- Asked by: Linda Fabiani, MSP for Central Scotland, Scottish National Party
-
Date lodged: Thursday, 04 May 2000
-
Current Status:
Answered by David Steel on 17 May 2000
To ask the Presiding Officer, further to his answer to question S1W-5936 on 6 April 2000, what alternative solutions were considered for the provision of car parking for the Holyrood complex and what the comparative costs of each solution were.
Answer
The original provision of 135 car parking spaces for the Parliament building was influenced primarily by security considerations which recommended a secure space for each MSP, and also by building regulations which requires a proportionate number of spaces to be provided for the disabled, in this case six spaces. Following a survey of MSP's, and after weighing up both security and environmental considerations the SPCB decided that the number could sensibly be reduced to 65 while still retaining six spaces for the disabled. This decision was reported to MSPs in SPCB Report No. 3 of December 1999.
- Asked by: Linda Fabiani, MSP for Central Scotland, Scottish National Party
-
Date lodged: Thursday, 04 May 2000
-
Current Status:
Answered by David Steel on 17 May 2000
To ask the Presiding Officer, further to his answer to question S1W-5938 on 6 April 2000, what the current base works cost estimate is for the Holyrood Project; when this figure was last contractually altered for the purpose of calculating the fees of the design team; what the dates were of any previous alteration to this figure, and on whose authority any previous alterations to this figure were made.
Answer
The current base works cost estimate for the Holyrood Project is £108 million. This figure was agreed by Parliament following the Holyrood Project debate on 5 April 2000. The previous base works cost estimate was £62 million and was also agreed by Parliament following the first Holyrood Project debate on 17 June 1999. The Design Team fees will be adjusted in line with the latest change.
- Asked by: Linda Fabiani, MSP for Central Scotland, Scottish National Party
-
Date lodged: Thursday, 04 May 2000
-
Current Status:
Answered by David Steel on 17 May 2000
To ask the Presiding Officer what unforeseen site conditions have been experienced during the planning period for the Holyrood complex and the period of construction of the substructure and what additional costs have been incurred as a result.
Answer
During the planning phase of the Holyrood project, geotechnical surveys revealed the presence of rock, subterranean wells and ground water. The design for the substructure of the building took these ground conditions into account, and therefore no additional costs were incurred.
- Asked by: Linda Fabiani, MSP for Central Scotland, Scottish National Party
-
Date lodged: Tuesday, 18 April 2000
-
Current Status:
Answered by Sarah Boyack on 17 May 2000
To ask the Scottish Executive whether the review of regional Eurostar services has been the subject of discussion, at ministerial level, between it and representatives of (a) the Scotland Office or (b) the Department of the Environment, Transport and the Regions.
Answer
European rail services are a reserved matter. During its review of Regional Eurostar for the Department of the Environment, Transport and the Regions, Arthur D. Little consulted officials of the Scottish Executive.
- Asked by: Linda Fabiani, MSP for Central Scotland, Scottish National Party
-
Date lodged: Tuesday, 18 April 2000
-
Current Status:
Answered by Sarah Boyack on 17 May 2000
To ask the Scottish Executive whether it will place a copy of its submission to Arthur D Little consultants in respect of the review of regional Eurostar services in the Scottish Parliament Information Centre.
Answer
I have arranged for the summary report and its appendices to be placed in SPICe.
- Asked by: Linda Fabiani, MSP for Central Scotland, Scottish National Party
-
Date lodged: Thursday, 13 April 2000
-
Current Status:
Answered by David Steel on 4 May 2000
To ask the Presiding Officer who were commissioned to submit proposals for the Scottish Parliament "logo".
Answer
Only one logo design has been commissioned for the Scottish Parliament. Redpath were commissioned to propose design ideas to accompany their existing text-based corporate identity, one of which was based upon the winning entry in the students competition held last year. One of the designs proposed by Redpath was developed for full design and production as the logo. The design costs are commercial-in-confidence, but the overall project costs, which cover several aspects including copyright, design, and trademark application, are around £20,000.
- Asked by: Linda Fabiani, MSP for Central Scotland, Scottish National Party
-
Date lodged: Thursday, 13 April 2000
-
Current Status:
Answered by David Steel on 3 May 2000
To ask the Presiding Officer when the proposed Scottish Parliament "logo" will be laid before the Parliament for ratification or otherwise and why the "logo" has been printed on Scottish Parliament documentation prior to such ratification or otherwise.
Answer
One of the primary functions of the SPCB is to provide property, staff and services for the Parliament's purposes. Provision of a logo is the provision of property for the Parliament's purposes and so it was considered by the SPCB that ratification by the Parliament was not a requirement. However, as stated in the written answer to PQ's 5764-5766, consultation with business managers took place during the selection process.
- Asked by: Linda Fabiani, MSP for Central Scotland, Scottish National Party
-
Date lodged: Thursday, 13 April 2000
-
Current Status:
Answered by David Steel on 3 May 2000
To ask the Presiding Officer how many Scottish Parliament "logo" designs were commissioned by the Scottish Parliamentary Corporate Body and at what cost individually and in total.
Answer
Only one logo design has been commissioned for the Scottish Parliament. Redpath were commissioned to propose design ideas, one of which was based upon the winning entry in the students competition held last year. One of the designs proposed by Redpath was developed for full design and production as the logo. The design costs are commercial-in-confidence, but the overall project costs, which cover several aspects including copyright, design, and trademark application, are around £20,000.
- Asked by: Linda Fabiani, MSP for Central Scotland, Scottish National Party
-
Date lodged: Monday, 17 April 2000
-
Current Status:
Answered by David Steel on 3 May 2000
To ask the Presiding Officer whether any consultations have been held with the Lord Lyon regarding the logo proposed for use by the Scottish Parliament.
Answer
Consultations with the Lord Lyon have of course been held during the process of selecting the logo and he has provided his professional advice and support. He has granted the necessary permissions for the logo.
- Asked by: Linda Fabiani, MSP for Central Scotland, Scottish National Party
-
Date lodged: Monday, 17 April 2000
-
Current Status:
Answered by David Steel on 3 May 2000
To ask the Presiding Officer whether the proposed Scottish Parliament logo is to be subject to any application for copyright; if so, to whom and what the penalties will be for any breach of copyright.
Answer
The SPCB has copyright in the logo and there is no requirement for an application for copyright as such. If any third party were to breach the SPCB's copyright, infringement proceedings under the Copyright Designs and Patents Act 1988 could result. Any penalty for breach of copyright would be for determination by a court.