- Asked by: Elaine Smith, MSP for Coatbridge and Chryston, Scottish Labour
-
Date lodged: Monday, 06 October 2014
-
Current Status:
Answered by Keith Brown on 30 October 2014
To ask the Scottish Government when it will announce the successful bidder for the ScotRail franchise and on what date it will publish the franchise agreement.
Answer
On 8 October 2014, Scottish Ministers announced the intention to award the new ScotRail franchise to Abellio ScotRail Limited.
The ScotRail franchise agreement will be published in due course.
- Asked by: Elaine Smith, MSP for Coatbridge and Chryston, Scottish Labour
-
Date lodged: Monday, 06 October 2014
-
Current Status:
Answered by Keith Brown on 30 October 2014
To ask the Scottish Government what discussions with rolling stock companies it had regarding the design of the invitation to tender for ScotRail services published in January 2014 and whether it discussed the deadline for connecting rolling stock toilets to effluent retention tanks.
Answer
During early 2013, Transport Scotland held a series of market briefings with the rail industry about the franchise procurement exercise and the franchise objectives. The draft invitation to tender (ITT) was issued to pre-qualified bidders in November 2013 with the final ITT issued to bidders in January 2014.
From December 2017 there will be no ScotRail or Caledonian Sleeper franchise-operated rolling stock that discharges toilet effluent on to the track.
- Asked by: Elaine Smith, MSP for Coatbridge and Chryston, Scottish Labour
-
Date lodged: Monday, 06 October 2014
-
Current Status:
Answered by Keith Brown on 30 October 2014
To ask the Scottish Government what guidance on passenger toilet facilities it issued to the operator of ScotRail services prior to the Commonwealth Games 2014.
Answer
Transport Scotland engage regularly with ScotRail on rolling stock and station improvements to passenger facilities. The current ScotRail franchise requires that ScotRail passenger toilet facilities are fully functional including all lights, locks and seats.
Recent discussions on passenger toilet facilities included the ongoing refurbishment of the class 318 trains which are being fitted with new compliant passenger toilet facilities and the upgrade to the toilets at Glasgow Queen Street station.
- Asked by: Elaine Smith, MSP for Coatbridge and Chryston, Scottish Labour
-
Date lodged: Monday, 06 October 2014
-
Current Status:
Answered by Keith Brown on 30 October 2014
To ask the Scottish Government whether ScotRail rolling stock used during the Commonwealth Games 2014 was fitted with effluent retention tanks and what discussions it had with the operator regarding the discharge of effluent on the tracks on ScotRail routes prior to the start of the Games.
Answer
All ScotRail rolling stock used during the Commonwealth Games were fitted with effluent retention tanks with the exception of class 156 trains and class 314 trains. The class 314 trains are not fitted with toilets. No discussions were held regarding the discharge of effluent on the tracks prior to the start of the Games.
- Asked by: Elaine Smith, MSP for Coatbridge and Chryston, Scottish Labour
-
Date lodged: Monday, 06 October 2014
-
Current Status:
Answered by Keith Brown on 30 October 2014
To ask the Scottish Government what (a) service level, (b) station and (c) infrastructure improvements it has achieved on each franchised ScotRail passenger route in each year since 2012 and how each was funded.
Answer
Since 2012 the Scottish Government has worked with ScotRail to achieve many improvements to service level, stations and infrastructure. The improvements and funding is set out in the following table by Regional Transport Partnership (RTP) area.
