Question

To ask the Scottish Executive what action is being taken to overcome the delay in wind farm projects due to radar issues and when the matter will be resolved with aviation stakeholders


Answer

The Scottish Government (SG) has been very proactive in overcoming delays to wind farm developments due to radar issues. The SG formed the South West Scotland Aviation Solution Group in March 2009 which has met seven times and brings together all the relevant stakeholders. Developments in this forum led to the publication of the SG''s Feasibility Report which described the potential for finding solutions to radar issues and is the foundation upon which much of the progress made to date has been built. SG is also member of the Aviation Management Board which brings stakeholders together at UK level, including to support the development of new technological solutions.

The work is ongoing and covers a multitude of developments requiring different solutions, including some at pre-planning stage, so it is not possible to apply any timescales for completion.

Further information on the issue and the feasibility report can be obtained on the SG website at:

http://www.scotland.gov.uk/Topics/Business-Industry/Energy/Infrastructure/Energy-Consents/Guidance.