Question

To ask the Scottish Government whether seaweed cultivation will be included under schedule 2 of the Marine Works (Environmental Impact Assessment) (Scotland) Regulations 2017.


Answer

Construction of a seaweed farm is not considered to be a schedule 2 project under the Marine Works (Environmental Impact Assessment) (Scotland) Regulations 2017 and as such no Environmental Impact Assessment (EIA) or EIA screening is currently required.

There are currently no plans to revise the Marine Works (Environmental Impact Assessment) (Scotland) Regulations 2017 to include construction of seaweed farms as a schedule 2 project.