Current status: Initiated by the Scottish Government. Answered by John Swinney on 18 December 2014
To ask the Scottish Government whether it will provide an update on the public information costs associated with Scotland’s Future: Your Guide to an Independent Scotland.
Information on costs of public information activity related to Scotland’s Future was released in answer to parliamentary questions S4W-21283 on 22 May 2014 and S4W-22236 on 20 August 2014. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at:
http://www.scottish.parliament.uk/parliamentarybusiness/28877.aspx
In addition to the expenditure set out in those answers, the following expenditure has been made in financial year 2014-15 in relation to public information activity associated with Scotland’s Future:
Description | Spend |
Digital Development | £31,149 |
Media | £74,918 |
Creative and Production | £50,274 |
Total | £156,341 |