|
RTP
|
Improvement since 2012
|
Funded
|
|
SPT area routes - Paisley Canal, Anniesland, Whifflet, East Kilbride, Neilston, Newton, Barrhead, Kilmarnock, Dunbartonshire, Lanarkshire, Ayrshire, Inverclyde, Shotts
|
|
|
|
(a) service level
|
|
Sunday service on Edinburgh to Glasgow via Shotts
|
No increase to franchise payments
|
|
New two hourly service between Glasgow Central and Edinburgh via Carstairs
|
Scottish Goverment - franchise
|
|
Paisley Canal electrification has provided journey time improvements
|
Network RailRegulatory Asset Base (RAB)
|
|
Increased frequency and reduced journey time between Glasgow and Ayr – Monday to Saturday (from two to four trains per hour)
|
Scottish Government – franchise
|
|
Increased frequency of service between Glasgow and Ayr on Sundays (from hourly to half hourly with earlier start and later finish)
|
No increase to franchise payments
|
|
Introduction of a two hourly service between Ayr and Edinburgh via Glasgow Central between peak periods;
Increased frequency of service between Glasgow and Gourock (from three to four per hour)
|
Scottish Government - franchise
|
|
Sunday service introduced to call at Dalmarnock station;
Sunday service introduced to call at Anderston station;
New hourly Sunday service between Glasgow and Anniesland
|
No increase to franchise payments
|
|
Electrification of the Cumbernauld route has enabled three services per hour to be provided (previously two per hour); two extended from Dalmuir to Springburn and one service between Glasgow Queen Street and Falkirk Grahamston via Cumbernauld
|
Scottish Government - franchise
|
|
Increased frequency between Glasgow Queen Street and Edinburgh via Airdrie to Bathgate providing a half hourly service from start of service;
Recast of Argyle Line services with improved journey time on some routes;
Introduction of electrified services on the Whifflet route (some routes have also been improved with early morning, later services or additional station calls)
|
No increase to franchise payments
|
|
|
(b) station
|
|
Cumbernauld redevelopment
|
Network Rail RAB
|
|
Dalmarnock redevelopment
|
Third party funding with RAB contribution
|
|
Newton - new lifts and footbridge;
Hyndland - new lifts and footbridge;
Milliken Park – ramp
|
Network Rail RAB
|
|
Irvine – car park expansion
|
Scottish Government budget – shovel ready
|
|
Glasgow Central High level, Low Level, Charing Cross, Anderston and Argyle Street – Gateline
|
Network Rail RAB
|
|
Glasgow Queen Street toilet refurbishment
|
Scottish Government - franchise
|
|
Pollokshaws West – disused station building: cycle hire/repairs;
New Cumnock – disused station building: café/youth hub;
Helensburgh Central – mixed martial arts gym
|
Scottish Government – Station Community Regeneration Fund (SCRF)
|
|
A package of station enhancements have also been carried out at a large number of stations in the SPT area such as new customer information screens, new shelters, cycle racks, ticket vending machines, wi-fi, seating, automatic ticket doors, adjustable counters, environmental improvements etc.
|
Scottish Government – franchise/ third party
|
|
|
(c) infrastructure
|
Rutherglen and Coatbridge (Whifflet electrification);
Cumbernauld electrification;
Paisley corridor improvements;
Paisley Canal electrification;
Newton junction re-doubling to provide improved line speed;
Busby Junction doubling;
Whitecraigs turnback
|
RAB
|
|
SWESTRANS routes – Stranraer, Carlisle and Newcastle
|
|
|
|
(a) service level
|
Early morning service from Dumfries to Glasgow;
Additional Sunday evening Glasgow to Stranraer service
|
No increase to franchise payments
|
|
(b) station
|
A package of station enhancements have also been carried out at a number of stations in the area such as new customer information screens, new shelters, cycle racks, ticket vending machines, wi-fi, seating, automatic ticket doors, adjustable counters, environmental improvements etc.
|
Scottish Government – franchise/third party
|
|
(c) infrastructure
|
Hurlford improvement;
Dumfries station turnback and line speed improvements
|
Network Rail RAB
|
|
SEStran routes – Fife, Newcraighall, North Berwick, Dunbar, Edinburgh-Glasgow
|
|
|
|
(a) service level
|
Enhanced Sunday service on Fife Circle providing an hourly frequency;
New Sunday Perth to Edinburgh service via Dunfermline and return journey in the evening;
Introduction of a Saturday service between Edinburgh and Dunbar;
Increased frequency between Glasgow Queen Street and Edinburgh via Falkirk High providing a half hourly service from start of service;
Increased frequency of Sunday service between Stirling and Edinburgh
|
No increase to franchise payments
|
|
(b) station
|
Haymarket redevelopment;
Edinburgh Waverley redevelopment and steps upgrade;
Linlithgow – new lifts;
Rosyth – new access ramp;
Shotts – new access ramp;
Camelon line speed improvement;
Ladybank junction
|
Network Rail RAB
|
|
|
Bathgate – car park expansion
|
Scottish Government budget - shovel ready
|
|
|
North Queensferry – disused station building: exhibition centre
|
Scottish Government - SCRF
|
|
|
A package of station enhancements have also been carried out at a number of stations in the area such as new customer information screens, new shelters, cycle racks, ticket vending machines, wi-fi, seating, automatic ticket doors, adjustable counters, environmental improvements etc.
