Current status: Answered by Alasdair Allan on 19 December 2024
To ask the Scottish Government, further to the answer to question S6W-31510 by Alasdair Allan on 28 November 2024, whether it will provide a breakdown of the outturn on energy efficiency and decarbonisation for the three-year Budget period of 2021-24.
Between 2021 and 2024, expenditure under the Heat in Buildings Programme totalled £493m. The annual spend is as follows:
21-22 | 22-23 | 23-24 |
£68m | £175m | £250m |