Question

To ask the Scottish Government how much of the £1.8 billion Heat in Buildings funding has been spent to date, and what the forecast trajectory is of spending to the end of the current parliamentary session.


Answer

From April 2021 to the end of September 2023, the Heat in Buildings Programme has spent £340m, with an additional estimated spend of £163m over the remainder of this financial year.

  • The programme forecasts are showing an increased demand that supports a continuing increase in capital support across the range of schemes offered by the HiBs programme. Final outturn will be based on actual demand for schemes and final budget allocations for 24-25 and beyond.
  • We are continuing to make long term commitments to funding – for example, we have recently re-procured the Warmer Homes Scotland successor scheme at a contract value of £700 million over the next 5 years.