|
Scottish Government – franchise/ third party
|
|
(c) infrastructure
|
No improvements
|
|
|
Tactran routes – Dundee, Stirling, Perth, Dunblane, Alloa
|
|
|
|
(a) service level
|
Additional calls at Monifeith, Broughty; Ferry and Invergowrie stations on Monday to Saturday;
Early morning Dundee to Inverness service;
|
No increase to franchise payments
|
|
(b) station
|
|
Gleneagles station refurbishment and enhancement
|
RAB and other third parties
|
|
Dunblane – new footbridge;
Perth – new footbridge, Gateline
|
Network Rail RAB
|
|
Ladybank – new car park
|
Scottish Government budget - shovel ready
|
|
Ladybank – disused station building: multi-purpose meeting room
|
Scottish Government - SCRF
|
|
A package of station enhancements have also been carried out at a number of stations in the area such as new customer information screens , new shelters, cycle racks, ticket vending machines, wi-fi, seating, automatic ticket doors, adjustable counters, environmental improvements etc.
|
Scottish Government – franchise/ third party
|
|
|
(c) infrastructure
|
Stirling Middle junction;
Barnhill line speed improvement
|
Network Rail RAB
|
|
Nestrans routes -
Aberdeen, Inverness,
|
|
|
|
(a) service level
|
|
Additional weekday calls at Portlethen and Laurencekirk stations
|
No increase to franchise payments
|
|
Increased frequency of service between Glasgow and Aberdeen on a Sunday providing an hourly service (previously two hourly).
|
Scottish Government - franchise
|
|
|
(b) station
|
|
Dyce – new footbridge;
Montrose – new footbridge
|
Network Rail RAB
|
|
Keith – car park expansion
|
Scottish Government – shovel ready
|
|
A package of station enhancements have also been carried out at a number of stations in the area such as new customer information screens, new shelters, cycle racks, ticket vending machines, wi-fi, seating, automatic ticket doors, adjustable counters, environmental improvements etc.
|
Scottish Government – franchise/ third party
|
|
|
(c) infrastructure
|
No improvements
|
|
|
HITRANS routes - Oban, Mallaig, Wick, Thurso, Kyle of Lochalsh, Fort William
|
|
|
|
(a) service level
|
|
New station call at Conon Bridge station
|
No increase to franchise payments
|
|
Increased frequency of service between Glasgow and Oban on weekdays (from three services to six service per day)
|
Scottish Government – franchise
|
|
Increased frequency of service between Glasgow and Oban on Sunday (from one service to two services)
|
No increase to franchise payments
|
|
|
(b) station
|
|
Conon Bridge station development
|
Scottish Government with contribution from other third parties
|
|
Inverness – Gateline
|
Network Rail RAB
|
|
Tain – disused station building: restaurant and bar;
Helmsdale – disused station building: Holiday let
|
Scottish Government - SCRF
|
|
A package of station enhancements have also been carried out at a number of stations in the area such as new customer information screens, new shelters, cycle racks, ticket vending machines, seating, automatic ticket doors, adjustable counters, environmental improvements etc.
|
Scottish Government – franchise/ third party
|
|
|
(c) infrastructure
|
No improvements
|
|
- Asked by: Elaine Smith, MSP for Coatbridge and Chryston, Scottish Labour
-
Date lodged: Monday, 06 October 2014
-
Current Status:
Answered by Keith Brown on 30 October 2014
To ask the Scottish Government what assessment it has made of the benefits to rail freight (a) volumes and (b) services of the next franchised ScotRail contract, broken down by (i) route and (ii) region.
Answer
We have a very clear expectation as part of our overall strategy that Abellio ScotRail will work closely with the rail freight sector, Network Rail and other stakeholders to maximise the economic and social impact of Scotland’s railways. For example, in the efficient delivery of major projects such as the Highland Main Line improvements and the identification, development and delivery of high value, opportunity led interventions through the CP5 funds.
- Asked by: Elaine Smith, MSP for Coatbridge and Chryston, Scottish Labour
-
Date lodged: Monday, 06 October 2014
-
Current Status:
Answered by Keith Brown on 30 October 2014
To ask the Scottish Government what assessment it has made of the benefits to passengers of the next franchised ScotRail contract, broken down by (a) passenger service route and (b) region.
