Official Report 309KB pdf
Good afternoon, everyone. We have 100 per cent attendance by members of the committee, so there are no apologies to record. I ask everyone in the room to check that their phones and so on are switched off.
I would be happy to do so, convener. There has been no change to our position on the matter. In the light of the minister's letter to the convener of 30 October, we were of the view that the issue was being addressed outwith the powers in the bill. We have kept in contact with Councillor Borrowman, in particular, and have given a commitment that we will keep Platform Blackridge informed of any further involvement that we have.
Thank you very much, Mr McAulay. Over to you, Mr Greig.
I am happy to rest on the evidence that was submitted by the promoter, and I have no questions for the witnesses.
Thank you very much. Does anyone from the objector group have questions?
We have four questions that I hope are brief and simple.
I must be honest and say that I do not have the numbers immediately to hand. They are in the promoter's memorandum, which one of my colleagues has to hand.
Do you anticipate that, with the use of the revised population projection figures for Blackridge that have been provided by West Lothian Council, the benefit cost ratio for the line including a Blackridge station is likely to rise?
When we ran the model again using the revised housing forecasts, the figure that came out was 1.92, but that was based on there being no Blackridge station. I would imagine that the gap between Blackridge being in and not being in will be similar to the one that I just described.
Is there any technical reason why a Blackridge station would be unduly complex or difficult to build?
In terms of technical construction issues, the answer is no. However, there are issues to do with timetabling, particularly at the Waverley end, and patronage numbers.
Is it possible to recast the timetable for the whole line to accommodate a service for Blackridge and retain a comprehensive service for the other stations along the line?
It is possible. As we have suggested elsewhere, the timetable will have to be recast to accommodate the new Airdrie to Bathgate railway. Anything is possible, but—I am in danger of going beyond your question—our modelling suggests that as soon as we started to add additional stations the number of people using the service would drop, because of the extension to journey times.
Thank you.
Do any other objectors want to ask questions?
During the preliminary stage, there was a lot of discussion about computer modelling and patronage figures, and I think that the promoter was going to rerun the models. Has that been done, and was the figure that we had for the potential annual patronage of a Blackridge station—80,300 boardings—substantially correct?
We reran the model based on the new housing forecasts that were provided by North Lanarkshire Council and West Lothian Council. However, that was based on the option that is in the bill—in other words, no stations at Plains or Blackridge.
But you ran the model based on a station at Blackridge as well. We had a figure of 80,300 boardings, although there was some debate over that. Would that figure still broadly stand if a station was built at Blackridge? There was some discussion about different computer models.
The only modelling that includes a station at Blackridge was carried out before the revised housing forecast—that is what I was trying to say in answer to Councillor Borrowman's question.
The figures of 1.71 and 1.82 are to do with making the business case.
That is correct.
But the number of people who would use Blackridge station is reached by using a different algorithm. As I said, during the preliminary stage, you gave the figure of 80,000 boardings annually. Is that figure still broadly what you would predict for usage if a station were built at Blackridge?
I would need to come back to you with the numbers; I am afraid that I do not have those numbers with me.
You gave those figures and we talked about computer modelling when you provided them. The usage figure is relevant to us because it is greater than the figures for patronage at Shotts and West Calder. Your modelling suggests that a station at Blackridge would be economically viable. Regardless of whether the ratio is 1.71 or 1.81, if the station paid for itself through public usage, that would show the need for the platform and the benefit that we would receive if it were built, for the modest sum of £2 million. That is our whole case.
The results, and our concerns, related not so much to whether the number of boardings at Blackridge station would be more than those at other stations on the network as to the project as a whole. Our modelling suggested that adding a station at Blackridge would reduce the number of boardings throughout the line, which would weaken the business case, as the revenue from passengers joining the service and travelling end to end would drop.
Yes, but if the ratio dropped only from 1.81 to 1.71 and the station was economically viable, the benefits that would accrue to our area would be worth the small drop.
Will you stick to asking questions rather than making statements?
I am sorry; I beg your pardon, convener.
My recollection is that the journey time is 74 minutes.
Network Rail proposes to make the Shotts line an express route, on which the journey time would be 67 minutes.
I do not remember off the top of my head the figure for the express service on the Shotts line.
Okay. I understand that to be the figure, but I read it in the press, so it might not be accurate. If that is the figure, will people tend to use the Shotts line as an express route to Edinburgh or Glasgow? I am trying to say that flexible timetabling options would be available with a station at Blackridge, which would be only one station among many. Network Rail would also have options to vary the timetable on the Shotts line. Some material balancing of patronage between Edinburgh and Glasgow must be available. We do not see why a station at Blackridge, which would be economically viable, should become a show-stopper for investment in our area's transport infrastructure, the benefit of which we will not really feel if we do not have a station.
In all the evidence that we have given, we have said strongly that the better the benefit cost ratio that we achieve on the Airdrie to Bathgate line, the faster the end-to-end journey is. If the journey time became longer, the service would become less attractive to people, so the number of people who were likely to use it would drop. That is the argument that we have made. Our job as promoter of the bill is to present what we believe to be the best case for delivering the railway and we have based our case on that argument. All the modelling has shown that the best benefit cost ratio comes with fewer stops and a better end-to-end journey time, because that will attract more people to the railway.
If we follow the logic of what you said, we could get into the reductio ad absurdum position that we should cut out all the intermediary stations and just go straight from Glasgow to Waverley, which is clearly not what you propose. Therefore, the question arises of which stations are in and which are not. Why should Blackridge be the one that is out?
If I recall correctly, the initial technical feasibility study for the project involved no new stations. From the first consultation exercise that we carried out, it was obvious that there was a strong desire for more stations to be included, which is why we carried out an analysis to discover whether we could strike a balance and include some stations to try to increase the number of stops, although without increasing the journey time to the point at which we would start to lose end-to-end journeys. That is why we came up with the stations at Caldercruix and Armadale. The analysis and the steps that we took to get to that point are listed in the promoter's memorandum. We used the places where we believed the biggest patronages would be generated.
I presume that there is a political judgment to be made. In the ins and outs of the analysis that you carried out, I presume that you did not suggest taking out any existing stations. Is that correct?
That is correct. We worked on the premise that there would be no deterioration in service to existing stations. I should point out that we cannot unilaterally consider taking out existing stations, but instead must take on board the views of all industry players. The train operating company, Transport Scotland and the regulator all have a say in such matters.
But we might well end up in the curious situation in which the advantage of or public benefit from including a station at Blackridge could have been much higher than the benefit from including some of the other stations, even though we are not even discussing whether they will be included.
You would have to take up that matter with the people who use those stations. I am sure that you would find strongly held views.
I am sure that I would.
The issue is the number of people who use some of those stations compared with the number of people who would use a station at Blackridge. Some of the stations are pretty infrequently used, as far as I am aware.
Some of them have relatively low take-up or boarding numbers but, nevertheless, they are important to those communities.
Yes, but I am sure that a station at Blackridge would be important to the community in Blackridge.
I do not doubt that for one second. We have tried to strike a balance or reach a compromise. I could go back over the arguments that we have made about what rail is good at and not good at. We have said already that rail is very good at moving large numbers of people into city centres, but it is not good at stopping to pick up small numbers of people. I accept readily that many of the stations have small boarding numbers.
Have you considered how many potential passengers you might lose if you do not provide a station at Blackridge, as a result of people feeling that it is too difficult to access stations further along the line?
