- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Jenny Gilruth on 25 July 2022
To ask the Scottish Government, further to the Infrastructure Investment Plan 2021-22 to 2025-26: Programme pipeline update (March 2022), what assessment it has made of the number of full-time equivalent (a) manufacturing, (b) seafarer and (b) port jobs that could be created in Scotland from the (i) CMAL Net Vessel Investment and (ii) Piers and Harbours Grants programmes.
Answer
The assessments undertaken to inform ferries investments focus on direct infrastructure impacts such as route capacity and connectivity. The benefit realisation process for each project will seek to identify and maximise the positive impact of our investments. As an example of this, the recent introduction of the MV Loch Frisa was enabled by modifications works, instructed by Caledonian Maritime Assets Ltd (CMAL), undertaken at the Dales facility in Leith, and CalMac Ferries Ltd have now completed the recruitment of 38 crew for the vessel to provide the year round commutable service for Mull.
- Asked by: Stephen Kerr, MSP for Central Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Angus Robertson on 25 July 2022
To ask the Scottish Government what the predicted cost of the Census Coverage Survey 2022 is, and what steps are being taken to ensure its success.
Answer
As the Census Coverage Survey (CCS) is ongoing, the predicted costs are based on the budget assigned to the CCS. Across the lifecycle of the Census Programme it was estimated that a budget of £3.1m would be required to deliver the CCS.
The CCS, alongside high quality administrative data and innovative statistical methods, will build on the census returns to deliver high quality Census Outputs. National Records of Scotland is continuing to take the action necessary to deliver the CCS phase of Scotland's Census Programme.
- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Jenny Gilruth on 25 July 2022
To ask the Scottish Government, further to the Infrastructure Investment Plan 2021-22 to 2025-26: Programme pipeline update (March 2022), whether it will provide an update on what commercial discussions Transport Scotland has had with Peel Ports regarding infrastructure work at Ardrossan Harbour.
Answer
Transport Scotland continues to engage with Peel Ports on the commercial arrangements for the Ardrossan upgrade project. The project moved to the tender preparation stage in April 2022 and it will take a number of months to complete prior to progressing to contract award and contractor mobilisation, subject to funding approval and agreeing commercial terms with Peel Ports.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Jenny Gilruth on 25 July 2022
To ask the Scottish Government, further to the answer to question S6W-08743 by Jenny Gilruth on 14 June 2022, whether it will provide the information requested regarding when it will replace the 25 Class 43 HSTs in the ScotRail fleet; whether it will confirm whether Transport Scotland's position remains that such replacement will occur only when "Network Rail has completed the electrification of all or most of the routes they serve", as reported in The Herald on 21 May 2022; when it anticipates that "the electrification of all or most of the routes they serve" will be completed, and for what reason it did not provide this information in its answer.
Answer
The replacement of train fleets in Scotland, including the HSTs, is aligned with the phases of the Decarbonisation Action Plan, a link to which is provided here:- Rail Services Decarbonisation Action Plan | Transport Scotland
This timescale is of course subject to continuous review in line with delivering the decarbonisation of the rail network in Scotland affordably and practicably and any other relevant developments, including recommendations arising from the Steering Groups considering the recommendations of, and subsequent analysis from the recent RAIB report into the Carmont accident.
- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Jenny Gilruth on 25 July 2022
To ask the Scottish Government what the current timelines are for (a) delivering the vessel concept design and (b) the award of the first vessel construction contract in the Small Vessel Replacement Programme.
Answer
The concept design for the Small Vessel Replacement Programme is set to be completed by the end of 2022 with the Single Procurement Document (Scotland) set to issue at the same time.
- Asked by: Russell Findlay, MSP for West Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 12 July 2022
-
Current Status:
Answered by Keith Brown on 25 July 2022
To ask the Scottish Government what its position is on whether the current reported prison population of 7,427 is too high.
Answer
There continues to be an increase in the prison population since the easing of lockdown, which has been largely driven by growth in the remand population. We continue to monitor the prison population to ensure prisons remain safe and well ordered.
We are taking actions and working towards using imprisonment only for those who pose a risk of serious harm and only be contemplated where absolutely necessary.
