To ask the Presiding Officer what works packages have still to go out to tender in relation to the Holyrood Project and what the indicative timescale is in each case for issuing and return of tenders, award of contract and commencement and completion of works.
The information is as follows:
1. Assembly Building Brick/Blockwork.
2. General Builderswork.
3. Assembly Building Foyer Frame & Glazing.
4. Assembly Building Specialist Glazing.
5. Assembly Building Cladding.
6. Assembly Building/Canongate Roofing
7. Assembly Building Timber Trusses.
8. Canongate Constituency Wall.
9. Fire Stopping (Whole Site).
10. Assembly Building/Canongate Fire Protection Steelwork.
11. Queensberry House Ceilings/Partitions/Plasterboard.
12. MSP Building Ceilings/Partitions.
13. Queensberry House Suspended Ceilings.
14. Assembly Building Ceilings/Partitions.
15. Queensberry House Raised Floors.
16. Assembly Building Raised Floors.
17. MSP Building Stone Floors/Screeds
18. Queensberry House Stone Floors/Screeds.
19. Assembly Building Stone Floors/Screeds.
20. MSP Building Floor Covering.
21. Queensberry House Timber/Vinyl Flooring.
22. Assembly Building Timber Flooring.
23. Assembly Building Carpet & Vinyl Flooring.
24. Queensberry House Carpentry & Joinery.
25. Assembly Building Carpentry & Joinery.
26. Queensberry House Metal Blast Windows/Doors.
27. Assembly Building Metal Doors/Shutters.
28. MSP Building Architectural Metalwork.
29. Queensberry House Architectural Metalwork.
30. Assembly Building Architectural Metalwork.
31. MSP Building Decoration.
32. Queensberry House Decoration.
33. Assembly Building Decoration.
34. MSP Building Toilet/Fitness/Changing Fit Out.
35. Queensberry House Toilet Fit Out.
36. Assembly Building Toilet Fit Out.
37. Furniture/Fittings/Equipment.
38. Filing Systems.
39. Catering Equipment (Whole Site).
40. Bar & Restaurant Fit Out (Whole Site).
41. Audio Visual Equipment (Whole Site).
42. Signage.
43. Cleaning Cradles.
44. Mechanical & Plumbing East.
45. Fire Alarm & Protection (Whole Site).
46. Building Maintenance System (Whole Site).
47. Commissioning (Whole Site).
48. Electrical East.
49. Structured Cabling (Whole Site).
50. Security (Whole Site).
51. Electricity Incoming (Whole Site).
52. Water Incoming (Whole Site).
53. Gas Supply (Whole Site)
54. IT/Communications (Whole Site).
55. Sewer Connections.
56. Cable/Satellite.
57. Hard Landscaping.
58. Soft Landscaping.I am informed by the Convener of the Holyrood Progress Group that, while a broad time frame was included as part of the Stage D Scheme Design report, it would be misleading to give definitive programme dates relating to the award, site start and completion of the above packages. These are liable to change in line with arrangements made by the Construction Manager, who is employed to manage a dynamic programme, to the overall benefit of the project. The programmed building completion date remains as 31 December 2002.