Question reference: S6W-26694

  • Asked by: Sarah Boyack, MSP for Lothian, Scottish Labour
  • Date lodged: 5 April 2024
  • Current status: Answered by Gillian Martin on 23 April 2024

Question

To ask the Scottish Government what the average time was for a response to a scoping opinion request submitted under section 12 of the Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2017 in (a) 2019, (b) 2020, (c) 2021, (d) 2022 and (e) 2023.


Answer

Applications which make their way through the application journey on the energyconsent.scot portal are assigned a single case number which is retained from the pre-application period, all the way through to a determination decision.

The dates at which a scoping opinion request submitted under section 12 of the Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2017 is received, and then a response provided, are not data points which are captured by the portal system. It is therefore not possible to calculate the average time taken to provide a response in the years requested.