- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Wednesday, 27 January 2021
-
Current Status:
Answered by Michael Matheson on 11 February 2021
To ask the Scottish Government whether Transport Scotland launched the consultation of the A96 Huntly to Aberdeen dualling project (a) without providing notification to Aberdeenshire Council and (b) on 21 December 2020 while local communities were entering the Christmas holiday period, and what the reasons were for its decision in this regard.
Answer
As for all Transport Scotland’s major infrastructure projects, consultation is an integral part of the design process for the A96 Dualling East of Huntly to Aberdeen scheme.
Transport Scotland advised a representative from Aberdeenshire Council about the forthcoming virtual exhibition and followed this up in writing on 18 December to confirm that the consultation would go live on the Transport Scotland website on 21 December 2020. In addition, a meeting with Aberdeenshire Council officers took place during the current feedback period on 03 February 2021 to present the outcome of the route options assessment and explain the next stage of the design process.
Due to the significant interest in the scheme and the amount of feedback received during the route options assessment process, it was considered appropriate to give communities visibility on the conclusion of the assessment at the earliest opportunity. This ensured communities were kept fully appraised of our plans as soon as they were available.
Recognising the impact of the festive period and the COVID-19 restrictions, we had already extended the usual feedback period by two weeks to eight weeks. However, in recognition of the widespread interest in this scheme and in light of the ongoing restrictions and feedback received, we have extended the consultation period for a further three weeks till 08 March 2021, to let the public have their say on the preferred option.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Wednesday, 27 January 2021
-
Current Status:
Answered by Michael Matheson on 11 February 2021
To ask the Scottish Government what its response is to reported concerns by the Deputy Leader of Aberdeenshire Council regarding the window of time allowed for the consultation on the A96 Huntly to Aberdeen dualling project, before it is completed on 15 February 2021.
Answer
As with all Transport Scotland’s major infrastructure projects, consultation is an integral part of the design process for the A96 Dualling East of Huntly to Aberdeen scheme.
Recognising the impact of the festive period and the COVID-19 restrictions, we had already extended the usual feedback period by two weeks to eight weeks. This is a non-statutory consultation, and forms part of our rolling programme of regular engagement aimed at providing greater transparency about the decision making process associated with project route selection. Consequently there is no minimum duration required.
However, in recognition of the widespread interest in this scheme and in light of the ongoing restrictions and feedback received, we have extended the consultation period for a further three weeks till 08 March 2021, to let the public have their say on the preferred option.
As we continue to develop the preferred option in greater detail, individuals, communities and businesses affected by the work will be kept fully informed and their feedback carefully considered.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Tuesday, 19 January 2021
-
Current Status:
Answered by Michael Matheson on 29 January 2021
To ask the Scottish Government, in light of the additional pressure on the NHS due to COVID-19, what (a) action it has taken and (b) additional funding it has provided to support local authorities in preventing injuries caused by inadequate gritting during periods of icy weather.
Answer
Scotland's 32 local authorities are responsible for the maintenance and safe operation of Scotland's local road network. Each local authority is responsible for all aspects of the non-trunk road network within their jurisdiction, including Winter Service Operations. This includes all footways, footpaths and cycle tracks not in private ownership. While each road authority will prioritise the treatment of their own networks, mutual aid is offered, when possible. This includes the sharing of plant, facilities, labour and salt.
Systems are already established to prioritise road clearing around hospitals and NHS Sites. In addition, Transport Scotland and their trunk road partners have reviewed vaccination sites on or adjacent to the trunk road network and considered the potential for pre-cautionary treatment routes to be flexed to assist access to these locations should mutual aid be requested.
No additional direct funding has been provided in support of winter maintenance in relation to COVID-19 although we have provided £204 million as general revenue support which local authorities could use to supplement their winter maintenance budget if they choose to do so.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Monday, 18 January 2021
-
Current Status:
Answered by Michael Matheson on 27 January 2021
To ask the Scottish Government whether the Passenger Assist app, which enables disabled passengers to pre-book boarding assistance six hours ahead of a train journey, will work in Scotland and, if so, when it will be available for passengers to use.
Answer
The responsibility for this lies with the Rail Delivery Group, however once the app is approved it will be available for use in Scotland.
The member may wish to contact the Rail Delivery Group for further information.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Wednesday, 23 December 2020
-
Current Status:
Answered by Jamie Hepburn on 11 January 2021
To ask the Scottish Government, further to the answer to question S5W-34207 by Jamie Hepburn on 23 December 2020, what proportion of the target of 30,000 apprenticeship starts this year will be met.