We are making a total investment of over £3.1 billion in 2022-23 to strengthen and reform vital services across the justice sector including substantial expansion of community justice services supporting diversion from prosecution, alternatives to remand and community sentencing.
The Bail and Release from Custody (Scotland) Bill was introduced to Scottish Parliament on 8 June 2022. The provisions of this Bill are intended to introduce a number of reforms designed to deliver on the Scottish Government’s commitment to refocus how imprisonment is used. They are intended to ensure that, as much as possible, the use of custody for remand is a last resort for the court, and to give a greater focus to the rehabilitation and reintegration of individuals leaving custody.
We are also investing over £500 million in the prison estate over this parliamentary term which will allow the Scottish Prison Services to meet the needs of the diverse prison population, realise the associated benefits and ensure equality of access to regimes and services.
- Asked by: Beatrice Wishart, MSP for Shetland Islands, Scottish Liberal Democrats
-
Date lodged: Monday, 11 July 2022
-
Current Status:
Answered by Maree Todd on 25 July 2022
To ask the Scottish Government, further to the answer to question S6W-08638 by Maree Todd on 7 June 2022, whether it will provide an update on its work to restart the self-referral route for breast cancer screening by autumn 2022.
Answer
Since the answer to question S6W-08638, the Scottish Breast Screening Programme has continued work towards the restart of self-referrals for those over 71, and these are on-track to recommence by Autumn 2022.
Commencement will be done in a careful, phased way to ensure that it does not unduly impact screening on the eligible cohort of 50-70, for whom the benefits of breast screening are clear.
I will update parliament with further details on the plans in the coming weeks.
- Asked by: Craig Hoy, MSP for South Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 05 July 2022
-
Current Status:
Answered by Humza Yousaf on 25 July 2022
To ask the Scottish Government, further to the answer to question S6W-02344 by Humza Yousaf on 30 September 2021, whether it will provide an update on how many calls to the Scottish Ambulance Service have been responded to (a) within (i) under 10, (ii) 10 to 29, (iii) 30 to 59 and (iv) 60 to 120 and (b) after over 120 minutes in each calendar year since 2007, also broken down by NHS board area.
Answer
The information that has been requested is not held centrally by the Scottish Government.
Official statistical reports relating to the Scottish Ambulance Service can be found on the following link. Public Health Scotland .
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Wednesday, 13 July 2022
-
Current Status:
Answered by Kevin Stewart on 25 July 2022
To ask the Scottish Government how many applications (a) have been made and (b) were successful for the Social Care Staff Support Fund since it became active in June 2020.
Answer
The Scottish Government launched the Social Care Staff Support Fund on 25 June 2020 to ensure that social care workers receive their expected income should they be off ill or self-isolating due to coronavirus.
Staffing costs claimed through sustainability payments encompass the Social Care Staff Support Fund, the staff movement policy and other additional staffing arrangements therefore, we do not have data broken down to the level that you have requested. The guidance for the financial support for social care providers recommends a light touch approach to gathering evidence, recognising the administrative burden of claiming additional costs on both commissioners and providers alike, whilst they respond to the pandemic.
Feedback from stakeholders confirms that the Social Care Staff Support Fund has been utilised to prevent financial hardship for eligible social care workers.
- Asked by: Ariane Burgess, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Tuesday, 28 June 2022
-
Current Status:
Answered by Jenny Gilruth on 25 July 2022
To ask the Scottish Government what consideration it has given to a Low Emission Zone (LEZ) in Inverness, in light of its approval of LEZ plans for Glasgow, Edinburgh, Aberdeen and Dundee.
Answer
The need for Low Emission Zones (LEZs) is for individual local authorities to consider based on specific air quality parameters within their respective areas. To date no LEZ proposals have been submitted for Ministerial approval by Highland Council.
Any local authority considering the introduction of a LEZ would undertake an assessment in accordance with the National Low Emission Framework (NLEF).
Highland Council carried out an NLEF assessment in 2020 and concluded that existing measures contained within their Air Quality Action Plan (AQAP), along with other local measures, would be sufficient to improve air quality within Inverness.