises the cost of foundations, the tower and the decks. Moving from three towers to two saves to an extent on foundations and the number of towers, but the deck becomes much more expensive. The whole exercise is to optimise the bridge's overall cost. We are relatively confident that if the bridge configuration were different, the bridge would be more expensive.

Shirley-Anne Somerville:

The policy memorandum says that

"The embodied carbon assessment is not yet complete",

but an initial calculation suggests that it will

"be in the order of 121,000"

tonnes of CO2. Will you describe how that figure was calculated and advise us when the final figure will be available?

Mike Glover:

The policy memorandum is clear about the issue—the way in which you related the figure shows that. As part of the tender process, we are asking contractors to give us their response on carbon. When we have that information, we will have a better figure with which to respond to your question.

Shirley-Anne Somerville:

Is a process being completed to ensure that that figure is kept as low as possible? I accept that, until you have the tenders from the contractors, you will not know their best estimates, but will you then try to ensure that the embodied carbon level is kept as low as possible rather than just pick a figure?

John Howison:

The competition will be decided on two elements—one is price and the other is quality. On quality, we are considering how the contractor approaches risk, wider social benefits, the organisation of management and how much carbon the product will generate. We recognise that the project will cost so much in pounds, shillings and pence and so much in tonnes of carbon and we will assess both costs in the final award assessment.

Shirley-Anne Somerville:

The policy memorandum also says that, in 2032, the additional carbon emissions that will be due to the Forth crossing might be 20,317 tonnes. Why did you pick 2032? That does not relate to the Climate Change (Scotland) Act 2009 or anything else on the general climate change agenda.

John Howison:

I will definitely ask Alan Duff to explain the choice.

Alan Duff (Arup-Jacobs):

The answer is simply that 2032 is the year for which the traffic model predicts traffic flows. It is 15 years after the bridge opens and we have traffic figures for that year, which we can feed into the carbon calculation.

Given that, do we have figures for each year?

Alan Duff:

We have figures for 2017 and 2032.

Shirley-Anne Somerville:

So, we just extrapolate from the figures for those years.

Is it the case that the figures for carbon emissions from the Forth crossing do not include any increase in emissions that would result from a cable replacement on the current Forth crossing?

Alan Duff:

That is correct.

John Howison:

The figures that were quoted in the policy memorandum were produced by a conventional traffic model. However, we are concerned about the way in which that replicates real traffic conditions, as the crossing operates under stop-go rather than free-flow conditions, so we have undertaken further estimates using a microsimulation model called Paramics. As a result of that, and taking into account the amount of carbon that cable replacement would generate, our current view is that the new bridge will be carbon neutral, in comparison to a cable replacement operation, up to the year 2025 or thereabouts.

The Convener:

It would be useful if you could provide in writing to the committee the calculations that lead to the conclusion that the new bridge will be carbon neutral. It is perhaps a bit too complex to go into here, but it would be good to have the figures on that at some point.

I want to ask not about the carbon emissions that are embodied in the crossing, but those that arise from traffic flows. Am I right that the calculation assumes that the existing road bridge will maintain its position—as described by the Scottish Government—as being closed to car traffic up to that period?

Alan Duff:

Yes.

Has there been any calculation of what would happen to traffic flows and the resulting emissions if that very brave assumption did not hold until 2032?

Alan Duff:

No.

There is no intention to do that?

Alan Duff:

No.

The figure of 20,317 tonnes—which we acknowledge is an estimate at this point—is an annual figure, so the cumulative figure for emissions by 2032 would be around a third of a million tonnes.

Alan Duff:

Yes.

As has been mentioned, the crossing is a very long-term project. What is being done to minimise the disruption to the existing—and very busy—commuter routes at various stages of the project?

John Howison:

The project will involve several areas of extreme sensitivity. The most difficult part of the construction will take place around the Ferrytoll junction, north of the Forth, where the new bridge joins in. We need also to weave in fresh ramps onto the public transport facility of the existing bridge. It is fairly complicated—I invite Mike Glover to explain how that will be done.

Mike Glover:

Do you want me to explain how the Ferrytoll junction operates?

John Howison:

Yes.

Mike Glover:

You have a go, and then I will answer.

John Howison:

The first point is to recognise the community routes that exist, such as the route from Dunfermline—Castlandhill Road—and the route up from North Queensferry. The design has been altered since it was first put forward in January 2009 in order to pull those routes out of the general conglomeration of traffic going through the Ferrytoll junction. That will allow much of the construction work to go on without impacting on those local roads.

South of the Ferrytoll junction, the construction will involve a fairly extensive viaduct: a bridge will be constructed with lots of piers. North of the junction, the road needs to be fitted in between the existing earthworks and rock cuts, and the levels and alignments in that area will need to be adjusted. [Interruption.] I have just had something pushed at me. It is so complicated that I would prefer to provide the committee with a set of drawings to show how it can be done. Needless to say, we have looked at the design in some depth and we have presented it to the North Queensferry and district community council. It is a working policy that is available to the contractor but, at the end of the day, the contractors must work out their own way of proceeding within the constraint that they must keep two lanes of the M90 operating at all busy periods during the process.

The drawings would be helpful.

Members have a copy of the scheme map in front of them—you might refer to that.

John Howison:

I am afraid that that map is at a different level of complexity. You will appreciate the fact that bits of road will be moved around, backwards and forwards, in five different phases to accomplish the project.

If you can provide that information subsequent to the meeting, that will be helpful.

Mike Glover:

It is a question of the level of detail. I was not sure what you wanted. As John Howison says, the best thing would be to look at a series of phased plans. Looking at the plan will just show you what the plan is; it will not show you how we will get there.

