- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Wednesday, 06 February 2002
-
Current Status:
Answered by Ross Finnie on 26 February 2002
To ask the Scottish Executive whether the West of Scotland Water Authority will nominate a specific member of staff to be responsible for liaising with local residents while the Environmental Statement is being exhibited by the authority and during construction of the proposed water treatment plant at Milngavie as part of the Katrine Water Project.
Answer
This is a matter for West of Scotland Water, and I have asked the Chief Executive to respond. His response is as follows:The Environmental Statement is part of the planning process and in the first instance all correspondence on this matter should be addressed to the Head of Partnership & Planning, East Dunbartonshire Council, The Triangle, Kirkintilloch Road, Bishopbriggs G66 4TJ.West of Scotland Water's Katrine Water Project team are currently responding to queries from residents on all matters relating to the project including the Environmental Statement. Members of the public can contact either the Katrine Water Project Office at Kirk Wynd House, Montgomery Place, The Village, East Kilbride G74 4BF, telephone number 01355-581469 or the authority's Customer Helpline number on 0808-100-5333 should they wish further information.For community liaison during the construction phase, I refer the member to the answer given to question S1W-22386 on 8 February 2002.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Friday, 08 February 2002
-
Current Status:
Answered by Ross Finnie on 22 February 2002
To ask the Scottish Executive what consultation was undertaken by West of Scotland Water before it determined its preferred option for the location of a new water treatment plant as part of the Katrine Water Project.
Answer
This is a matter for West of Scotland Water, and I have asked the Chief Executive to respond. His response is as follows:The preferred option became a firm proposal when the planning application was submitted. Prior to this Katrine Water Project was very proactive in communicating with statutory and non-statutory consultees. In total 71 statutory and non-statutory consultees were contacted. Consultations began as early as March 2000 as part of the Babtie Mott Strategic Review. As the project developed, meetings were held with the major consultees and presentations were given. Initially this was to explain the large numbers of options, then to seek their views about the short-listed options, and more recently to include for any concerns they had in the design and development of the preferred scheme. In addition, during the process of surveying possible sites and pipe routes, members of the project team and our land agents visited some 75 landowners, occupiers and tenants. A further consultation process was undertaken as part of their Environmental Impact Assessment by our consultants, ERM. They wrote to 62 bodies giving details of our proposals and seeking their comments. The project team has also met with and given presentations to, on several occasions, local community and interest groups including: Baldernock Community Council, Milngavie Community Council, the Mugdock Association, Strathblane Community Council and the Baldernock Amenity Society.In August 2001, once the preferred scheme had been identified, a website (www.katrinewaterproject.com) was established and a caravan display taken to the Milngavie and Baldernock areas. It was exhibited over a continuous period of 26 days and received nearly 3,000 visitors. Comment sheets were available. Those completed showed no disapproving comments on the detail of the initial proposal itself. Some asked for information on other options considered and most raised concerns on aspects of project implementation.Following the caravan initiative, public meetings were held in Balmore and Milngavie on 29 and 30 August to explain the project proposals, respond to queries and seek feedback. To satisfy requests for further information on the site selection process, a third meeting was held on 26 September. At that meeting further documentation was handed out which gave cost comparisons and explained how the data previously given out had been used to come to the preferred option.Since the planning application was submitted, material relating to the submission has been displayed at six local venues where members of the project team have been available to explain the proposals to anyone interested. At all stages the various public meetings and displays have been publicised in the local press and by widespread distribution of posters.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Friday, 08 February 2002
-
Current Status:
Answered by Ross Finnie on 22 February 2002
To ask the Scottish Executive what will happen to the eight members of West of Scotland Water's tourist office at Loch Katrine and the SS Walter Scott screw steamer following the commissioning of a new water treatment plant at Milngavie.
Answer
Tourism at Loch Katrine and the Katrine Water Project are not related.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Friday, 08 February 2002
-
Current Status:
Answered by Ross Finnie on 22 February 2002
To ask the Scottish Executive what impact any delays in the development approvals process would have on the costs of the Katrine Water Project.
