Current status: Answered by Kate Forbes on 21 October 2021
To ask the Scottish Government whether it will provide an update on the estimated final cost of the MV Glen Sannox ferry upon completion.
The Turnaround Director’s June 2021 update to the Net Zero, Energy and Transport Committee contains a summary of the costs to complete vessels 801 and 802 within appendix 11. The report is available on the Scottish Parliament website at Update on progress and impact of COVID19 on programme for vessels 801 and 802 | Scottish Parliament Website