Question reference: S6W-02328
- Asked by: Edward Mountain, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
- Date lodged: 18 August 2021
-
Current status: Answered by Keith Brown on 31 August 2021
Question
To ask the Scottish Government which company has been awarded the contract to design and construct HMP Highland.
Answer
I have asked Teresa Medhurst, Interim Chief Executive of the Scottish Prison Service (SPS), to respond. Her response is as follows:
‘ Tender evaluation for the pre-construction services award (PCSA) element of the HMP Highland project is underway and SPS anticipates the initial contract award will be made during September 2021.’