- Asked by: Jamie McGrigor, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 02 April 2013
-
Current Status:
Answered by Keith Brown on 24 April 2013
To ask the Scottish Government when the final report by MVA Consultancy on the removal of road equivalent tariff from commercial vehicles in the Western Isles will be published.
Answer
We are finalising publication arrangements, and anticipate that the final report into the post-RET commercial vehicle fares impact study will be published shortly.
- Asked by: Jamie McGrigor, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 03 April 2013
-
Current Status:
Answered by Margaret Burgess on 22 April 2013
To ask the Scottish Government, further to the answer to question S4W-13464 by Margaret Burgess on 27 March 2013, whether it will provide the information broken down by postcode area.
Answer
Information on the relative costs of housebuilding cannot be provided by postcode, because the volume of information is not sufficient for meaningful sub-analysis at this level.
- Asked by: Jamie McGrigor, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 26 March 2013
-
Current Status:
Answered by Keith Brown on 18 April 2013
To ask the Scottish Government, further to the answer to question S4W-13438 by Keith Brown on 18 March 2013, where in the contract for the Dunoon-Gourock service the specification is set out regarding the requirement for vessels to be able to operate reliably in the weather conditions on the route.
Answer
In my reply to question S4W-13438, I explained that each contract specifies the vessels to be deployed and contains detailed provisions for their maintenance and operation.
In the case of the contract between the Scottish Ministers and Argyll Ferries Ltd for the provision of the Gourock-Dunoon Ferry Service:
Part 1, Section 2 (page 47-48) of the Schedule to the contract includes the specification of the vessels (the MV AliCat and MV Banrion Chonamara, renamed the MV Argyll Flyer).
Part 2, Section 2 (page 51-52) of the Schedule to the contract sets out requirements regarding the vessels.
Part 2, Section 5 (page 57) of the Schedule to the contract sets out operational undertakings applying to the contract which include maintenance and operation of the vessels.
A copy of the contract can be found at;
http://www.transportscotland.gov.uk/water/ferries/subsidised/gourock-dunoon.
- Asked by: Jamie McGrigor, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 02 April 2013
-
Current Status:
Answered by Keith Brown on 15 April 2013
To ask the Scottish Government, further to the answer to question S4W-13662 by Keith Brown on 27 March 2013, what provisions there are to ensure that vessels are able to operate safely in the weather conditions that can be anticipated on the Firth of Clyde.
Answer
The Masters operate the vessels in accordance with the Safety Management Certificates issued by the Maritime and Coastguard Agency, taking cognisance of any individual limitations expressed therein. In addition, Argyll Ferries Ltd have safety management systems which provide further guidance on actions to be taken, or factors to be considered, in various circumstances, including adverse weather.
- Asked by: Jamie McGrigor, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 02 April 2013
-
Current Status:
Answered by Keith Brown on 15 April 2013
To ask the Scottish Government, further to the answer to question S4W-13661 by Keith Brown on 27 March 2013, how many staff who received a voluntary severance package had an employment contract with Argyll Ferries Ltd.
Answer
One member of staff who had an employment contract with Argyll Ferries Ltd took the voluntary severance package.
- Asked by: Jamie McGrigor, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 02 April 2013
-
Current Status:
Answered by Keith Brown on 15 April 2013
To ask the Scottish Government, further to the answer to question S4W-13660 by Keith Brown on 27 March 2013, what the increased cost to CalMac Ferries Ltd will be.
Answer
I refer the member to the answer to question S4W-13660 on 27 March 2013. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at:
http://www.scottish.parliament.uk/parliamentarybusiness/28877.aspx.
- Asked by: Jamie McGrigor, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 14 March 2013
-
Current Status:
Answered by Keith Brown on 27 March 2013
To ask the Scottish Government, further to the answer to question S4W-08882 by Keith Brown on 15 August 2012, what provisions are in the contract with Argyll Ferries Ltd to ensure that the service operates with reasonable reliability in the weather prevailing.
Answer
Argyll Ferries Ltd shall provide the services in accordance with the published timetable except in the event of a Relief Event. There are a number of Relief Events specified in the contract to ensure that the services only operate when it is safe to do so. Cancellations or disruption due to adverse weather, tidal conditions or any other safety factor, outwith Argyll Ferries Ltd’s reasonable control, are permissible Relief Events.
- Asked by: Jamie McGrigor, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 14 March 2013
-
Current Status:
Answered by Keith Brown on 27 March 2013
To ask the Scottish Government when CalMac Ferries Ltd will stop paying Caledonian Maritime Assets Ltd a single harbour access charge (HAC) and start paying berthing dues and harbour charges; what HAC CalMac Ferries Ltd pays; what the increase in costs to the company will be as a result of the change, and whether the Scottish Government will compensate the company for the increase.
Answer
CalMac Ferries Ltd (CFL) will cease paying a Harbour Access Charge to Caledonian Maritime Assets Ltd (CMAL) on 30 September 2013 on the expiry of the existing Clyde and Hebrides Ferry Services agreements. A new charging agreement will commence on 1 October 2013.
CFL currently pay approximately £1,918,080 per year as a Harbour Access Charge.
Costs of the new agreement are still being finalised between CFL and CMAL but will reflect the costs to CMAL to maintain, operate and provide the necessary capital investment to improve the harbour facilities. The final sum will be broadly in line with CMAL’s published tariff.
The terms of the Clyde and Hebrides Ferry Services contract between CFL and Transport Scotland state that: “in the event that the Operator receives notice that the dues payable at any Ports shall increase during any Service Year and such increase has not been allowed for in the Base Case of that Service Year either Party shall be entitled to require a Revised Costs Base Case Recalculation for the then current and subsequent Service Years.” Given that, and subject to agreement between Transport Scotland and CFL, it is anticipated that Transport Scotland will recompense CFL should there be any increase in costs.
- Asked by: Jamie McGrigor, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 14 March 2013
-
Current Status:
Answered by Keith Brown on 27 March 2013
To ask the Scottish Government, further to the answer to question S4W-12378 by Keith Brown on 29 January 2013, whether all staff who received redundancy payments had employment contracts with Argyll Ferries Ltd when the payments were made and, if not, for what reason the payments were not made by the employing company.
Answer
Not all staff who received a voluntary severance package had employment contracts with Argyll Ferries Ltd.
The reasons for this were set out in the answer to question S4W-13285 on 6 March 2013. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at: http://www.scottish.parliament.uk/parliamentarybusiness/28877.aspx.
- Asked by: Jamie McGrigor, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 05 March 2013
-
Current Status:
Answered by Margaret Burgess on 27 March 2013
To ask the Scottish Government what information it has on housebuilding costs in (a) island and (b) remote rural areas and how these compare with costs in less remote mainland areas.
Answer
The Scottish Government analyses the costs of subsidised affordable housing developments at local authority level, with a subdivision of the Highland council area. The most recent figures, shown in the following table, indicate that costs were above the Scotland average in the three Island authorities and a number of other rural authorities. The Scottish Government does not hold regional information on the costs of private housebuilding.
Shetland
|
average costs 22% above Scotland average
|
Argyll & Bute
|
18% above Scotland average
|
Orkney
|
15% above Scotland average
|
Eilean Siar
|
7% above Scotland average
|
Dumfries & Galloway
|
5% above Scotland average
|
Highland South (Lochaber and Skye & Lochalsh)
|
3% above Scotland average
|
Moray, Aberdeenshire
|
level with Scotland average
|
Scottish Borders
|
1% below Scotland average
|
Perth & Kinross, Angus
|
2% below Scotland average
|