To ask the Scottish Government on what date (a) it currently anticipates that CMAL will deliver the Glen Sannox to CalMac, (b) the operator currently anticipates that it will begin delivery to operational sea trials of the vessel and (c) it currently anticipates that the Glen Sannox will enter service on the Troon-Brodick route.


Answer

In his most recent letter to the NZET committee on 12 September, the interim Chief Executive of Ferguson Marine indicated that the handover date for MV Glen Sannox of 30 September 2024 was delayed by around two weeks. Following successful Builder’s LNG sea trials the vessel is on track for delivery by mid-October 2024.

Following delivery there will be a period of familiarisation needed by the operator, usually around 6-8 weeks, to conduct further owner’s sea and berthing trials and conduct final operational readiness preparations before she is ready to enter service.

CalMac anticipate the vessel entering service on the Troon-Brodick route around the end of November based on current planning assumptions.