All the modelling that we have carried out suggests that we will not lose people by not having a station at Blackridge. In fact, the modelling suggests that we will lose people if we have a station at Blackridge, as the overall number of people using the service daily would drop considerably—if I remember correctly, the figure is 513.
Mr Greig, do you have any further questions?
I would like to raise just one matter.
Transport Scotland has been in what I would describe as early discussion with us about how we might provide it with information that we hold on a Blackridge station. There has been discussion on the issue.
I do not know whether you have a copy of the minister's letter to hand.
I do not, but I recall the letter.
In it, is the Minister for Transport acknowledging the case for constructing a station at Blackridge, but then saying that it would require
That is my recollection.
Does the letter also say, in relation to Blackridge, that
That is correct.
Does it also say that all that will be
That is correct.
Is that for the purpose of ensuring that it would be possible for
That is the proposal; you are correct.
Should the objectors take some comfort from that?
I would say so, yes.
Thank you.
Thank you, Mr Greig.
I will, convener. The—
I am sorry, Mr Borrowman—it has to be Mr Webster or Mr Steele. You can come in afterwards, to ask questions.
The thrust behind our maintaining our objection comes from the apparently wide consensus that a station at Blackridge would bring benefits to our area. It would be an economic incubator for housing developments that are already taking place or are already planned. Because of the modest sums of money involved, we feel that it would be a dereliction of our duties if we did not argue for a station at Blackridge.
Thank you. Stuart Borrowman may want to ask questions.
Thank you for keeping me right, convener.
Broadly speaking, the figures sound very similar to me. We seem to be splitting hairs.
Can you say a little bit about what has happened in the community since the committee concluded its preliminary stage work? There has been a lot of correspondence from members of the Scottish Parliament, there has been a ministerial statement and so on. How has that been received?
There is still confusion in the communities surrounding the proposed station about whether it is going to be built. Many people think that it is going to be built—various statements have been made that seem to indicate that it will be. However, the reality is that the funding is not in place. There is confusion about whether the station is going to be built, so the reality of the situation is that there are mixed messages in the area.
I have further questions for Mr Steele. We were asked to consider withdrawing our objection to the bill. Can you say how we went about gauging opinion in the village on that issue and what the response was?
After Mr Webster and I visited the Parliament, when the bill was proposed, we went back to the community and prepared a leaflet asking people whether the objection to the bill should be withdrawn or should stay in place. We held a public meeting on 9 January, to which our two local MSPs came along. On the basis of the replies that we received from those who could attend the meeting, the unanimous decision was reached that the objection should stay in place.
There is a feeling among those of us who have been active on the front line of the process that the committee has served Blackridge well in ensuring that the case for a station at Blackridge is given a proper hearing. However, we are aware that there are limits to what the committee can do. Platform Blackridge does not wish to imperil the bill. In the circumstances, what would satisfy people in Blackridge that they were not letting slip this major opportunity for the village?
The people of Blackridge would like a commitment to fund the station. We have heard about works through the Transport and Works (Scotland) Act 2007. Like you, we do not wish the Airdrie to Bathgate line to be delayed, but we will have more than 120 trains going through our village each day without there being any benefit to the village.
Thank you, convener.
Mr Greig, do you want to question the witnesses?
I have a question for Mr Webster. You have said that it is important that the station should be built now and that building it should not be held up until the line is built. However, did the minister not say in his letter that the plan would be to ensure that a station at Blackridge is constructed when the railway is constructed?
That is correct. That timetable has been given, but it should be remembered that the year that has been set for opening the line is 2010. If there are any planning delays with respect to Blackridge, the timetable could be pushed much further out. If the majority of people think that a station at Blackridge would be a good thing, that it would be economically viable and that it would bring economic development opportunities to an area that needs such opportunities, why is funding not available now so that construction of the station can go ahead and it will be guaranteed that the timetable will be met? That is our problem.
With good faith on the part of all the parties involved, should it not be possible to bring forward the station in line with the railway as per the minister's letter?
We would love that to be the case.
Thank you. I have no further questions.
Thank you, Mr Greig. I invite members of the committee to ask questions.
I acknowledge what Councillor Borrowman has said about the interest that the committee has taken in the matter, but I am sure that the witnesses are aware of what the committee has said about potential developer contributions given the number of houses that are being built around Blackridge. We have received further evidence from the local authority on housing prospects in the area. As far as I could see from the final letter that we received from West Lothian Council, there will be no developer contributions, even from forecast housing, for the capital costs of the stations. I think that Mr Webster said that we are talking about a relatively small amount of money in the overall scheme. Are you slightly disappointed, as I am, that three months after the publication of our report, the local authority still takes the view that there will be no developer contributions towards the capital costs of the stations, which could make their construction, even under a new procedure in a new parliamentary session, considerably swifter, as the capital costs would be catered for? I have seen only potential contributions to capital costs for access roads to the stations.
Yes, I am slightly disappointed.
We understand that the developer has offered to pay for access roads, which I hope will include access to the car park, which will make it a park-and-ride facility. I do not live in Blackridge, but I understand that there is pressure in and around the area on the local plan development boundaries as a result of what has been proposed. It is unfortunate that the committee is not in receipt of a letter with a definitive figure for the contribution from the developer, who is willing and who wants to see the line built, obviously for his own benefit. However, we do not have a figure to give the committee.
Would that be a letter to West Lothian Council?
That is what I understand it to be. I am sorry but, from what you said, I thought that you would be looking for a letter from the developer with a figure that he would be willing to contribute towards the costs.
West Lothian Council will no doubt have comments on this point, but there is a headline figure of £2.4 million for planning gain, which will assist in the reopening of the railway. The point that the committee has been making quite consistently—indeed it is in our report—is about the developer contributions that could be secured for the capital costs of the construction of the stations, not just the associated roads and access to the stations. However, no work has been done on that. In fact, West Lothian Council considered our report to be "harsh". If no work has been done, and you are hoping for a guarantee that the money will be found for the development of the railway, what is your view of the lack of activity to identify other sources of revenue that could fund the stations?
Maybe we should have been more proactive in that area and got a much better and firmer indication of what that contribution to the project would be. However, that contribution should not necessarily be a prerequisite for a station to be built. I do not know whether there are other examples along the line where such a contribution has been a prerequisite for a station to be built. Generally, a decision will be made on the benefits and economic viability of the case. Personally, I do not think that we should always rely on developers to fund public investments.
Thanks, Jeremy. I think that we might have drifted a little bit there.
It is simple economics. As Mr Webster said, most people are coming from the large cities. Housing costs are considerably cheaper in Blackridge than they are in the larger towns and cities. The committee has visited Blackridge and has seen that we have only one shop. With the influx of new houses, we hope that more commercial premises will be opened.
Thank you. Councillor Borrowman, do you have any questions for the panel?
I have a final question on developer contributions. Given that the Scottish Executive has committed to funding all the other stations on the line, might people in Blackridge not feel that it would be fair if developer contributions went towards school expansion and an increase in social and leisure facilities in the village rather than towards paying for Blackridge railway station?
Exactly. The bill is being promoted by the Scottish Executive and we do not expect to have to find money for it from developers because that money might be earmarked or ring fenced for other areas—even though I gripe that it might not necessarily be spent in Blackridge.
Thank you.
Thank you very much indeed. Mr Greig, you have a maximum of five minutes to say anything that you would like to say about the situation.
I hope that I will not take five minutes.
I ask Councillor Borrowman to sum up for the objectors.
We understand the procedural limitations. However, the political reality is that the community that we represent is isolated in terms of transport and has limited public transport services. It has more challenging social conditions even than other communities in West Lothian have. There is a strong business case for a station at Blackridge.
