Question
To ask the Scottish Government, further to the answer to question S6W-07655 by Jenny Gilruth on 27 April 2022, whether any changes were made to the draft Temporary Measures Agreement, shared with Serco on 25 February 2022, before it was agreed, and, if so, what these changes were.
Answer
There were no substantive changes made to the draft of the Temporary Measures Agreement (TMA) shared with Serco Caledonian Sleepers Limited (‘Serco’) on 25 February 2022.