Skip to main content
Loading…

Chamber and committees

Questions and answers

Parliamentary questions can be asked by any MSP to the Scottish Government or the Scottish Parliamentary Corporate Body. The questions provide a means for MSPs to get factual and statistical information.

  • Written questions must be answered within 10 working days (20 working days during recess)
  • Other questions such as Topical, Portfolio, General and First Minister's Question Times are taken in the Chamber

Urgent Questions aren't included in the Question and Answers search.  There is a SPICe fact sheet listing Urgent and emergency questions.

Find out more about parliamentary questions

Filter your results Hide all filters

Dates of parliamentary sessions
  1. Session 1: 12 May 1999 to 31 March 2003
  2. Session 2: 7 May 2003 to 2 April 2007
  3. Session 3: 9 May 2007 to 22 March 2011
  4. Session 4: 11 May 2011 to 23 March 2016
  5. Session 5: 12 May 2016 to 4 May 2021
  6. Current session: 13 May 2021 to 15 September 2025
Answer status
Question type

Displaying 2136 questions Show Answers

|

Question reference: S4W-13018

  • Asked by: Richard Baker, MSP for North East Scotland, Scottish Labour
  • Date lodged: Friday, 08 February 2013
  • Current Status: Answered by Fergus Ewing on 20 March 2013

To ask the Scottish Government what progress has been made by the forum that it established to promote cycling tourism and when its action plan will be published.

Question reference: S4W-13526

  • Asked by: Richard Baker, MSP for North East Scotland, Scottish Labour
  • Date lodged: Thursday, 07 March 2013
  • Current Status: Answered by Keith Brown on 20 March 2013

To ask the Scottish Government for what reason the projected start date of the construction of the Aberdeen Western Peripheral Route is two years after the resolution of the legal challenge to the project.

Question reference: S4W-13525

  • Asked by: Richard Baker, MSP for North East Scotland, Scottish Labour
  • Date lodged: Thursday, 07 March 2013
  • Current Status: Answered by Keith Brown on 20 March 2013

To ask the Scottish Government whether it will seek EU assistance for the (a) construction of the Aberdeen Western Peripheral Route and (b) (i) M8, (ii) M73 and (iii) M74 motorway improvements projects.

Question reference: S4W-13530

  • Asked by: Richard Baker, MSP for North East Scotland, Scottish Labour
  • Date lodged: Thursday, 07 March 2013
  • Current Status: Answered by Nicola Sturgeon on 18 March 2013

To ask the Scottish Government, further to the answer to question S4W-12698 by Nicola Sturgeon on 25 February 2013, if staggering the timing of procurement of the three colleges avoided them competing with each other in the market, for what reason the colleges will now move into construction around the same time.

Question reference: S4W-13532

  • Asked by: Richard Baker, MSP for North East Scotland, Scottish Labour
  • Date lodged: Thursday, 07 March 2013
  • Current Status: Answered by Nicola Sturgeon on 18 March 2013

To ask the Scottish Government, further to the answer to question S4W-12698 by Nicola Sturgeon on 25 February 2013, how the staggered timing for college projects has been prioritised.

Question reference: S4W-13528

  • Asked by: Richard Baker, MSP for North East Scotland, Scottish Labour
  • Date lodged: Thursday, 07 March 2013
  • Current Status: Answered by Nicola Sturgeon on 18 March 2013

To ask the Scottish Government, further to the answer to question S4W-12698 by Nicola Sturgeon on 25 February 2013, what funding has been made available for each school project that has been delayed by project-specific issues.

Question reference: S4W-13533

  • Asked by: Richard Baker, MSP for North East Scotland, Scottish Labour
  • Date lodged: Thursday, 07 March 2013
  • Current Status: Answered by Nicola Sturgeon on 18 March 2013

To ask the Scottish Government, further to the answer to question S4W-12698 by Nicola Sturgeon on 25 February 2013, which minister approved the decision to deliver the Borders Railway project using Network Rail’s Regulatory Asset Base and not the non-profit distributing model, and for what reason Network Rail’s Regulatory Asset Base was chosen as the preferred method.

Question reference: S4W-13531

  • Asked by: Richard Baker, MSP for North East Scotland, Scottish Labour
  • Date lodged: Thursday, 07 March 2013
  • Current Status: Answered by Nicola Sturgeon on 18 March 2013

To ask the Scottish Government, further to the answer to question S4W-12698 by Nicola Sturgeon on 25 February 2013, whether moving the colleges into construction around the same time might have a detrimental effect, and what the reasons are for its position on this matter.

Question reference: S4W-13527

  • Asked by: Richard Baker, MSP for North East Scotland, Scottish Labour
  • Date lodged: Thursday, 07 March 2013
  • Current Status: Answered by Nicola Sturgeon on 18 March 2013

To ask the Scottish Government, further to the answer to question S4W-12698 by Nicola Sturgeon on 25 February 2013, when it will publish the timescale for the delivery of each of the 19 schools projects in Phase 3.

Question reference: S4W-13529

  • Asked by: Richard Baker, MSP for North East Scotland, Scottish Labour
  • Date lodged: Thursday, 07 March 2013
  • Current Status: Answered by Nicola Sturgeon on 18 March 2013

To ask the Scottish Government, further to the answer to question S4W-12698 by Nicola Sturgeon on 25 February 2013, whether any school projects will be delivered through the HUB initiative and, if so, which projects.