- Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 24 March 2023
-
Current Status:
Answered by Kevin Stewart on 5 April 2023
To ask the Scottish Government, further to the answer to question S6W-15567 by Jenny Gilruth on 21 March 2023, whether it will provide a breakdown of the information in the table showing the name and location of each bridge, and the date that the repair work (a) was first identified as required and (b) is projected to be completed by.
Answer
Please find the following table providing the name and location of each bridge on the trunk road network highlighted in our previous answer to S6W-15567. The dates that upgrades were first identified as required and projected to be completed are also contained:
Local Authority Area | Structure Reference | Structure Name | Work Identified | Planned Year of Completion |
Highland | A887 80 | A887 Lagain Bhain | 1998 | 2024-25 |
Highland | A830 160 | A830 Shlatach | 2013 | 2025-26 |
Stirling | A85 270 | A85 Dalkenneth | 2021 | 2026-27 |
Stirling | A84 137 | A84 Balquidder Station | 2019 | 2026-27 |
Highland | A82 1180 | A82 Lagain | 2018 | 2027-28 |
Moray | A95 170 | A95 Craigellachie Bridge | First identified over 10 years ago | 2024-25 |
Moray | A95 180 | A95 Craigellachie Bridge | First identified over 10 years ago | 2025-26 |
Fife-Falkirk | A985 1 | Kincardine | 1983 | 2024-25 |
Highland | A830 130 | A830 Finnan River | 1998 | 2027-28 |
Stirling | A84 35 | A84 Cambus | 1999 | 2028-29 |
Highland | A82 670 | A82 Allt Molach | 1990 | 2028-29 |
Highland | A82 680 | A82 Allt Nan Guibhas | 1990 | 2029-30 |
Highland | A82 690 | A82 Creagdubh | 1990 | 2029-30 |
Highland | A82 770 | A82 Alltanrigh | 1990 | 2030-31 |
Highland | A82 800 | A82 Achtriochtan | 1990 | 2030-31 |
Highland | A87 30 | A87 Daingean | 2018 | 2031-32 |
Highland | A87 40 | A87 Bhoira | 2018 | 2031-32 |
Highland | A87 50 | A87 Garbh Dhoire | 2018 | 2032-33 |
Highland | A87 60 | A87 Loyne | 2018 | 2032-33 |
Highland | A87 70 | A87 Moriston | 2018 | 2033-34 |
Highland | A87 520 | A87 Allt A'ghlarsair | 2013 | 2033-34 |
Highland | A87 540 | A87 Lon Chaorach | 2013 | 2034-35 |
Argyle & Bute | A828 10 | Connel | 2016 | 2024-25 |
Borders | A702 80 | A702 Westwater | 2018 | 2023-24 |
West Dunbartonshire | A82 150 | A82 Leven Bridge | 1999 | 2025-26 |
Dumfries and Galloway | A76 160 | A76 Marchburn | 1993 | 2025-26 |
Dumfries and Galloway | A75 690 | A75 Barlae | 2016 | 2025-26 |
Highland | A82 700 | A82 Etive | 2018 | 2034-35 |
West Dunbartonshire | A82 640 | A82 Tulla | 2018 | 2035-36 |
Stirling | A84 10 | A84 Drip | 2016 | 2035-36 |
Highland | A830 140 | A830 Challium | 2013 | 2036-37 |
Highland | A830 150 | A830 Dhuibh | 2013 | 2036-37 |
Highland | A87 600 | A87 Lon Na H'Iolainn | 1997 | 2037-38 |
Stirling | A84 80 | A84 Kilmahog 1 | 1997 | 2037-38 |
Stirling | A84 90 | A84 Kilmahog 2 | 1997 | 2038-39 |
All substandard structures on the trunk road network are monitored and managed in accordance with national standards until such time as funds are prioritised for remedial work.
- Asked by: Roz McCall, MSP for Mid Scotland and Fife, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 24 March 2023
-
Current Status:
Answered by Michael Matheson on 5 April 2023
To ask the Scottish Government, further to the statement by the Cabinet Secretary for Health and Social Care on 23 November 2022, when it will publish a full progress report on the improvement plan for NHS Forth Valley, following its escalation to stage 4 of the NHS Scotland performance escalation framework.
Answer
The Chair of the Assurance Board, Christine McLaughlin, wrote to members on 31 March 2023 with a full progress update on NHS Forth Valley’s escalation in Governance, Leadership and Culture. The letter has been published on the Scottish Government website: NHS Forth Valley Assurance Board update: letter from the Chair to MSPs - gov.scot (www.gov.scot) .
The onus remains on NHS Forth Valley to deliver and evidence the required improvements in governance, leadership and culture; and, in turn, on performance. The Assurance Board will continue to monitor and scrutinise NHS Forth Valley’s progress.
- Asked by: Monica Lennon, MSP for Central Scotland, Scottish Labour
-
Date lodged: Thursday, 23 March 2023
-
Current Status:
Answered by Michael Matheson on 5 April 2023
To ask the Scottish Government what steps are being taken to ensure that people on hormone replacement therapy for menopause are being seen by their GP in person for monitoring and blood pressure checks, in line with NHS guidelines.
Answer
Scottish Government is determined to ensure that women have access to the care and support they need for menopause, be that through primary or specialist care. Patients are able to request a face to face appointment for monitoring where in person assessment is required.
- Asked by: Alexander Burnett, MSP for Aberdeenshire West, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 27 March 2023
-
Current Status:
Answered by Kevin Stewart on 5 April 2023
To ask the Scottish Government what measures Transport Scotland has in place to monitor the success rates of the tree planting that it carried out along the Aberdeen Western Peripheral Route.
