- Asked by: Michael Russell, MSP for Argyll and Bute, Scottish National Party
-
Date lodged: Thursday, 18 June 2015
-
Current Status:
Answered by Derek Mackay on 6 July 2015
To ask the Scottish Government, further to the answer to question S4W-25968 by Derek MacKay on 11 June 2015, what communications it has had with (a) Caledonian MacBrayne and (b) the Lismore community about the issue of small-scale petrol supplies to the island and when.
Answer
I refer the member to the answer to question S4W-26188 on 6 July 2015. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at:
http://www.scottish.parliament.uk/parliamentarybusiness/28877.aspx
- Asked by: Michael Russell, MSP for Argyll and Bute, Scottish National Party
-
Date lodged: Thursday, 18 June 2015
-
Current Status:
Answered by Derek Mackay on 6 July 2015
To ask the Scottish Government, further to the answer to question S4W-25968 by Derek MacKay on 11 June 2015, when it was made aware that the Loch Striven would be fitted with a cage to allow the safe carriage of petrol cans to Lismore and for what reason that information was not included in the answer.
Answer
I refer the member to the answer to question S4W-26188 on 6 July 2015. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at:
http://www.scottish.parliament.uk/parliamentarybusiness/28877.aspx
- Asked by: Michael Russell, MSP for Argyll and Bute, Scottish National Party
-
Date lodged: Friday, 19 June 2015
-
Current Status:
Answered by Derek Mackay on 6 July 2015
To ask the Scottish Government what work (a) Transport Scotland or (b) Caledonian Maritime Assets Ltd has undertaken to balance carrying capacity with length in plans for new vessels for the CalMac routes in order to avoid substantial new expenditure on modifications to piers and harbours as a result of the introduction of very long vessels.
Answer
The targeted carrying capacity of the proposed vessels was outlined by CalMac Ferries Limited on the basis of an analysis of forecast demand. Caledonian Maritime Assets Ltd’s invitation to tender requires a vessel design that can accommodate these capacities within the length, breadth and draft restrictions on a number of routes.
The various shipyard designs submitted in response are being evaluated.
The vessels specified cannot be described as “very long” when compared to existing CalMac vessels.
- Asked by: Michael Russell, MSP for Argyll and Bute, Scottish National Party
-
Date lodged: Friday, 19 June 2015
-
Current Status:
Answered by Derek Mackay on 6 July 2015
To ask the Scottish Government, further to the answer to question S4W-25870 by Derek MacKay on 10 June 2015, what deeper water ports the proposed new vessels being procured by Caledonian Maritime Assets Ltd will serve; what emerging technologies will feature on those vessels, and what steps are being taken to ensure that they will (a) reduce fuel consumption, (b) minimise emissions and (c) drive down operating costs.
Answer
CalMac Ferries Ltd has requested that the new vessels operate initially on Uig Triangle (Uig to Tarbert to Lochmaddy) and to Arran (Ardrossan to Brodick).
Tenderers were required in preparing their bids to consider the reliability required of a lifeline vessel in terms of sea keeping, manoeuvring, mechanical redundancy and machinery availability and also the environmental benefits these vessels are aiming to achieve through careful design, maximising efficiencies, new technologies and innovations. Caledonian Maritime Assets Ltd is scrutinising, clarifying and evaluating the bids submitted to ensure that the optimum design specification including new technologies and innovations are incorporated to maximise the vessel effectiveness and efficiency.
Emissions are directly related to fuel consumption for the same type of fuel. For example, a 20% reduction in fuel consumption will result in a 20% reduction of CO2, SOx, NOx and particulate matter. An important element to drive down direct operating costs relates to the fuel consumption. Consequently, a key aspect of the vessel design is reducing fuel consumption and emission levels through use of new technologies and innovations.
- Asked by: Michael Russell, MSP for Argyll and Bute, Scottish National Party
-
Date lodged: Friday, 19 June 2015
-
Current Status:
Answered by Derek Mackay on 6 July 2015
To ask the Scottish Government, further to the answer to question S4W-25869 by Derek MacKay on 10 June 2015, whether it will list the 15 piers and harbours that the planned new vessels can serve without, or with only minimal, modification.
