Current status: Answered by Paul McLennan on 24 September 2024
To ask the Scottish Government how much it has allocated for remediating unsafe cladding on buildings in each year since 2017.
£97.1m in Barnett consequentials was received in 2021-22. The cumulative spend of the programme to date is £9.m, spend of £0.5m was incurred in quarter one 2024-25 to support programme delivery works. Details on spend to date are on the Scottish Government website Single Building Assessment programme: spending information - gov.scot (www.gov.scot)