That ends the session on Blackridge.
Good afternoon, and thank you for the further information on housing. The panel will be aware of the concerns expressed by the committee in its preliminary stage report on the impact of the railway on the volume of housing development, both before and after the railway has been built. How likely is it that the railway will be a catalyst for even more housing development in North Lanarkshire and West Lothian?
From the West Lothian perspective, we are in many respects pre-empting the benefit of the railway station. The development strategy that is being promoted through the West Lothian local plan, which has just finished the public inquiry stage, has been predicated on delivery of the railway line, particularly in the western part of West Lothian. Much of the housing land supply in the western part of West Lothian has been specifically allocated to benefit from the railway line. We are giving particular consideration to the core development area at Armadale, but we are also considering areas slightly further afield, such as in and around Whitburn, where a significant amount of land is allocated for housing development. That land supply should take us to about 2020. It is clear, however, that with the delivery of the Planning etc (Scotland) Bill, we will shortly have to start considering the city region plan in West Lothian. Through that process, we would anticipate building on the land supply, particularly in the western part of West Lothian.
The housing situation in North Lanarkshire is not substantially different from that of which I advised the committee when it met in Airdrie in September. The local plan that we have been working on was presented to the planning and environment committee on 31 January, and included the nascent developer contribution policy, which is our interpretation of planning contributions. It also included some limited housing release, primarily in line with the council's stated agenda for regeneration—primarily urban regeneration. However, on the day, the councillors decided to defer making a decision until some future date. At the moment, we are still in a state of flux in which we do not have an approved local plan to act as the main catalyst for seeking developer contributions or any kind of further information from likely developers.
The North Lanarkshire witnesses will be aware of our conclusion in paragraph 132 of our preliminary stage report, in which we stressed that in order to have robust forecasts for patronage it is important to have robust forecasts for housing. We are pretty close to having those forecasts for West Lothian. However, in your letter to us on 25 January, you said:
The timetabling intention is that the study will inform the process in the next 12 to 18 months between the period of the initial consultation draft, which we have not yet managed to get out the door, and the finalised draft, which is the stage at which people can make a formal objection that could result in a hearing at a public inquiry. The finalised draft will contain much more certainty about the council's position.
You are aware of the significance of this committee and of the fact that we asked for specific information before we can recommend to Parliament whether the project has robust patronage forecasts.
Yes.
Housing is the key element. You have not even got the first stage of your work through the door.
All I can say is that the council's position is as I have described it. Until we have an approved report, I am afraid that I cannot be any more specific.
The letter from West Lothian Council was helpful with regard to developer contributions. I appreciate that the figures can only be rough at this stage, but they are indicative. The first element comes to £2.4 million. How closely will the proposed work be directly associated with the stations?
We tried to set out the position when we met the committee before, and we have also done so on pages 3 and 4 of the letter that we sent you. We hope to get about £2.4 million of planning gain in Armadale. If we were to go ahead with Blackridge station, the planning gain would be in a range up to £1.4 million. We have taken those initiatives into account when we have been able to do so. As we have explained to the committee before, councils are bound by a whole set of national legislation on the structure plan and local plan. We have been in consultation for about five years—that is the process.
I am not sure whether there is any point in asking North Lanarkshire Council to comment.
I simply emphasise the importance of the matter and express our support for our colleagues in West Lothian. As you probably gather, they are a considerable way further down the line—no pun intended—with the local plan.
I have a brief question for Mr McCorriston. You mentioned the tremendous amount of building that is planned around Armadale and its link with the station. What consideration is being given to that building and its effect on road traffic, particularly with respect to the access to Armadale station and the west-east approach?
If I may take a liberty with the committee, I will first answer the second part of Mr Purvis's question, which was about developer contributions and forecast housing demand. Mr Dickson described West Lothian Council's position on the allocations in the development plan and made the point that, when we put the plan together, we pursued that in terms of the position as we understood it at that time. However, that does not mean that we will never seek to secure developer contributions.
Perhaps I am missing something, but are you referring to the station that might be built at Blackridge? If that station does not go ahead, will any developer contribution fall?
You are right that I was referring to the Blackridge situation. The contribution to the development of the railway station—the provision of the car park and the access road—is part of a much larger package that we are negotiating with the developer. We would continue to pursue that because, clearly, the council's aspiration is for Blackridge to have a railway station at some stage—sooner rather than later, preferably. We would seek to ensure that the land for the access road and the station car park, for example, was reserved as part of the development on that site.
Thank you very much.
If I may, I will pass over the question about the Armadale situation to my colleague.
The question was on the traffic volumes that will be associated with the station.
And the effect of the expansion and development.
I am not too concerned about the scale of development in the Armadale area and its effect on the station, because we did traffic modelling work as part of the evidence giving on the finalised West Lothian local plan. As regards the selection of sites, we have a transportation framework that we are working to, which we are developing with each of the developers, so we will have a master plan for the layout.
As there are no more questions, I thank the witnesses for coming along.
What practical steps, other than dialogue, can and will you take after the bill has been passed to improve bus provision to the stations for local communities?
We recognise that it will be some time before the trains are operational; I understand that the committee has received evidence to that effect. However, we are committed at the appropriate time to working with bus operators, the promoter and Transport Scotland to see what interest we can generate in bus feeder services to stations.
West Lothian Council will do exactly the same. We will be in close liaison with all our bus operators to see what we can offer.
In the former Strathclyde area we work through SPT, which has primary responsibility for many bus issues. We will examine those issues in conjunction with SPT.
I would like you to convince me that you are enthusiastic about ensuring that the new services will exist. Concern has been expressed to us that they will not be set up. If that does not happen, many people will not have access to trains. More forward thinking and planning could go into ensuring that new bus services are created.
I trumpet the credentials of SPT in promoting public transport. SPT is the new Strathclyde partnership for transport, but it also embraces all the public transport interests in the Strathclyde area. We have a long history of promoting public transport and of working not only in the subsidised bus market but with bus operators to apply for bus route development grants—in other words, assisting operators to develop routes so that they can become commercial.
Our concern is based on our experience of the bus industry. We want to ensure that people are able to access stations; that is why the committee is keen to hear what plans exist. Clearly, local authorities have a role. You say that there are plans, but I would like to be given a timetable for them and to hear about the discussions that are taking place.
West Lothian Council has worked strenuously with the bus companies. We have formed quality partnership arrangements, including a particularly successful partnership with First Bus between Bathgate, Livingston and Edinburgh. We have also bid for route development grant funding. We have a service from Blackridge to Livingston that is paid for by route development grant, and in May we will start another service that will link Edinburgh airport with West Lothian. We are keen to follow the approach that is outlined in the action plan for buses, which was produced late last year. Whenever we talk to bus operators, there are funding implications in respect of services at certain times of the day, but I assure members that our plans are robust. We want to work with the bus operators to serve all the stations.
From the consultations and other local communications that have taken place, we are aware that there is a definite need for bus services. We will push to ensure that there are services in the Airdrie area and further west, in the Coatbridge area. It was mentioned that in the east Airdrie area there are a lot of small operators—at this time, there is no big operator to which we can talk effectively about quality contracts, quality partnerships and bus route development grants, which are the best mechanism but which may be subject to change. Because of the legislation that governs them, it is too early for us to enter into definitive agreements. At the moment, it is more a matter of working towards what we might be able to achieve, with a view to reaching full agreement 12 or 18 months before the station opens.
