- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Tuesday, 28 February 2017
-
Current Status:
Answered by Keith Brown on 9 March 2017
To ask the Scottish Government how many people have been employed on the Forth Replacement Crossing project, and how this compares with the initial projection.
Answer
Through the duration of the project well over 10,000 different people have been employed on site. An annual average of 1300 people have been employed on site on the Forth Replacement Crossing, which well exceeds the initial projection of a maximum of 1200 people at the peak of construction.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Tuesday, 28 February 2017
-
Current Status:
Answered by Keith Brown on 9 March 2017
To ask the Scottish Government how many working days on the Forth Replacement Crossing have been lost due to bad weather, and how this compares with the initial projection.
Answer
The Forth Crossing Bridge Constructors (FCBC) programme allowed an average of 20% downtime for weather over the construction period. Since deck lifting operations commenced in September 2015, the downtime due to adverse weather, specifically wind, has been 40% compared to the 25% anticipated by the contractor. Until May 2016, FCBC believed that they could mitigate these weather effects. However the impact of the unfavourable wind speeds in April and May 2016 was particularly severe, with 13 days and 12 days lost to wind respectively. As a result, FCBC advised Ministers that due to the combined effects of the time lost in these two months they could no longer deliver the December 2016 target opening date for the structure. In the period from June 2016 up to the end of February 2017, FCBC has reported a total of 37% of working days with some activities affected by the weather, principally wind.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Tuesday, 28 February 2017
-
Current Status:
Answered by Keith Brown on 9 March 2017
To ask the Scottish Government whether it will provide an update on what the total cost of the Forth Replacement Crossing will be and how this compares with each of its previously published estimates, and what impact (a) the inflation rate has and (b) other factors have had on these figures.
Answer
The total estimated cost of the Forth Replacement Crossing is £1.325 - £1.35 billion, £245 million lower than the June 2011 estimate when construction began. The inflation element of the £245 million saving is £192 million. The remaining saving of £53 million is a reduction in the allowance for risk and optimism bias which have steadily decreased as the project has progressed through robust risk and project management. These savings are in addition to those achieved through the contract procurement process in 2010 which reduced the median project forecast by £512 million and the near halving of the initial £3.2 to £4.2 billion project estimate by incorporating the Forth Road Bridge and other existing infrastructure in the overall project scope.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Tuesday, 28 February 2017
-
Current Status:
Answered by Keith Brown on 9 March 2017
To ask the Scottish Government, further to the answer to question S5W-04726 by Keith Brown on 25 November 2016, whether the full range of options available to commemorate the opening of the Forth Replacement Crossing have been finalised and, if (a) so, whether it will publish these; how much the commemorations will cost, and on what dates they will take place, (b) not, what the reason is for the delay.
Answer
The arrangements for the opening events to commemorate the opening of the Forth Replacement Crossing are currently being finalised. A full range of options to commemorate the options is being considered together with the requests to participate in any events. It is expected that the final arrangements, details and dates will be confirmed shortly.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Wednesday, 01 March 2017
-
Current Status:
Answered by Fergus Ewing on 9 March 2017
To ask the Scottish Government whether it is making sufficient progress to meet its targets of 95% coverage of superfast broadband by 2018 and 100% by 2021.
Answer
The Digital Scotland Superfast Broadband programme is progressing well and remains on track to meet its target of 95% fibre broadband access by the end of 2017. In 2016, Audit Scotland reviewed progress of the DSSB Programme and concluded that it was on track to meet coverage targets, with more premises than expected being able to access superfast speeds. To date 87.9% of premises across Scotland can access fibre broadband. This figure assumes that commercial rollout is completed on time and in line with plans submitted to the Scottish Government as part of the 2012 Open Market Review.
Likewise the Reaching 100% programme is also progressing well with responses to the Open Market Review currently being evaluated and supplier engagement continuing. The programme remains on track to launch new procurement activity later this year.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Wednesday, 01 March 2017
-
Current Status:
Answered by Fergus Ewing on 9 March 2017
To ask the Scottish Government what its position is on whether investment in superfast broadband should prioritise rural blackspots and hard to reach areas to ensure that it meets its targets for 2021, and what the (a) current and (b) planned levels of relative spending are across each region.
Answer
The Reaching 100% programme will promote an ‘outside-in’ approach, prioritising future public investment in the hardest to reach rural areas – those that won’t benefit from the Digital Scotland Superfast Broadband programme.
The Scottish Government’s draft budget confirmed that up to £112 million will be invested during 2017-18 to improve digital infrastructure across Scotland. The funding will support the final phases of the Digital Scotland Superfast Broadband (DSSB) programme and enable new activity to begin on the Reaching 100% programme and mobile infill. The DSSB programme is delivered via two contracts - one in the Highlands and Islands investing £145.8 million and one in the Rest of Scotland investing £266.5 million. As procurement for the Reaching 100% programme has not yet begun it is not currently possible to determine the level of expenditure across each region.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Tuesday, 28 February 2017
-
Current Status:
Answered by Keith Brown on 9 March 2017
To ask the Scottish Government what its position is on whether the initial projected cost of the Forth Replacement Crossing project was an overestimate.
Answer
I refer the member to the answer to question S5W-07593 on 9 March 2017. The development and breakdown of the initial projected cost of the Forth Replacement Crossing project was detailed in the Financial Memorandum to the Forth Crossing Bill dated 16 November 2009. This was subjected to detailed scrutiny by both the Parliament and the Forth Crossing Bill Committee and resulted in the Bill being passed in December 2010 by 108 votes to 3.
All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at http://www.parliament.scot/parliamentarybusiness/28877.aspx
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Tuesday, 28 February 2017
-
Current Status:
Answered by Keith Brown on 9 March 2017
To ask the Scottish Government what information it has regarding the (a) average, (b) lowest and (c) highest wage paid pro rata of staff on the Forth Replacement Crossing project.
Answer
It is the responsibility of the contractor FCBC to manage matters relating to its workforce and the Scottish Government does not hold this information. However, Transport Scotland has been provided with assurances from the contractor, FCBC, that contractual agreements are in place to pay local rates.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Tuesday, 28 February 2017
-
Current Status:
Answered by Keith Brown on 9 March 2017
To ask the Scottish Government whether it will provide an update on the assessment that it has made of the economic impact of the Forth Replacement Crossing on the (a) north, (b) south and (c) rest of the country.
Answer
Consideration of potential economic impacts was reported in Chapter 7.14 of the DMRB Stage 3 Scheme Assessment Report Part 2 Engineering, Traffic and Economic Assessment, published Nov 2009. The Scottish Government will provide an update on these aspects following a period of at least three years of operation of the project. The DMRB Stage 3 Scheme Assessment Report can be found: http://www.transport.gov.scot/system/files/documents/tsc-basic-pages/FRC_Stage_3_Scheme_Assessment_Report__Part_2__v3_Final.pdf
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Tuesday, 28 February 2017
-
Current Status:
Answered by Keith Brown on 9 March 2017
To ask the Scottish Government how many meetings the (a) First Minister and (b) (i) cabinet secretary or (ii) minister with responsibility for transport has had each year with the directors of the Forth Replacement Crossing project, and how many future meetings are planned.
Answer
Transport Scotland is part of the Scottish Government and meetings with Ministers occur regularly in the course of normal business. Transport Scotland Directors also routinely attend monthly meetings with Ministers to discuss issues including progress of major infrastructure projects, including the Forth Replacement Crossing project.