  • Asked by: Jamie Greene, MSP for West Scotland, Scottish Conservative and Unionist Party
  • Date lodged: 3 February 2022
  • Current status: Answered by Jenny Gilruth on 1 March 2022

Question

To ask the Scottish Government whether it will provide an update on (a) when it anticipates that vessels 801 and 802 for the CalMac fleet will enter into public service and (b) the current revised total cost of the build, including a breakdown of (i) capital costs, (ii) resource costs and (iii) any loans or underwritten finance made in relation to the build at any point and to any party.


Answer

We continue to work with the yard to do everything we can to ensure that the new vessels enter service as quickly as possible, to deliver the further service improvements our island communities deserve .

After further analysis has been undertaken regarding the recently discovered legacy cabling issue, the new Ferguson Marine Chief Executive will outline the revised schedule for vessels 801 and 802, in his quarterly update to the Net Zero, Energy and Transport Committee at the end of March 2022.

The total estimated costs to complete the vessels remains the capital spend of £110m-114.3m, this is likely to change with the most recent cabling issue however we are unable to provide an update at this time, as we await the quarterly update. There is no resource funding at this time or loans to any parties regarding the build out of 801/802.