But given how much money is being spent on the railway line, we are seeking a strong commitment from you with regard to bus services, instead of comments about what you are trying to do or what you might be able to achieve.
The issue is difficult, but the point is that we all operate in a deregulated market. Indeed, under current legislation, we are duty bound to allow the free market to operate. Of course, the free market will operate if there is a good market for serving the stations. I also point out that we can step in and offer subsidies only if a commercial service is not identified. I realise that the issue affects all our communities, but, as I have said, that is the legislative arrangement under which we have to operate.
This is a £350 million transport project, after all, and we want it to have maximum benefit.
I cannot give such a commitment for the reasons that I have already given, but the intent is certainly there. For example, a number of subsidies already support out-of-hours and off-peak services. My colleague Mike Heyes might be able to elaborate on that.
Every year, West Lothian Council makes available £1.439 million in bus subsidies and very carefully considers where that money is spent. For example, as far as the proposed railway line is concerned, we fund the evening service linking Bathgate, Armadale and Whitburn. Because of the contract, I can tell the committee that the council is committed to that service for five years. The balance of the rest of the services is either commercially operated or—as far as the early morning services are concerned—paid for by the council. Those services are subject to variation. Twelve or 18 months before the line opens, we will look closely at the current operation and find out what we can do to fund services that might serve the railway line.
I understand that that is as positive as you can get on this matter, and we will certainly take a positive slant on it. I thank the witnesses for giving evidence.
Has the engagement process that we have facilitated with the promoter and others proved beneficial? Has the promoter's latest position on cycle path alignment and access changed in a good way from its original proposal when the bill was introduced in Parliament?
The process has been beneficial. A series of meetings has been held with the promoter and we have gone some way towards resolving some of the issues that we raised when we met the committee previously. Two issues are still outstanding, but if we continue to work as we have done, we can resolve them.
For the record, what are those two issues?
Sustrans remains concerned about cycle access and pedestrian access to Armadale station and to Bathgate station from the national cycle network realignment and from the communities and the communities-to-be—if I can use that expression—in Armadale.
The committee's intervention has certainly been partially beneficial. We have managed to resolve some of the east-to-west issues of the cycle path's alignment, but we have not made much progress on what I call the north-to-south issue of access to stations—not just to Armadale and Bathgate stations, but more generally from the surrounding communities to all the stations along the line. We believe that more than half West Lothian's population lives within comfortable cycling distance of the stations that exist and will exist. More should be done to encourage people to cycle rather than drive to those stations.
Given the mechanism that has been established for negotiating, how optimistic are you that a satisfactory conclusion will be reached within the limits of funding and the terms of the bill?
The crucial problem is that we remain in the position that we were in when we saw the committee in Airdrie, whereby responsibility for creating the infrastructure to allow people to walk and cycle to stations seems to fall into a gap between the promoter and local authorities. That remains a concern of mine. I am a little worried by the length of time that the process is taking—we have talked about the issues for about 18 months and movement has been slow. With good will on everyone's part, the issues may be resolved, but I feel that time is ticking on and that movement could be a little speedier.
I was interested in what was said about bus provision to stations, because we are in the same situation. We want to get people to stations in the most sustainable way. Some organisations are prepared to provide buses. Cycling offers a door-to-door transport solution—people do not have to sit around waiting for a bus; they just get on their bike and go. We must have some infrastructure in place on the roads to encourage people to cycle. That must be provided for in the bill or given reliable support by organisations such as SPT or the south-east of Scotland transport partnership—in other words, the regional transport partnerships. We have seen no evidence that any provision will be made for cycling. We regard cycling as a unique form of transport that is different from walking, because it is three or four times faster. Cycling does not have the organisational support that bus provision has.
As we proceed, others may answer the points that you have raised, Mr Lauder and Mr Hawkins. Thank you very much for coming. Next, we will listen to what the councils have to say—it is changeover time again.
Do the local authorities have any comments on what we have just heard from the previous panel on access to the stations, the potential gap in ability to deliver between the promoter and local authorities, and the mechanisms that are in place to resolve the two outstanding major issues?
To pick up on access, I can confirm that North Lanarkshire Council produced a cycling and walking strategy document a couple of years ago, and we have spent a considerable amount of money on cycling and walking projects. A considerable portion of the cycling, walking and safer streets ring-fenced budget from the Executive goes towards cycling schemes, and we have been quite successful in obtaining money from SPT to provide walking and cycling access to stations. That work is on-going.
There is a similar situation in West Lothian. The difficulty that everyone has is in judging the bounds of the bill. It started as a rail scheme, and the cycle path was a relocation. In previous evidence, I said that the promoter has done a fairly good job in relocating the path—that work is not without difficulty. Mr McDove's point is well made, in that there is still a job to be done outwith the bill; what is important is how quickly the job can be done.
Thank you very much. That was a brief appearance. We will move on to the next subject.
SEPA has said that a thorough flood risk assessment is required. Do you have that? If not, what is missing?
SEPA has received and considered further information, subsequent to our receiving the original flood risk assessment, but we still feel that further information is required. Many of the issues can be dealt with through conditions in the bill. For example, the flooding issues that relate to the design level of the formation of the railway can be dealt with through conditions or similar measures. SEPA's main concern relates to the upsizing of culverts underneath the railway. If a culvert is upsized, more water will pass downstream, which could increase the flood risk downstream. SEPA's view is that that matter has not been dealt with adequately.
How long will it take you and the promoter to agree on something on which you will be satisfied?
We will have further meetings with the promoter. SEPA does not yet have certain information that we require from the promoter. Our concern is that if culverts are upsized, mitigation measures may be needed, but we do not know what the scale of those mitigation measures may be.
Can you give the committee a feel for how long the process might take? If you started talking to the promoter about the issue tomorrow, how long would the process of interaction be likely to take before you—and, I presume, the promoter—could be satisfied?
You will have to ask the promoter that, as it has to do the work. Obviously, we will work with the promoter to come to a solution. I hope that that will happen within a couple of months.
Is the work complex, expensive or time consuming? Give us a feel for it.
It is complex, but SEPA expects that the promoter could do it in a reasonably short period. Again, the question is for the promoter, because we are in its hands.
I am sure that we will ask the promoter about that. We aim to report on the bill in early March. Is it safe for us to pass the bill?
Until the promoter provides us with the additional information, we will have serious concerns about the flood risk. As I said, the promoter must identify the risks that are associated with upgrading the culverts.
In the great scheme of things, are the concerns serious enough to say that if you do not have the questions answered by early March, it will not be safe for us to proceed with the bill?
We are following the Scottish Executive's guidance in Scottish planning policy 7, which is on planning and flooding, to ensure that the development does not exacerbate flood risk elsewhere.
As with all things, guidance can be followed in different ways and to a greater or lesser degree. The issue that I want to get at is whether you are trying to get a gold-plated provision from the promoter.
We are not seeking a gold-plated provision. In essence, all we seek to do is ensure that a flood risk to others is not exacerbated or created as a result of the upsizing of the culverts. The promoter could assess each culvert and say that there is no increase in flood risk. If the information is appropriate, SEPA will accept it, but we need that information to determine our full response.
This point might be a bit unfair. On page 3 of your letter of 19 January you talk about Hillend reservoir and a potential
I did not provide the response on that aspect of the flood risk assessment, so it is difficult for me to comment. Clearly a stability issue arises, and the bill should deal with that, but at this stage I cannot comment on that aspect of SEPA's response.
We are talking about part of your submission. If you cannot answer Mr Morgan's question, it brings the whole railway line into question.