Answer
This is a matter for West of Scotland Water, and I have asked the Chief Executive to respond. His response is as follows:Any delay in the approvals process will have an adverse financial impact on the Katrine water Project.Planning was submitted to East Dunbartonshire Council in November and the statutory approval/decision period is four months, i.e. until mid-March 2002. Thereafter there is a 28-day period for Scottish ministers to give listed building approval bringing us to mid-April. A delay of greater than four to six weeks will inconvenience the excavation operations which rely on better weather for their efficiency. This means that more muck would be shifted in the winter months resulting in increased operation times and costs.Should a planning inquiry be deemed necessary, the consequent delays and costs are a larger order of magnitude. Our best advice is that an inquiry cannot be carried out in less than one year and is more likely to take 18 to 24 months. Direct costs of such an enquiry could easily be in the order of £2.5 to £3 million. Consequential increased construction costs resulting from the delay could bring this figure up to £10 million.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Friday, 08 February 2002
-
Current Status:
Answered by Ross Finnie on 22 February 2002
To ask the Scottish Executive whether it will detail the reasons for the decision by West of Scotland Water Authority to engage Stirling Water as contractor for the Katrine Water Project.
Answer
I refer the member to the answer given to question S1W-22821 on 20 February 2002.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Friday, 08 February 2002
-
Current Status:
Answered by Ross Finnie on 22 February 2002
To ask the Scottish Executive on what basis West of Scotland Water considers the construction of a new water treatment plant at Milngavie to be the best value solution for the Katrine Water Project.
Answer
I refer the member to the answers given to questions S1W-22387 (8 February 2002), S1W-22134 (5 February 2002), S1W-22133 (5 February 2002), S1W-22086 (4 February 2002) and S1W-22155 (11 February 2002).
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Friday, 08 February 2002
-
Current Status:
Answered by Ross Finnie on 22 February 2002
To ask the Scottish Executive what the highest point above ground will be of the proposed new water treatment plant at Milngavie.
Answer
This is a matter for West of Scotland Water, and I have asked the Chief Executive to respond. His response is as follows:The highest point of the proposed new treatment works at Milngavie is the roof above the lime storage silo at the north end of the treatment building which is at an elevation of 126.4 meters above Ordnance Datum (AOD). The general level of the ridge of the treatment building is 125.4 meters AOD. The level of the hillside behind and to the west of the building is 139 meters AOD.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Friday, 08 February 2002
-
Current Status:
Answered by Ross Finnie on 22 February 2002
To ask the Scottish Executive when the construction of the works associated with the Katrine Water Project will commence and be completed.
Answer
This is a matter for West of Scotland Water, and I have asked the Chief Executive to respond. His response is as follows:The construction of the works associated with the Katrine Water Project cannot commence until East Dunbartonshire Council (EDC) grants planning approval. The work must be constructed, commissioned and supply drinking water to the Glasgow distribution system by December 2005 in order to comply with drinking water quality regulations.If EDC grants planning approval, and Scottish ministers grant listed building approval by June this year, the construction work should be completed by mid-summer 2005.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Friday, 08 February 2002
-
Current Status:
Answered by Allan Wilson on 22 February 2002
To ask the Scottish Executive what plans it has to enhance the provision of greenspace in East and West Dunbartonshire.
Answer
The Scottish Executive recently approved Scottish Natural Heritage's business case for their "Greenspace for Communities" initiative. This will allow Scottish Natural Heritage, the Glasgow and Clyde Valley Greenspace Trust, and other organisations including local authorities within the area, to enhance and manage greenspaces with the aid of additional funding from the New Opportunities Fund.
- Asked by: Des McNulty, MSP for Clydebank and Milngavie, Scottish Labour
-
Date lodged: Friday, 08 February 2002
-
Current Status:
Answered by Iain Gray on 22 February 2002
To ask the Scottish Executive how successful it has been in assisting with the establishment of credit unions and what is being done to ensure that existing credit unions, such as those in Dalmuir, Dunbartonshire and East Clydebank, continue to trade successfully.
Answer
The Executive will assist the development of the credit union movement in Scotland through the implementation of the action plan "Unlocking the Potential". £1.5 million of new resources are available over this and the next two years to help implement the plan. To help credit unions meet the Financial Services Authority's new regulatory changes (coming into effect on 1 July), every credit union in Scotland has been offered free compliance training.