Public Audit Committee
Meeting date: 24 March 2022
Willie Coffey
Thanks for that. I could not see that in the Audit Scotland report that we have in front of us. However, I saw a comment on the financial statements from 2020-21, which show your income at £18.8 million and your expenditure at £22.7 million. That is a deficit of £3.9 million. How can that comment be squared with those facts in the financial statements? We think that there is a maintenance backlog of £70 million or so. How can the comments about there being no concerns about financial sustainability be squared with the figures that I have just read out?
Public Audit Committee
Meeting date: 24 March 2022
Willie Coffey
Would the committee be able to see at some point whether there has been any allocation towards that maintenance backlog, so that we can see whether progress is being made on it? It is great to be able to talk in terms like this at the meeting, but the committee would appreciate information on real changes on the ground or at the canals, so that we can see that moving forward.
Lastly, Catherine Topley talked about how the status change gives Scottish Canals other opportunities to generate income. Could the committee also see some indication of how those are being embraced by Scottish Canals and how that might impact on your future financial statements?
Public Audit Committee
Meeting date: 24 March 2022
Willie Coffey
I would like to start with a question for Catherine Topley on financial sustainability. Did you say in your opening remarks that the Auditor General said that he had no core financial sustainability issues with Scottish Canals? Did I pick up correctly what you said? Did you say that at the outset of the meeting?
Public Audit Committee
Meeting date: 24 March 2022
Willie Coffey
Good morning to the panel. Catherine Topley, I have a wee question on the status change that occurred. Were you taken by surprise by the decision of the ONS to change Scottish Canals into an NDPB? The only explanation that we have in front of us is that, because it carried out administrative, commercial, executive or regulatory functions, it had more of the characteristics of an NDPB. However, it had been doing that for years, I presume. Why did the change suddenly occur? Were you taken by surprise? Why were you not granted the extension that you requested in order to prepare the organisation for that NDPB status?
Public Audit Committee
Meeting date: 24 March 2022
Willie Coffey
Okay. Thank you.
Public Audit Committee
Meeting date: 24 March 2022
Willie Coffey
Many thanks.
Public Audit Committee
Meeting date: 24 March 2022
Willie Coffey
Has the £70 million been factored into your financial planning? Has it been agreed with anyone? Where is the money to address the maintenance backlog coming from?
Public Audit Committee
Meeting date: 24 March 2022
Willie Coffey
You are bound to need some kind of allocation to assist you with the maintenance backlog. We cannot wait year after year for that. There surely has to be some kind of annual recognition of that and an allocation of funding to support the good work that you described. However, it is not clear to me that the money that you said you need for the work that you intend to do will be forthcoming next year and the year after.
Public Audit Committee
Meeting date: 24 March 2022
Willie Coffey
What was its explanation to you for its not granting the extension?
Local Government, Housing and Planning Committee
Meeting date: 22 March 2022
Willie Coffey
Good morning. I want to give you a chance to tell us about some of the possible risks ahead for councils and landlords. George Walker mentioned a few of those in his opening remarks, including increasing costs, the affordability of rents and even cyber attacks. Could you give us a flavour of the risks that you envisage and how you are engaging with landlords to minimise their impact on tenants?