Did you say page 3 of our letter of 19 January?
Yes. This might be a red herring, but that letter—from Dr Chris Spray—raised an awful lot of issues, whereas today you have talked only about culverts. I want to get a feel for how serious your objections are. The reservoir collapsing seems to have nothing to do with building the railway, but I am concerned that you seem to be suggesting that we should take that sort of thing into consideration.
We drafted the letter of 19 January without having some of the details. We had received only the draft version of the flood risk assessment, and admitted the figures. On 23 January, we received the figures from the promoter, and we provided the committee with our revised position last Friday. There was a lack of information in the original flood risk assessment, but the issues we raised have been covered in the revision.
So the only substantive issue that remains is the culverts. Is that correct?
Yes.
There is also a concern about the Barbauchlaw burn crossing, just upstream of Blackridge. The promoter's consultant acknowledged that more detailed flood modelling would be required for that, and we agree.
Will that be a substantial piece of work?
No, I would not say so—it is an assessment of risk at a single site. We have to be consistent in our approach and treat this major infrastructure development like any major housing development near a watercourse. We require a level of detail on the risks.
We will take that up with the promoter later this afternoon.
Thanks very much. That was disappointing, to some degree.
We are content that the third test can be met provided that the promoter provides us with further information or provides the information in the code of construction practice. We would like further information on the location of European protected species, the precise mitigation that will be required and how that mitigation will be enforced.
Is not SNH aware of where those species are along the line? Do you not have an involvement there, somewhere?
We are aware of that. The promoter has undertaken surveys, as part of the environmental impact assessment, that demonstrate the precise location of those species. We would like that information to be taken forward as part of the design and build. The design has to allow for those species, where they are present.
We believe that the test can be met. We have sufficient information on which to base that conclusion. The issue with European protected species is that they are mobile, so the survey that was undertaken for the environmental impact assessment will need to be updated prior to the application for the licence that the Scottish Executive will provide.
I am not sure whether otters are involved in the Edinburgh Airport Rail Link Bill, but I have received a note on the issue. Would you be happy with the conditions that are provided in that bill?
Yes.
Yes.
Thanks.
We are aware of the committee's intention to amend the bill, but we have not seen any details of the amendments. If what is proposed is similar to what is in the other private bills that have gone ahead—the Waverley Railway (Scotland) Bill and especially the Edinburgh Airport Rail Link Bill, which has also had to deal with otters—we would be happy for the code of construction practice to be integral to the bill, so that the commitments of mitigation that are incorporated into the code of construction practice will be stated in the bill. However, without seeing the amendments we cannot say for definite.
I think that that is clear enough for committee members. We will move on to the code of construction practice and vibration aspects.
I want to ask some wider questions about the COCP. You will have seen previous drafts of it, including that which was received by the committee on 6 February. Is there anything in, or not in, the report that causes you concern?
We have some comments to make on it. One of the main issues is what we have just discussed—European protected species. We think that the code of construction practice should be tightened to ensure that there is mention of the requirement for the code of construction practice to take account of any disturbance licence that is granted by the Scottish Executive. If that is not done, it will not be clear what level of mitigation the promoter is adhering to.
So you want a more formal commitment to dialogue?
There is an intention to have a meeting with the mandatory consultees on 12 March. We welcome that sort of on-going dialogue. However, prior to the design and build aspect, we would want the landscape habitat management plan and the environmental management plan to be approved by the mandatory consultees.
So liaison is not enough; you need more?
Yes.
We note the points that SEPA made in its letter of 29 January to the clerk about waste ground and ground water. Would incorporating those into the next draft cause any difficulty for the promoter?
I do not imagine so. We are being asked to review the waste management plan to ensure that waste is being handled and disposed of appropriately. There might be situations in which the waste management plan could comply with a section of the code of construction practice and, therefore, be acceptable to the promoter. However, there might be separate issues that SEPA is privy to but the promoter is not aware of, which might cause problems. We want to review those and have an opportunity to comment.
The committee assumes that that is standard in any construction project.
Yes, it is standard.
We note the points that SEPA made in its letter of 26 January to the clerk under the headings of "Implementation", "Badgers", "Biodiversity, Landscape and Visual Impacts" and "Engineering Drawings and Hours of Work". Would incorporating those into the next draft cause any difficulty for the promoter?
We do not think that that should cause any difficulty for the promoter.
That seems sensible. Would it be standard practice to ask for that in this context?
It is the approach that has been taken in all other private bills.
It is also the approach that is increasingly being taken in relation to a lot of large infrastructure projects, not only those that relate to the private bill process.
It allows continuing monitoring?
Yes.
Are there any particular areas of construction practice or vibration policy that you feel you need to be more involved in over the next few weeks, or are you fairly satisfied with the level of communication and contact between you and the promoter on them?
We are more than happy, so far. The promoter has addressed all our comments and incorporated them into the bill. At this stage, we are happy to progress with the proposed liaison meeting in March and be part of the monitoring group for the code of construction practice.
We are reasonably content with the dialogue that has taken place. At our liaison meeting in March, we will highlight the fact that aspects of section 2.8 of the revised code of construction practice—we are now on to version 6—which relates to liaison with the mandatory consultees, are quite woolly. We will look to have the code tightened up, especially the provisions that relate to the landscape and habitat management plan and to the environmental management plan.
I am aware that the clerk has taken up the issues with the promoter in a constructive manner. I hope that they will be picked up between now and our final consideration of the bill.
What is your assessment of the risk of flooding?
Are you asking about Hillend reservoir specifically or about the scheme as a whole?
The whole scheme.
I have looked at the preliminary flood risk assessment that Dr Riddell has prepared. It is helpful, because it identifies the various flood risks along the length of the route. It is important to recognise that much of the infrastructure is already in place, because the new rail line will be constructed on an existing rail line. In his report, Dr Riddell indicates that the crossings of the North Calder water in North Lanarkshire do not pose a significant flood risk to the railway. North Lanarkshire Council is quite comfortable with the assessment that Dr Riddell has carried out.
What does SUDS stand for?
Sustainable urban drainage systems, which are constructions that can alleviate potential flood risks. SUDS are not flood defences; rather, they control discharges to watercourses or sewers.
Do you agree with our conclusion that the culverts and the bridge over Barbauchlaw burn are the main areas of concern?
The bridge is a matter for West Lothian Council; it is not in North Lanarkshire. The culverts are a main concern, and we are looking for clarification on what will happen when new developments put additional demands on the existing drainage infrastructure. From our perspective, the culverts and the new infrastructure, which perhaps needs to be attenuated, can be managed. Those things will be picked up during the construction phase.
Does the witness from West Lothian Council want to add anything?
I understand from the promoter's consultant that the flood risk at Barbauchlaw has now been assessed and that it is not considered to be significant.
In a letter to the committee, West Lothian Council urged Network Rail
Culverts are, as a result of their incapacity or, more frequently, their obstruction, the biggest cause of flooding in West Lothian. The Scottish Environment Protection Agency has pointed the promoter in the direction of Construction Industry Research and Information Association—CIRIA—report 168 and recommended the fitting of trash screens, but I am concerned about the fitting of trash screens. They have a place, particularly in an urban environment, but only if they are inspected and cleaned. They must be cleaned more often than a culvert that has no trash screen. I therefore urge caution in that respect.
Okay. Do you know of any significant issue that is not be resolvable by the time the committee must reach a conclusion on the bill, which is some time in early to mid-March?
I think that all the flood risk issues can be addressed.
