Skip to main content

Language: English / GĂ idhlig

Loading…

Chamber and committees

Question reference: S6W-26012

  • Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
  • Date lodged: 12 March 2024
  • Current status: Answered by Neil Gray on 22 March 2024

Question

To ask the Scottish Government whether it will provide an update on the progress of remedial works at the Royal Hospital for Children and Young People in Edinburgh regarding the spacing of cavity barriers.


Answer

There has been significant progress on proposals for work on the spacing of cavity barriers behind the cladding, since NHS Lothian was recommended to reduce the spacing with cavity barriers from 20 metre intervals to 10 metre intervals. The following is a summary the progress to date:

1. The works required the submission to and approval from City of Edinburgh Council’s Building Control Department. The application was submitted in April 2023 and approved in October 2023.

2. Following approval from Building Control, NHS Lothian and IHSL, the consortium that built and owns the Royal Hospital for Children and Young People and Department of Clinical Neurosciences, have been in discussion about commercial terms for the works to be undertaken.

3. Further detail on the frequency and duration of works was provided by IHSL in February 2024. It is anticipated that, including pre-construction activities, the works will take in excess of one year to complete. An agreed start date will be finalised once commercial terms have been completed.