- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Wednesday, 23 April 2025
-
Current Status:
Taken in the Chamber on 1 May 2025
To ask the Scottish Government what support it is providing to any people in Glasgow who are at risk of losing their mental health support due to the reported reductions announced by the Integration Joint Board.
Answer
Taken in the Chamber on 1 May 2025
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Tuesday, 22 April 2025
-
Current Status:
Answer expected on 6 May 2025
To ask the Scottish Government whether it will engage with the board of Wood Group PLC to explore all alternative options to refinance the firm and prevent a takeover by the Dubai-based, Sidara.
Answer
Answer expected on 6 May 2025
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Tuesday, 22 April 2025
-
Current Status:
Answer expected on 6 May 2025
To ask the Scottish Government whether it plans to seek an equity share in the development of any of the nine projects identified by the Project Willow report for the industrial redevelopment of the Grangemouth refinery complex.
Answer
Answer expected on 6 May 2025
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Tuesday, 22 April 2025
-
Current Status:
Answer expected on 6 May 2025
To ask the Scottish Government when the Glasgow Central Station low-level refurbishment works will commence.
Answer
Answer expected on 6 May 2025
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Friday, 28 March 2025
-
Current Status:
Answered by Fiona Hyslop on 22 April 2025
To ask the Scottish Government what sub-contracting opportunities are contained in the Small Vessel Replacement Programme, as defined by section 24 of the Procurement Reform (Scotland) Act 2014.
Answer
Sub-contracting arrangements within the Small Vessel Replacement Programme Phase One vessel contracts are ultimately determined by the main contractor and may reflect existing supply chain relationships. The wider programme of works to support the new vessel deployment and operation includes around £40 million of shore power upgrades, power connections and port improvement works. These works will be progressed across the network over the coming years to enable delivery from around summer 2027 and may present further sub-contracting opportunities.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Thursday, 17 April 2025
-
Current Status:
Answer expected on 15 May 2025
To ask the Scottish Government whether any funds received by local authorities from the extended producer responsibility scheme will be used to reduce council tax bills and, if so, how this will be implemented.
Answer
Answer expected on 15 May 2025
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Tuesday, 01 April 2025
-
Current Status:
Answered by Fiona Hyslop on 17 April 2025
To ask the Scottish Government whether any Barnett consequential funding arising from the Lower Thames Crossing project will be used to accelerate the development of the Clyde Metro project.
Answer
Development consent for the Lower Thames Crossing was granted by the UK Secretary for State for Transport on the 25 March 2025. The UK Chancellor of the Exchequer noted in a speech made on the 29 January 2025, that the UK Government was exploring private finance as option to fund the project. Therefore, it is currently unclear what, if any, Barnett consequentials may arise from this project and in any case, these are not ring fenced for transport projects in Scotland.
The ongoing stage of the early development process for Clyde Metro, known as the Case for Investment, is being led by Strathclyde Partnership for Transport (SPT), supported by Glasgow City Council, with Transport Scotland providing a project assurance role. This key stage, which will inform decisions around network selection, phasing and implementation is well underway and is currently anticipated to be complete by mid-2027.
This initial stage in the development process is being delivered drawing upon funding from the Glasgow City Region Deal. It is too early in the development process to determine the longer term funding of Clyde Metro, however, it is envisaged that the funding models for its implementation will be considered as part of the on-going Case for Investment work.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Friday, 28 March 2025
-
Current Status:
Answered by Fiona Hyslop on 17 April 2025
To ask the Scottish Government what community benefit requirements have been included in the contract for the Small Vessel Replacement Programme under the terms of the Procurement Reform (Scotland) Act 2014.
Answer
CMAL has confirmed that it included two strands of community benefit commitments in its contract with Remontowa. The first provides opportunity for three Scotland-based shipbuilding apprentices per vessel, 21 in total, to attend optimisation and sea trials for training purposes when the vessels are delivered. The second is that Remontowa shipyard will match CMAL’s funding for its Corporate Social Responsibility programme over the course of the build, which supports charity initiatives across local communities in the Clyde and Hebrides region.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Wednesday, 16 April 2025
-
Current Status:
Answer expected on 14 May 2025
To ask the Scottish Government how the funding received by local authorities under the extended producer responsibility scheme will be managed, and whether there are plans to pass on these funds to residents through reduced council tax bills and, if so, how this will be implemented.
Answer
Answer expected on 14 May 2025
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Wednesday, 16 April 2025
-
Current Status:
Answer expected on 14 May 2025
To ask the Scottish Government what the requirements expected of local authorities are in return for the additional funds that they will receive under the extended producer responsibility scheme.
Answer
Answer expected on 14 May 2025