I agree. However, it is important that the promoter looks urgently at the culverts that must be upsized and that modelling or anything else that must be done to assess downstream flood risks is done quickly.
Thank you very much. I am sure that the hearts of the promoter's representatives are fluttering. We will see where we go.
Is anything missing from the draft code of construction practice or the noise vibration policy that you believe should be included?
There is nothing missing; it is just that we would like some adjustments to be made. Initially, North Lanarkshire Council suggested that noise from the work on the upgrading of the existing line from Airdrie to Drumgelloch and on the new line from Drumgelloch to Bathgate be restricted to working hours—in other words, daylight hours. We suggested that work could be carried out between 8 am and 7 pm Monday to Friday and between 8 am and 1 pm on Saturdays, and that no noise-producing works should be carried out on Sundays or public holidays.
We have been in touch with our environmental health colleagues from North Lanarkshire Council and we agree with those points.
In general, we are pleased with progress on the code of construction practice and the noise and vibration policy. Although there are a few outstanding issues, we think that they will probably be addressed as the design stages progress. However, as SNH and SEPA proposed, we would favour the involvement of an independent monitor in the process, as was set out in the code of construction practice for the Edinburgh airport rail link project.
You think that an independent monitor would be helpful in overseeing the work.
That is quite common practice. At a previous meeting, we mentioned how the Black Law wind farm project—which has recently received awards—went through a similar process.
The involvement of an independent monitor is common practice and would provide you with greater reassurance.
I should add that enforcement, complaint investigation and ensuring compliance with the code of construction practice will represent a cost to the local authority, which should be met by the promoter. That applies both during construction and during the initial period of operation. Once the trains start running, complaints will be made, which will need to be investigated. That will be a cost on the local authority, which should be met by the promoter.
Does the approach being taken, whereby the code of construction practice and the noise vibration policy will be enforced as if they were planning conditions, cause you any difficulty?
If an independent monitor was involved, I do not think that we would have any difficulty with that approach.
However, the witnesses from SNH said that the statutory consultees should be required to give their approval, rather than simply being consulted.
Do you agree that the position should be strengthened?
Yes. That would help SNH, SEPA and the other consultees that were mentioned earlier.
So you agree with SNH that it is not enough to keep people up to date.
Yes.
Mr Toner, you said that your council would prefer to make the decision if the promoter proposed working outwith the agreed hours. Would your fear about noise be alleviated if the decision was made by an independent clerk of works, rather than by a person who worked for the promoter?
Yes. Either the person should consult and get approval from the local authority or there should be an independent clerk of works.
I have a question for Mr Toner on the same topic. Efficient working is important in any construction project, particularly with respect to the overall cost. Is it fair to say that you could identify parts of the line where out-of-hours working could happily take place rather than working hours being constrained?
Yes. That happened with the work on the Auchenkilns roundabout near Cumbernauld. In such cases, the developer comes to us and says, "We've identified that there are no problems here." We check their figures and the proximity of local dwellings and we say yes or no. Sometimes we do not agree, but usually we give approval.
Is it in the interests of the people whom you represent and of the project that the greatest flexibility is allowed? Will that allow the railway to be constructed on time and to be up and running as soon as possible?
Yes. We are not trying to add cost to the development for no reason. We want the project to be completed as quickly as possible, with the maximum flexibility. We are not trying to stand in the way of the development or add cost to it. We just want to safeguard the residents' interests.
I thank the panel for their evidence.
Meeting suspended.
On resuming—
I welcome the witnesses. We will start off on the housing forecasts, although I realise that not everyone on the panel can address that issue. We will move through a range of matters and hear from various individuals as we go.
With regard to the evidence that we heard earlier from local authorities, what does the promoter see as its future role, if any, in relation to housing, housing projections and housing growth along and associated with the line?
I am not sure that I understand your question fully. Do you mean our role in developing housing?
You have stated frequently that the patronage forecasts and economic impact are linked with housing along the route. The committee has received updated figures from West Lothian Council and we have evidence from North Lanarkshire Council. Does the promoter have a continuing role in forecasting the number of houses, the economic impact and the patronage levels?
For our initial submission, we used the housing forecast numbers with which the two councils provided us in the lead-up to the lodging of the bill. We ran the model using those housing forecasts and came up with the benefit cost ratios that we included in the submission. At the time, we also ran a sensitivity analysis, which was included in our promoter's memorandum. It included a number of tests that used different scenarios, such as no population growth in Armadale, Blackridge, Caldercruix and Plains and other bits and pieces, and the analysis confirmed that the business case was still robust.
Therefore, you think that the committee, in its recommendations to Parliament, can have no reservations about the housing forecasts and their association with the economic case for the railway.
I would have no reservations about the business case being strong; I could not say, with my hand on my heart, that the housing figures provided by my colleagues in North Lanarkshire Council are sufficiently robust. However, the numbers that we received before, which are lower, suggest that the business case is robust.
Am I right that, notwithstanding the lack of robust information, even the worst-case scenario from North Lanarkshire does not undermine the case?
That is correct.
Thank you.
Let us move on to local bus provision.
Other than dialogue, what practical measures can and will you take to work towards improved bus provision to bring the stations a step closer to local communities?
It is worth saying from the outset that, following the preliminary stage report, we convened an extremely productive meeting with SPT, West Lothian Council and North Lanarkshire Council. There was a meeting of minds on what could and could not be done.
The committee wants some firm commitments that people who live in villages in the areas surrounding the railway line and who do not have cars will have access to stations. We are looking for a strong commitment to partnership working towards ensuring that there is a bus service for people who use the trains.
I believe that the report gives the firm commitment that you are looking for. All the parties who were co-authors of the report have committed to doing just what you asked for, which is to work together, find solutions and enter into negotiations and discussions with bus companies at the right time. We believe that that is in the lead-up—18 months before the railway comes into service.
So you think that the committee could confidently recommend spending £350 million based on assurances that local people who do not have access to cars will be able to get a bus to and from the stations.
I believe that you can be as confident as you can be with a deregulated bus market and the issues that surround that. We are giving a firm commitment to do what is possible to get the services up and running in time for the start of the railway.
Convener, the committee should make strong recommendations to ensure that people have access to public transport and can get to and from stations. We should seek assurances on that.
Thanks, Cathy. I am sure that we will discuss that in due course. However, not everybody will want to go by bus; some people will want to go by bike. At this point we come to Jeremy Purvis and issues on cycle path alignment. There will be a change of witnesses. [Interruption.]
Mr Lauder of Sustrans believes that, as we move forward with regard to cycle path alignment and access, there are gaps between the promoter and the local authorities in what could be delivered within and outwith the bill. How could that issue be resolved, given the mechanism that has been set up and the fact that the first meeting took place in December? What can the promoter do both before the bill goes before the Parliament and subsequently, as the provider of the service?
First and foremost, we had an extremely productive and positive meeting with the members of the cycling lobby back in December, and we have another meeting planned for March. We have given a commitment to continue those meetings throughout the detailed design process, so that we can get the best out of the cycle run. In the meeting that we had in December, we went through each of the plans individually and agreed whether the cycle route was fine as it was or whether there were opportunities for minor improvements here and there. We identified a number of improvements, and we have given a commitment that we will include them if it is reasonably practicable to do so.
For the record, I ask what definitions you are using. We have heard that reasonably practicable changes could be made, and in your written submission you say that the group is looking at innovative thinking for providing new routes. Can you give an example of what would be reasonably practicable and what would be innovative thinking in providing some of the new routes? What you suggest sounds nice, but illustrations would be helpful.
