Question

To ask the Scottish Government how much money it was liable to pay to lead partners under the European structural and investment funds, as of 31 December 2023.


Answer

The Scottish Government was liable for paying all compliant claims submitted by Lead Partners. The figure at 31 December 2023 was £73.7m.