As John Howison says, the first priority is to ensure that North Queensferry is not disadvantaged in terms of communication. Therefore, the first thing that we will do is move the B981 and Castlandhill Road, so that communication from North Queensferry into Rosyth and further north will not be impacted on by any of the construction activities. Secondly, we will try to avoid rock cut into the Ferry Hills adjoining the railway. We will also, as John Howison said, maintain two carriageways—both north and south—at all times during the construction sequence. After that, as members will see, it is a question of shifting from one thing to another. However, the priority is to get the B981 out of the way so that there is a secure way out of North Queensferry that is not confused by construction. The other thing that we must do is secure the bus routes from the Ferrytoll park-and-ride facility. We have directed a lot of attention to ensuring that the routes to and from it will be as secure as we can make them.

Given the recent tragic loss of life on both the Forth and Tay rail bridges, can you explain what you will do to ensure the safety of those who will be working on building the Forth crossing?

John Howison:

A fairly elaborate safety hierarchy has been established in the UK under legislation. We have certain responsibilities to ensure that we employ competent and experienced contractors and designers. Under the legislation, the responsibility for maintaining safety on the site then passes over to the principal contractor. We must recognise that there is an industry-wide responsibility to ensure site safety and that it is not for us to try to impose measures on the contractor. The contractor will need to set out the measures that it will take and specify to us before each operation how it intends to proceed safely. It will seek to maintain its own reputation as a contractor that preserves life rather than loses it.

It is a serious question, in the light of what has happened.

Mike Glover:

Although the contractor will adopt his own construction techniques, we have produced what we call the specimen design in which we have designed the construction with safety in mind. For example, we envisage many of the components for the marine works being pre-cast components that are made in a safe location and floated into position, thereby reducing the risks of working in a marine environment. We cannot avoid all the risks, but that is where the planning comes in and the construction techniques that are chosen often reduce those risks. For example, a cable-stayed bridge is a safer type of bridge to build than a suspension bridge.

Can you provide an update on the current status of the main cables and the cable anchorages on the Forth road bridge?

John Howison:

That is a task for the Forth Estuary Transport Authority. I think that it will make an announcement on that in the near future.

We need to recognise what has already happened. There has been a lot of strength in the existing cables. The dehumidification work is not going to repair the damage that has already been done, nor will it stop some aspects of the damage from continuing. For example, a wire that has been corroded will have less strength than a wire that has not been corroded, even if it has not actually broken yet, because the corrosion produces pitting and stress-concentration points in the wire.

We also need to recognise that there is an array of difficulties with the bridge. The cable is the one that immediately comes to mind, as well as the anchoring, which has yet to be investigated. However, there are also issues around surfacing, which currently needs to be replaced every eight years or so, and the length of time between each resurfacing is decreasing. There are issues around the main bearings on the bridge, the expansion joints and other things that can be damaged by heavy goods vehicles. Those issues must be dealt with on top of the normal maintenance, such as painting, that must be done in order to keep the thing up in the air. Around 86 per cent of the bridge's strength is required to keep it up in the air; the rest is what is used to carry the load of traffic. In addition to that, there are operational problems with the bridge. Because it does not have a hard shoulder, maintenance operations will inevitably cut down the capacity of the bridge and, when incidents occur, disruptions cannot be avoided. Further, it is not an all-weather bridge—it is not possible to put wind shielding on the bridge anywhere but in localised areas around the towers, because wind pressure would sway the bridge out of alignment.

We are where we are with regard to the cables. Strength loss has already occurred, which means that, without recabling, we would not be able to get back to the factor of safety that was originally considered appropriate. A range of other issues mean that the bridge is less than suitable as an all-weather, all-purpose connection between Fife and the north-east and Edinburgh.

Alison McInnes:

You said that the state of the cables is fundamentally an issue for FETA. However, given that your project includes the bridge as a transport corridor, it must be an issue for you, as well; you need to be sure that it can perform the task that you want it to perform. I appreciate that there are issues around loading but, given the catalogue of problems that you have outlined, do you have any regrets about the fact that financial constraints mean that the new bridge will not be multimodal?

John Howison:

No. We think that the current solution is better and represents better value for money.

You ask about our confidence that the bridge will be usable as a multimodal transport facility. The bridge has lost 8 to 10 per cent of its strength already. By taking off the traffic loading, we would be removing about 14 per cent of the load that the bridge must bear. The public transport loading is very much less, and if the dehumidification is successful, as we hope it will be, the bridge will come to us as a free good, at least in terms of capital cost—we will not have to replace the cable once the bridge's use is changed. With regard to those aspects of the bridge that are damaged by repeated punishing by heavy goods vehicles, it is true that buses have axle loads that are comparable to those of HGVs, but there will not be nearly as many axles going over the bridge if it is used by buses rather than HGVs.

The Convener:

We will deal soon with item 2 on the agenda, under which we will consider aspects of the Forth Crossing Bill that will overlap slightly with some areas that we have touched on so far, but I have a final question before we do so.

You anticipate that FETA might be making announcements in the near future. We are all expecting the engineering reports on dehumidification to be published next year, so are you saying that there will be an announcement sooner than that?

John Howison:

I think that FETA regularly updates its board at board meetings, and I presume that it will continue doing what it normally does.

It will do what it normally does. That—

John Howison:

It will, at the moment, have information that we do not have.

We can put the question to FETA or ministers at another time.

That brings us to the end of item 1 on our agenda. We will have the same witnesses with us for item 2, but I will allow a five-minute comfort break.

Meeting suspended.

On resuming—