I will answer the second question first. My experience of innovative thinking often means going back to basics and looking at simple means of design. An example came out of the discussions that we had with the cycling lobby. There are sections of the route where the cycle path will meet a footbridge or cycle-path bridge that will take the cycle path across the railway, but the path might continue on the same side of the railway as well as go across. To get the gradients right, you have to go round to get up the ramp and on to the bridge. The suggestion was, "Why don't we put a set of steps up the side so that people who come across can decide to take a shortcut down the embankment?" That is hardly what one would describe as innovative, but it is more sensible thinking outside the box. Another example of such thinking might be to put in an underpass so that instead of having to go up the ramp and on to the bridge, you could just carry straight on through. We are looking for simple ideas such as those.
Perhaps I can help. "Innovative" might mean cheap and "reasonably practicable" might mean that impracticable measures are expensive.
Cost comes within the terms of the definition of "reasonably practicable"—there is no question about that.
Perhaps the legal team wants to add to that.
The legal team is not at the table at the moment. Karen Gribben, who was sitting beside me, will return as part of a different panel so you can ask her about that then.
I will see how I feel.
That gives her time to think of the answer.
Exactly. I have a further question. The intention is for the group to carry on after completion of the bill in Parliament. Is the plan for it to keep going until the issues have been resolved and then it will cease, or will it carry on to make proper analysis of uptake and to promote the cycle route?
The frequency of meetings will increase during certain parts of the detailed design stage so that we can get feedback and bounce ideas off the group to make sure that we are taking on board their views. As we go into the construction stage, the frequency might continue at a slightly lower rate and the group might tackle issues around the inconvenience to cyclists during the time in which the cycle path or railway are being constructed.
I seek advice from the convener about whether there will be an opportunity during our consideration of the bill to get an update on outstanding issues. I am not sure whether we can accept further written submissions, but there are specific—
To be honest, we have a lot of questions to ask and several outstanding issues. I hope that Mr McAulay is content for the clerk to write to him with three or four further questions. Mr Lauder and Mr Hawkins may rest assured that although we will not pursue the matter in the public glare, they will get copies of those questions and responses. If Mr McAulay does not mind, I will give him a deadline for his responses of Wednesday at noon. I know that he is very good at reading papers. Is that acceptable?
This coming Wednesday?
Yes.
If you can give us the questions as soon as possible, it will help.
You will have them immediately after the meeting.
That will be fine. We are committed to working with the group to make the best of the cycle path.
We recognise that, but there have been concerns throughout the process.
Convener, if Mr McAulay could include in his response what it is that is reasonably practicable and impracticable, and other examples of innovation, that would be welcome.
Can the deadline be extended to Thursday?
I am sure that you can be innovative in how you reply.
I was just thinking of the legal information.
I will be kicked by the clerk, but I will say three o'clock on Wednesday.
That is very generous.
No problem.
First, I would like to get the reaction to what was said earlier, particularly by SEPA.
The convener said that the committee was somewhat disappointed; I have to say that I was disappointed. I spoke to two SEPA representatives before they left, and Angela Burke agreed that I could quote from her e-mail to the clerk of 6 February, in which she stated:
Yes. We received further information about the cross-section at the bridge, and some calculations were made of the one-in-200-year flow to the bridge to determine whether it would pass through the existing structure without touching the underside of the bridge deck. I am happy to advise that that is the case, and therefore there is no significant flood risk to the line at that crossing.
Another issue that was raised was the culverts and their potential for causing flooding downstream if they were increased in size to allow for more capacity. We will be inspecting the culverts and checking their structural integrity and hydraulic capacity. However, I make it clear that the majority of the culverts have been in place for about 100 years.
It is nearly 150 years.
We do not intend to upsize them if we do not need to. I am a wee bit concerned that the issue is a bit of a red herring. [Interruption.] I am sorry, should I wait until the blinds stop moving?
You might have to pause; it sounds as if a train is going past.
I am sure that we have a maintenance squad that we could send out to look at them for you.
The blinds are going up. They were originally lowered for the witnesses' convenience.
I fear that the sun has gone away.
That is right.
As I was saying, if any of the culverts need to be upsized, we will work with SEPA to address its concerns. There is no need to amend the bill to address those issues. We are committed to working with SEPA and, as Angela Burke's e-mail shows, we are talking to SEPA regularly. Our commitment to engagement should be commended, if nothing else.
To add to what Mr McAulay said, we welcome our involvement with SEPA. It has helped us in a lot of ways in preparing the documentation on the new railway. However, we are slightly puzzled by what the SEPA representatives said earlier. The answers to most of the questions that they raised are contained in a letter to the committee clerk dated 9 February. On minor watercourses, the letter states:
I suppose that one of the functions of this committee is to catch people on the hop.
I am turning to my colleague to see whether he can remember how frequently we inspect culverts and clear them out.
Culverts are inspected once a year. As part of our maintenance process we have a robust cleaning regime to ensure that they are kept clean. We have an interest in doing that ourselves, because if we do not do it it can result in flooding of the railway, which can interrupt services.
West Lothian Council does not seem to share that perception.
As far as I am aware, the council has not shared that concern with us. I am happy to look into it.
Are you happy that there will be no outstanding issues of significance between you and SEPA by the time we come to sign off—or not—the bill in early March?
Correct.
That was one of the more serious points that arose earlier.
It is a question of ensuring that there is efficient project management from the top to the bottom, which includes disseminating information as and where it is required. Sometimes, projects are not well enough managed in terms of ensuring that the person who is on the end of the machine or the shovel is involved. We will ensure that there is full training in every aspect of the project, especially where legal compliance is required with regard to protected species. Information will be available right down to the level of giving toolbox talks to people working on the site.
What level of expertise do you have in Network Rail on that?
Network Rail has a huge body of expertise. It is responsible for line-side management of 330 sites of special scientific interest in the UK. There are many rare species on those sites, many of which are European protected species, or nationally and internationally threatened species, such as sand lizards. The sites are managed for those species on a daily and week-to-week basis, in co-operation with the relevant statutory authority, for example Scottish Natural Heritage or English Nature.
I presume that Network Rail is happy with the conditions in the Edinburgh Airport Rail Link Bill being applied to this bill.
Yes. Network Rail is keen to ensure that its body of expertise is applied to this project. There is a slight difference with regard to the independent clerk of works. Network Rail has the competence and expertise that are necessary to ensure compliance on its own behalf. The local authorities and SNH have mentioned the independent clerk of works, but that is perhaps not fully justified, because Network Rail rightly feels that it can deal with the matter on its own behalf.
The arguments on the independent clerk of works extend beyond protected species issues. The committee will consider the matter in the not-too-distant future.
I do not know about being an expert.
In many ways, this code of construction practice is better, but I am slightly biased. I ask my colleague Hugh Wark to comment.
He will tell us how much better it is.
Absolutely. It is one of the best. Seriously, we have tried to take on board everything that has been done in previous codes of construction practice. However, we are different from any of the other promoters, and we believe that the code of construction practice must be tailored to suit the needs of the promoter and of the individual project. It is therefore wrong to expect all the codes to be exactly the same.
It makes sense to design the code of construction practice in line with the work that you are doing.
Once again, I thank all those organisations for their contributions to the code of construction practice. We have had active discussions with all of them and we have taken on board almost everything that they have asked us to do. Some new issues are still coming up and we are happy to take them on board.
