Question reference: S6W-28487

  • Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
  • Date lodged: 4 July 2024
  • Current status: Answered by Jenny Gilruth on 31 July 2024

Question

To ask the Scottish Government whether it had (a) completed all the work required to produce and (b) finalised a draft response to the Independent Review of Qualifications and Assessment, prior to the commencement of the purdah period for the 2024 General Election.


Answer

The Scottish Government was at the final stage of completing the work required to publish a response to the Independent Review of Qualifications and Assessment when the need to consider whether or not it could be published during the pre-election period arose.