Answer
The Aberdeen Western Peripheral Road/Balmedie-Tipperty (AWPR/B-T) section of the A90 is managed on behalf of Scottish Ministers/Transport Scotland by the Design Build Finance and Operate (DBFO) company Aberdeen Roads Limited (ARL). The associated landscaping areas are included in the Agreement with ARL. Around 1.5 million trees were planted. The project is in year 4 of the 5 year Establishment Period. As the name suggests the Establishment Period is designed to closely monitor plant development and take action if appropriate to address tree plant establishment failures.
During the Establishment Period ARL’s appointed specialist landscape architect is required to undertake inspections of the tree planting 6 times in year one, 4 times in year 2, and 3 times for each of years 3, 4 and 5. On completion of the Establishment Period the landscaping enters the Operation and Maintenance (O&M) phase when annual inspections are required. The O&M period ends in 2047.
Following each inspection the landscape architect makes recommendations which are carried out by ARL and which could include tree tube/guard removal as the trees develop as well as identifying opportunities to enhance biodiversity and reduce pesticide application. Other work carried out over the last 4 to 5 years includes weed control, grass cutting in amongst those trees, pruning of damaged branches and re-staking of trees.
The appointed Contracting Authority (Jacobs consultants) receive annual reports and undertake joint inspections to ensure the contractual requirements are being fulfilled. Jacobs subsequently advise Transport Scotland of progress and discuss any matters as necessary.
- Asked by: Alexander Burnett, MSP for Aberdeenshire West, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 27 March 2023
-
Current Status:
Answered by Kevin Stewart on 5 April 2023
To ask the Scottish Government how many trees it and its agencies have planted along the Aberdeen Western Peripheral Route.
Answer
There are approximately 1.5 million new trees planted alongside the Aberdeen Western Peripheral Route. No further tree planting is planned other than replacement planting which may be required in future where insufficient numbers of trees have become established to satisfy the environmental objectives and the Indicative Landscape Design.
- Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 21 March 2023
-
Current Status:
Answered by Kevin Stewart on 5 April 2023
To ask the Scottish Government, further to the comments by the Deputy First Minister during the ministerial statement on Ferguson Marine on 16 March 2023, whether the planned periods between maintenance for (a) MV Glen Sannox and (b) Hull 802, once they are operational, has changed.
Answer
There has been no changes to the maintenance periods following these comments. Every vessel within the CalMac fleet requires regular maintenance work and CalMac are contractually obliged to ensure annual overhauls are completed successfully.
Planned maintenance will be carried out on each vessel on an annual basis in line with other vessels in the CHFS fleet. The timing of these inspections and necessary dry docks is for the operator to manage.
- Asked by: Sarah Boyack, MSP for Lothian, Scottish Labour
-
Date lodged: Tuesday, 21 March 2023
-
Current Status:
Answered by Michael Matheson on 5 April 2023
To ask the Scottish Government whether it has at any point offered, or signalled support for, health services as part of the Gilmerton Gateway project.
Answer
The Scottish Government is working with NHS Lothian on a range of capital investment projects, including the Edinburgh Cancer Centre, a National Treatment Centre, a replacement for the Edinburgh Eye Pavilion and a number of primary care projects and we are in the process of establishing a prioritised list, which can be taken forward in line with our capital budget expectations.
- Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
-
Date lodged: Tuesday, 21 March 2023
-
Current Status:
Answered by Shona Robison on 5 April 2023
To ask the Scottish Government how much it has spent on TikTok in each of the last five years.
Answer
The expenditure by the Scottish Government in each of the last five years on TikTok is as follows:
2018: £0
2019: £0
2020: £71,179
2021: £127,372
2022: £112,508
2023: £27,474 (up to 31 March 2023)
- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Friday, 31 March 2023
-
Current Status:
Answered by Kevin Stewart on 5 April 2023
To ask the Scottish Government, further to the answer to question S6W-12940 by Jenny Gilruth on 22 December 2022, whether it will provide an update on the service continuity plan for the transfer and timetabling of services from Troon.
Answer
The service continuity plans for the Ardrossan-Brodick/Campbeltown route are currently being reviewed by CalMac following the recent announcement of the delivery date and deployment of the MV Glen Sannox to the route. CalMac are engaging with relevant partners including the Isle of Arran Ferry Committee on the Troon timetables and are expected to publish the Timetable Consultation Report (as part of a public consultation exercise undertaken in August and September 2022) in the coming weeks.
- Asked by: Alexander Burnett, MSP for Aberdeenshire West, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 27 March 2023
-
Current Status:
Answered by Kevin Stewart on 5 April 2023
To ask the Scottish Government what measures Transport Scotland has in place to monitor the success rates of any tree planting that it undertakes.
Answer
All new planting schemes on the trunk road network include a 5-year establishment period throughout which regular inspections are undertaken by professional landscape architects and by the landscape contractor. These inspections assess the establishment of the plants and determine any specific maintenance required, including the replacement of any failed material.
The trunk road operating companies assume responsibility after this period and are required to annually assess and report on all planting and other vegetation within their area of operation and to recommend management interventions as appropriate, such as pruning and thinning etc.
Following completion, all major road schemes are monitored and assessed through the Scottish Trunk Road Infrastructure Project Evaluation (STRIPE) procedure to determine whether the scheme objectives have been met and to assess how well the scheme has been implemented, including the planting element.