Question

To ask the Scottish Government what analysis it has (a) conducted and (b) commissioned on the total potential environmental remediation cost of the Dalzell steelworks.


Answer

A soil and groundwater contamination liability assessment covering the Lanarkshire steelworks was prepared for the Scottish Government in 2016.

A copy of the report with redactions in line with FOISA exemptions is available from the Scottish Government website here

( https://www.gov.scot/binaries/content/documents/govscot/publications/foi-eir-release/2021/07/foi-202100216003/documents/foi202100216003---information-released-2/foi202100216003---information-released-2/govscot%3Adocument/FOI202100216003%2B-%2BInformation%2Breleased%2B2.pdf ).