Answer
Covid-19 continues to present unprecedented challenges for business across Scotland with many employers delaying and pausing recruitment decisions which will continue to have, an impact on apprenticeship provision. Skills Development Scotland will publish Modern Apprenticeship statistics under official statistics protocols with the year end statistics(Quarter 4 2020/21) in June 2021.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Friday, 20 November 2020
-
Current Status:
Answered by Jamie Hepburn on 7 December 2020
To ask the Scottish Government what action it has taken to support taxi businesses during the COVID-19 pandemic.
Answer
We acknowledge the devastating impact that restrictions have had on the taxi and private vehicle hire sector since the outset of the pandemic. We also recognise that this sector has particularly high fixed costs associated with financing and maintaining vehicles.
In addition to the £5 million COVID-19 Public Transport Mitigation Fund to support the installation of equipment that reduces the risk of coronavirus transmission on public transport, including taxi and private hire operators, we have announced a £30 million discretionary fund for local authorities. This is specifically aimed at providing financial support to those small businesses and the self-employed who have not yet been reached by the Scottish Government. This includes taxi drivers as referenced by the First Minister her statement on statement to Parliament on 17 November.
We are actively considering support for fixed costs pressures on taxi drivers distinct from the new Strategic Framework Business Fund.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Friday, 20 November 2020
-
Current Status:
Answered by Jamie Hepburn on 7 December 2020
To ask the Scottish Government, in light of the £14 million financial support scheme for taxi drivers in Northern Ireland announced on 13 November 2020, whether it has considered providing an annual block grant for local licencing authorities in Scotland in order to remove the fee for processing licence applications for taxi operators.
Answer
In addition to the £30 million discretionary funding announced on 17 November, we are actively exploring additional opportunities to support taxi and private hire vehicle operators in recognition of the devastating impact of restrictions on their trade and the high fixed costs associated with operating their vehicles. As part of this we are reviewing the financial support provided to taxi drivers by the Northern Ireland Executive to consider what lessons we can draw from this.
It should be noted, however, that there are significant variations in the taxi vehicle licensing regime in Northern Ireland compared to here, not least that licensing fees are set and administered nationally by the Executive rather than by local authorities as is the case in Scotland.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Wednesday, 28 October 2020
-
Current Status:
Answered by Roseanna Cunningham on 11 November 2020
To ask the Scottish Government, further to the answer to question S5W-10494 by Roseanna Cunningham on 15 August 2017, which of the 42 formal flood protection schemes or engineering works have been completed, broken down by (a) the number of properties being protected, (b) the completion date and (c) what the (i) initial forecast and (ii) final cost was of each.
Answer
Details are as follows:
Scheme | (a) Properties Protected | (b) Completion Date | (c)(i) Initial Cost (£ million) (1) | (c) (ii) Estimated Final Cost (£ million) |
Huntly | 63 | 2017 | 4.9 | 3.8 |
Newmill | 18 | 2017 | 1.9 | 1.8 |
Dundee | 200 | 2018 | 6.2 | 6.9 |
Kirkwall | 750 | 2018 | 1.8 | 1.8 |
White Cart Water Phase 3 | 100 | 2019 | 5.9 | 7.2 |
Camlachie Burn | 410 | 2019 | 1.2 | 1.7 |
Broxburn (Liggat Syke) | Not held | 2019 | Not held | Not held |
New Cumnock Phase 1 Complete Phase 2 Under construction | 95 | P1 2018 P2 July 2022 | 3.3 | 6.2 |
(1) Note: Initial costs as provided by local authorities in 2016-17.
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Wednesday, 28 October 2020
-
Current Status:
Answered by Roseanna Cunningham on 11 November 2020
To ask the Scottish Government, further to the answer to question S5W-10494 by Roseanna Cunningham on 15 August 2017, how many floods have been recorded in each of the 42 formal flood protection schemes or engineering works' areas since January 2016, broken down by the (a) damage caused and (b) cost of each incident.
Answer
I refer the member to the answer to question S5W-27523 on 5 March 2020. All answers to written parliamentary questions are available on the Parliament's website, the search facility for which can be found at http://www.parliament.scot/parliamentarybusiness/28877.aspx .
- Asked by: Mike Rumbles, MSP for North East Scotland, Scottish Liberal Democrats
-
Date lodged: Wednesday, 28 October 2020
-
Current Status:
Answered by Roseanna Cunningham on 11 November 2020
To ask the Scottish Government, further to the answer to question S5W-10494 by Roseanna Cunningham on 15 August 2017, which of the 42 formal flood protection schemes or engineering works have been removed from the list of proposed works, broken down by the (a) number of properties that were expected to be protected, (b) reason for removal, and (c) (i) initial forecast cost of and (ii) amount that was spent on each.
Answer
I refer the member to the answer to question S5W-27519 on 4 March 2020. All answers to written parliamentary questions are available on the Parliament's website, the search facility for which can be found at http://www.parliament.scot/parliamentarybusiness/28877.aspx .