Question reference: S6W-26006

  • Asked by: Alex Cole-Hamilton, MSP for Edinburgh Western, Scottish Liberal Democrats
  • Date lodged: 6 March 2024
  • Current status: Answered by Gillian Martin on 19 March 2024

Question

To ask the Scottish Government whether it will provide an update on the progress of the projects that were successful in the 2022 ScotWind leasing round, broken down by the stage that each project has achieved; in light of any modelling that it has undertaken regarding any rental income from these projects, on what date it expects to begin receiving any such income, and how much it expects to receive annually.


Answer

There are 20 ScotWind projects with seabed option agreements. The first 17 successful projects were announced by Crown Estate Scotland in April 2022. These were joined in October 2022 by three further projects, granted agreements through the Clearing process. To date, one ScotWind project, N1 - West of Orkney Wind Farm, has submitted an application for consent under section 36 of the Electricity Act 1989 and associated marine licences under section 20 of the Marine (Scotland) Act 2010 and section 65 of the Marine and Coastal Access Act 2009. All other ScotWind projects are at the pre-application stage, with 6 environmental impact assessment scoping opinions issued by Scottish Ministers to date.

Crown Estate Scotland currently expects to see rental income of £4Million per Gigawatt per annum, based on 2024 prices. Rent is indexed against the Consumer Prices Index so this figure could change. The rent will go to Crown Estate Scotland once projects are operational. While it is too early to know when that will happen, it is generally 10 years from option award. The nature of project development means Crown Estate Scotland cannot be certain at this time what total capacity will ultimately get built.