Local authorities are looking to be part of and to develop the partnership about which we spoke earlier in relation to transport and buses. It does not matter whether we use the terms "consultation" or "liaison", but it is realistic for local authorities to have their views taken on board—I am not saying that a box needs to be ticked—when issues come up.
We intend to engage meaningfully with them. I am not talking about token engagement. We are working closely with local authorities on buses, the cycle path, the code of construction practice and the noise and vibration policy.
That is fine.
I want to pursue the point. A meaningful relationship with local residents is key to any code of construction practice. If this code is an example of best practice, why does it include no mention of consultation and no indication of enthusiasm to respond to the views of local residents? Section 2.9 is concerned with notification procedures, but it merely sets out the complaints procedures and encourages people to contact you about the effect on their circumstances of the work that is likely to be done. You stop short of saying that you will consider complaints and respond to them in good time. Mr McAulay may tell me that I am wrong.
I am about to.
I would be grateful if you would highlight the section that indicates that you will consider and respond to complaints.
In section 2.5 we talk about our community forums. We also talk about information centres, websites, project newsletters and community relations. We say that we are willing to work to the national standards for community engagement. As a package, those measures represent good practice in respect of engaging with the community and taking comments on board.
Where do you say that when you notify local residents about the work you will—
Sprinkled throughout the document there are references to 14 days' advance notice of works. You referred to section 2.9. The document states that the intention is to set up community forums that will allow us to bring people up to speed on exactly what is happening and to take on board concerns and comments. In some cases there is to be advance notice of as much as 21 days.
Let me phrase the question in another way. The second-last sentence of section 2.9 states that local residents will be encouraged
In the process to date we have responded to inquiries to our website and phone lines within, I think, 24 hours. We will do the same in future. We will get back to people and keep them informed of what we are doing in relation to their concerns. Somewhere in the code—I cannot remember the exact reference—we indicate that there will be a community or contact office that will be manned while work is under way, so that people can speak to someone who has knowledge of the job, is on site and can respond to issues.
To take that a step further, I assume that you envisage the appointment of a project manager who will be responsible for liaison and consultation—as you put it—with communities and other interested parties. We have heard many times today, and at other times, that there are concerns about the fact that the person who is to be responsible for that will be appointed by the promoter. Bills for similar transport schemes, including railway schemes, have included provision for an environmental clerk of works, to be funded by the promoter but employed and appointed by the local authorities that are involved. Both the local authorities that are involved, from which we have heard today and at other times during the bill's process, favour that route. Representatives of SNH spoke earlier about its concerns on the matter and we have previously expressed our concerns to the promoter.
I will start to answer that question, but I will turn to my colleague Hugh Wark to finish off the answer. The first and foremost point to make is that the project manager for the scheme is Hugh Wark, the gentleman who is sitting on my left, so you are seeing the whites of his eyes. He has considerable experience of delivering projects throughout Great Britain's rail network and he understands the issues that can arise when working on the railway or delivering major rail projects.
We have thought carefully about the role of the environmental clerk of works and have three reasons why we think that such a position would be inappropriate in this case. First, the idea is a bad one in principle, because such a role would split responsibility between two organisations—Network Rail and the local authority—which is not a good idea. Secondly, the role is unnecessary because, as Ron McAulay said, we deliver billions of pounds-worth of project work throughout the railway network; we have a myriad of processes and procedures in place and we are checked independently to ensure that we adhere to all our project management processes, which include properly managing environmental issues. Thirdly, the measure would not work. As Ron McAulay said, we have a railway safety case that is approved by Her Majesty's railway inspectorate and by the Office of Rail Regulation, which would make it difficult for someone to come in from outside and be part of the daily management process for our project.
I hear what you are saying about your legal responsibilities and about your being different from the promoters of other bills, although I cannot comment on that because I cannot remember who they all were. However, only one of your three arguments stacks up. The argument about splitting the role and the last of the arguments that you have made do not come into the fact—in your opinion—that you are legally responsible and audited closely. I have concerns about why, if there being an independent environmental clerk of works works in other situations, it will apparently not work in this situation.
The point that we were making before was that a mechanism of enforcement and policing exists, which is why we think that an environmental clerk of works is an unnecessary layer on the top. Enforceability, which comes through the planning process, is sufficient to address the operational issues.
Yes—but do not you agree that there is a perception that, if someone is working outwith the organisation promoting the bill, that is a better way to allow people to think that their views are being considered and that they are being given a fair hearing?
I can understand that perception. Our response is that the way in which we will deal with people in community fora will be evidence enough that we are listening to what they are saying and that we are taking on board their concerns. Through the enforceability side, councils will be able to say that they are not satisfied and that we need to do more. They have that fallback position.
Is there precedent of an independent clerk of works overseeing other projects that have been dealt with by Parliament?
This is a fairly contentious issue, and the committee will deliberate on it. I will comment on the matter in my winding-up remarks: as members have no further questions, we now come to those.
Nothing is actively preventing withdrawal of those objections. Some agreements are particularly complex and require detailed discussions. I am not sure whether we necessarily agree with the figure that you gave—by my reckoning, 29 objections have been withdrawn. We have had difficulties in obtaining final letters from some people, although they have confirmed that they are happy with the settlement. That does not include people such as the advance purchase scheme candidates, who have said as a whole that they are happy to accept the offer but will not withdraw their objections until missives have been exchanged on their properties. I am sure that the committee understands why they wish to wait until missives have been concluded.
It is good to hear that you are ahead of the game on the figures that we have, but we stress the importance of clearing the objections. Perhaps you recognise that already. What do you advise us to do in seeking to progress the bill through Parliament if several objections remain outstanding? In what position would that put the committee?
With the exception of Airdrie and District Angling Club's objection, to which we will come in a few moments, the vast majority of objections are resolvable; reaching an accommodation with the objectors is a question of detail. I do not consider that there are any fundamental issues outstanding that will affect Parliament's decision on whether to pass the bill. No issues of substance or impediment exist.
Determination of the validity and merits of objections is ultimately a task for the committee. We will certainly face up to that when the time comes.
We estimate that if the bill is not passed before Parliament is dissolved, the project will probably be put back about a year. We have explained our reasoning for that in previous evidence. That ties in with matters such as the timetabling process in the industry—new timetables are introduced every December. The big issue would be not so much the impact on Network Rail as the fact that the benefits that the railway can bring would not be realised for probably another year and the costs would rise because of inflation. I am not sure how much of the bill process would have to be followed again if the bill were not passed before Parliament dissolved—perhaps you can enlighten me on that.
I understand that we would return almost to square 1. Nobody—particularly the committee—would want that, but the committee has a duty to ensure that objections are dealt with properly and that all aspects of the bill, including costs, meet the original intent.
That is correct. If the process went back to square 1, I would revise my estimate and say that that would probably put benefits back two years.
Okay. Thank you very much, Mr McAulay. The committee has been conscious of time limitations throughout the procedure. We will do all that we can to ensure that progress is made, although whether it will be remains in your hands.
We do not have a problem with providing information in a note by the Friday deadline, but I want to be clear about something. Must the objector's comments on the note be submitted by Friday, too?
Yes.
I will have to speak to the club's agents about that. Obviously, we are talking about a private members' club, which must convene special meetings to obtain comments from members. I am not sure how soon the club can convene such a meeting, but I will speak to the agent about the matter.
It is in the club's interests to do so.
I realise that.
I would appreciate your discussing any problems with the clerk, who will, if necessary, be able to adjust the deadline to meet our requirements. Thank you for your positive comment.
Members indicated agreement.
Meeting closed at 17:03.