Answer
<>The evaluation criteria for franchise award was 65% price, 35% quality. The winning bidder’s quality submission contained a variety of benefits to passengers. Details of these benefits by route and by region may be found here:
http://www.transportscotland.gov.uk/rail/scotrail-franchise/scotrail-franchise-renewal-programme
- Asked by: Elaine Smith, MSP for Coatbridge and Chryston, Scottish Labour
-
Date lodged: Thursday, 02 October 2014
-
Current Status:
Answered by Michael Matheson on 28 October 2014
To ask the Scottish Government what arrangements it has made to support and encourage the breastfeeding of children by their mothers in each year since 2005.
Answer
The Scottish Government has continuously made arrangements to support and encourage the breastfeeding of children by their mothers since 2005 through a range of activities and interventions which include:
| Year | Activity |
| 2005 | The Breastfeeding etc. (Scotland) Act 2005 to support the rights of breastfeeding mothers. |
| 2006 | Health Improvement, Efficiency, Access to Treatment (HEAT) target 7 to increase the proportion of new-born children exclusively breastfed at 6–8 weeks from 26.6% in 2006-7 to 33.3% in 2010-11. Funding provision for 200 DVDs which include two Health Scotland breastfeeding adverts. |
| 2008-2011 | Chief Executive Letter (CEL) 36 – funding provided, part of which is to support delivery of the HEAT 7 target on breastfeeding. National Institute for Health and Clinical Excellence (NICE) Review of public health guidance (PH11) - Improving the nutrition of pregnant and breastfeeding mothers and children in low-income households provides an evidence base for use of the funding: http://www.nice.org.uk/guidance/PH011 Recruitment of an infant nutrition coordinator to implement an infant nutrition strategy for Scotland. The coordinator’s strategic role is to assist and coordinate activities, which will include breastfeeding, in Scotland. |
| 2011-2012 | Improving Maternal and Infant Nutrition: A Framework for Action (the framework) is the first framework which looks at the nutrition of mothers before and during pregnancy. The framework has an action plan of activities for all key partner organisations and seven out of the 30 actions focus on breastfeeding. We provide funding to health boards annually in order for them to carry out the work of the framework. A breastfeeding social marketing campaign was run in January 2011 and was repeated in June/July 2012 (the latter to coincide with the National Breastfeeding Week). The campaign was targeted at mums in lower socio economic groups aged between 19 and 35 as research shows that this group is much less likely to attempt or maintain breastfeeding due to a lack of confidence in their own abilities and the perceived stigma in communities where bottle feeding is commonplace. The campaign comprised of a television advert, outdoor posters and an updated feedgood factor website which provides help and support to breastfeeding mothers (http://www.feedgoodfactor.org.uk/) |
| 2014 | Funding provided to UNICEF to deliver the Baby Friendly Initiative (BFI) accreditation in maternity hospitals and community settings in Scotland. The BFI is a worldwide programme of the World Health Organisation and UNICEF which works with the health-care system to ensure a high standard of care related to infant feeding and very early child development. Support is provided for health-care facilities that are seeking to implement best practice, and an assessment and accreditation process recognises those that have achieved the required standard. We also fund the role of Professional Officer for Scotland which allows UNICEF to provide dedicated support to NHS boards in achieving and maintaining BFI accreditation. |
- Asked by: Elaine Smith, MSP for Coatbridge and Chryston, Scottish Labour
-
Date lodged: Thursday, 02 October 2014
-
Current Status:
Answered by Michael Matheson on 28 October 2014
To ask the Scottish Government what information is provided to mothers in relation to the Breastfeeding etc. (Scotland) Act 2005.
Answer
There are universal resources, available to all pregnant women, which include reference to the Breastfeeding etc. (Scotland) Act 2005. These are:
The Ready Steady Baby! book provided at initial booking with maternity services. There is also a Ready Steady Baby website: http://www.readysteadybaby.org.uk/
The booklet Off to a good start: All you need to know about breastfeeding your baby is provided at 28 weeks' gestation:
http://www.healthscotland.com/documents/120.aspx
- Asked by: Elaine Smith, MSP for Coatbridge and Chryston, Scottish Labour
-
Date lodged: Thursday, 02 October 2014
-
Current Status:
Answered by Michael Matheson on 28 October 2014
To ask the Scottish Government what information is provided to companies in relation to the Breastfeeding etc. (Scotland) Act 2005.
Answer
The Scottish Government produced a leaflet on the Breastfeeding etc. (Scotland) Act 2005 which was issued to all employers in Scotland in 2006. It explains the implications of the Act for employers and employees. The leaflet is available online:
http://www.scotland.gov.uk/Resource/Doc/135079/0033433.pdf