Answer
The 15 ports under consideration are as follows:
Ardrossan
|
Brodick*
|
Castlebay
|
Coll
|
Craignure
|
Gourock
|
Lochboisdale
|
Lochmaddy
|
Oban Number 1 berth*
|
Oban Number 2 berth
|
Stornoway
|
Tarbert
|
Tiree
|
Uig
|
Ullapool
|
*After planned works
- Asked by: Michael Russell, MSP for Argyll and Bute, Scottish National Party
-
Date lodged: Friday, 19 June 2015
-
Current Status:
Answered by Derek Mackay on 6 July 2015
To ask the Scottish Government, further to the answer to question S4W-25867 by Derek MacKay on 10 June 2015, whether, prior to the procurement of these vessels, it will publish an estimate of the cost of the work required to upgrade existing piers and harbours to allow the vessels to serve the (a) 15 piers and harbours requiring no or only minor modification and (b) other piers and harbours on the CalMac route that can accommodate only vessels of a length of (i) 90m, (ii) 80m and (iii) 70m.
Answer
The objective of the specification for the new vessels was to meet forecast carrying capacities for passengers, vehicles and freight without the need for major harbour works. It was therefore anticipated that shoreside costs linked directly to the introduction of new vessels would be minimised and covered by existing budget allocations.
Prior to any contract award, Caledonian Maritime Assets Ltd will ascertain that the new vessels will be suitable for the existing piers and harbours on the routes identified for their initial deployment. Minor modifications may be needed but it will not be possible to specify those, or their costs, until a vessel design has been finalised with the successful shipyard.
The cost of upgrading piers and harbours that cannot currently accommodate a vessel of 100m in length will be looked at in a forthcoming phase of the vessel replacement plan.
- Asked by: Michael Russell, MSP for Argyll and Bute, Scottish National Party
-
Date lodged: Tuesday, 09 June 2015
-
Current Status:
Answered by Aileen McLeod on 23 June 2015
To ask the Scottish Government, in light of complaints and objections from the local community and forest operators, including Forestry Commission Scotland, regarding the designation of Core Path C223 in the Cowal area, what its response is to the statement by the chief executive of Argyll and Bute Council in a letter to a complainant that "The Council has been directed by the Scottish Government to include C223 in the list of Core Paths and there is no process to reverse this."
Answer
All objections to the Argyll and Bute Council Core Paths Plan were considered by reporters from the Directorate for Planning and Environmental Appeals, who investigated the circumstances surrounding the objections and made recommendations to Scottish Ministers.
The recommendation in respect of Core Path C223 was accepted by Scottish Ministers who, under the powers in the Land Reform (Scotland) Act 2003 section 18(7), have directed Argyll and Bute Council to adopt their core paths plan. The Core Path C223 is also an agreed timber haulage route and, in recognition of this, the direction letter asks the council to ensure that there is information and signage both for vehicle drivers and path users, and that the situation is monitored.
- Asked by: Michael Russell, MSP for Argyll and Bute, Scottish National Party
-
Date lodged: Thursday, 04 June 2015
-
Current Status:
Answered by Michael Matheson on 17 June 2015
To ask the Scottish Government what action it will take to ensure that affidavit administration services are available in all (a) rural areas and (b) islands.
Answer
<>I refer the member to the answer to question S4W-25965 on 17 June 2015 All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at:
http://www.scottish.parliament.uk/parliamentarybusiness/28877.aspx.
- Asked by: Michael Russell, MSP for Argyll and Bute, Scottish National Party
-
Date lodged: Thursday, 04 June 2015
-
Current Status:
Answered by Michael Matheson on 17 June 2015
To ask the Scottish Government (a) on which islands and (b) in which rural areas affidavit administration services are not available because of an absence of JPs, and what arrangements it is putting in place to resolve this.
Answer
The Scottish Government recognises the difficulties on some islands and remote rural areas if there is not a local Justice of the Peace available to sign affidavits. Affidavits can also be signed by notary publics, although there may be a charge for this.
- Asked by: Michael Russell, MSP for Argyll and Bute, Scottish National Party
-
Date lodged: Friday, 05 June 2015
-
Current Status:
Answered by Derek Mackay on 11 June 2015
To ask the Scottish Government what action it takes to ensure that Transport Scotland and Caledonian MacBrayne have arrangements in place to ensure that petrol supplies can be conveyed by scheduled ferry to Lismore.
Answer
The transportation of petrol by CalMac on the Lismore ferry service is subject to the requirements of the Carriage of Dangerous Goods legislation. Roadtankers carrying up to 12000 litres of petrol are able to travel on the MV Loch Striven which operates the service.