- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government what the (a) construction costs and (b) repayment terms are for each capital project, broken down by (i) time period, (ii) annual revenue repayments and (iii) total revenue repayment over the project lifetime.
Answer
Information relating to those projects which are operational or in construction and which form part of the Scottish Government’s current revenue funded non-profit distribution/hub investment programme is available on the Scottish Government’s website:
www.gov.scot/Topics/Government/Finance/18232/12308
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether, under the Scottish Futures Trust's revised design-build-finance-maintain structure, revenue contributions from the public sector will be greater for capital projects for which all of the capital comes from the private sector, and what assessment it has made of the additional cost.
Answer
No changes are anticipated to the level of unitary charge payable by procuring bodies for the majority of non-profit distributing or hub funded developments. For those projects where capital contributions are no longer being made by the public sector, unitary charge payments will increase commensurately though it is anticipated this will have a relatively small effect across the programme.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government how it will finance the new Clydebank Health Centre; when the project will (a) start and (b) be completed, and how much public sector capital will be involved.
Answer
The timing of the Clydebank Health Centre has yet to be agreed. The project, with a capital cost of £19 million, is expected to be financed via the hub design-build-finance-maintain programme.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether it has (a) sought and (b) received advice from the Office of the Scottish Charity Regulator (OSCR) on the proposed new private sector charity that will be part of future design-build-finance-maintain capital projects and what the dates are of all its (i) meetings and (ii) communications with OSCR.
Answer
Scottish Futures Trust is leading work on the creation of a new charity that will form part of the structure of future hub infrastructure projects, seeking advice when required including ongoing engagement with the Office of the Scottish Charity Regulator with which it met on 16 July 2015.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether the Scottish Futures Trust's revised structure for design-build-finance-maintain projects gives a more direct and greater share of each project to the private sector and, if so, for what reason.
Answer
I refer the member to the answer to question S4W-26455 on 31 July 2015. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at:
www.scottish.parliament.uk/parliamentarybusiness/28877.aspx.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government which capital projects that were expected to have a financial close in (a) March, (b) April, (c) May, (d) June and (e) July 2015 now have a revised close date due to the changes to the Eurostat designation of capital projects and what the revised dates are.
Answer
At the start of the year, it was anticipated that the following projects would reach financial close as set out in the following table:
Month | Project |
January | Forfar Academy |
February | Inverclyde Health Centre, Baldragon Academy |
March | NHS Lothian Bundle, Newbattle High School, Anderson High School, Kelso High School, Elgin High School |
April | - |
May | - |
June | Barrhead High School, Our Lady and St Patricks High School |
Forfar Academy reached financial close in June 2015 following completion of an early construction works package and the Anderson High School is due to reach financial close shortly. Other projects have been delayed by a combination of changes to Eurostat guidance and project specific issues. It is too early to provide revised dates for reaching financial close.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether the Scottish Futures Trust's proposed model for design-build-finance-maintain projects will have an impact on so-called soft services.
Answer
Soft services, such as cleaning, catering etc, have always been excluded from all non-profit distributing and hub design-build-finance-maintain projects to increase flexibility and learn lessons from the past. There will be no change in any revised structure.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether it has changed the structure of the (a) Aberdeen Western Peripheral Route, (b) Dumfries and Galloway Infirmary and (c) Royal Hospital for Sick Children in Edinburgh capital project and, if so, what changes it has made and for what reason.
Answer
No changes have been made following financial close. Some limited contractual adjustments were made prior to financial close to address Scottish Government and Scottish Futures Trust’s understanding of the revised guidance in Eurostat’s recently updated Manual of Government Deficit and Debt.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether it has agreed its proposed changes to the model for design-build-finance-maintain projects with (a) the Office for National Statistics and (b) Eurostat.
Answer
The Office for National Statistics takes decisions independently about projects or programmes that it wishes to review. The proposed design-build-finance-maintain-model is not currently under review. Engagement with Eurostat, on any issues of classification, would be a matter for the Office for National Statistics or the UK Government, as the relevant EU member state.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether it will list all capital projects that the Scottish Futures Trust (a) is currently delivering and (b) has in the pipeline.
Answer
Information on the infrastructure investment projects which Scottish Futures Trust is supporting is available on its website: www.scottishfuturestrust.org.uk/