Question reference: S6W-18121

  • Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
  • Date lodged: 19 May 2023
  • Current status: Answered by Michael Matheson on 6 June 2023

Question

To ask the Scottish Government whether it will provide an update on the current (a) proposals and (b) timescales for the provision of a replacement (i) hospital, (ii) dental clinic and (iii) GP unit on the Isle of Barra, and whether it will propose scheduling a ministerial statement in order to provide a detailed update to the Parliament on these matters.


Answer

The Scottish Government remain committed to delivery of quality health and care facilities on Barra. However, the Scottish Government's ability to fund capital projects has been affected by a reduction in the amount of capital grant from the UK Government over the next two years, and unprecedented levels of inflation as a result of Covid, Brexit, uncertainty in the supply chain and the war in Ukraine.

The Outline Business Case for the provision of new health facilities at the Barra Health and Social Care Hub has been submitted, however detailed design work of the proposals has been unable to start due to the budgetary pressures across the capital investment programme.

Scottish Government officials will engage with NHS Western Isles and the Scottish Futures Trust to consider the timing of the construction and will work closely with partners to identify alternative options.