Question

To ask the Scottish Government, further to the answer to question S6W-24644 by Patrick Harvie on 2 February 2024, whether it will provide the information requested regarding whether an impact assessment was conducted regarding the £9.3 million reduction to the total "Energy Efficiency and Decarbonisation" budget, and for what reason it did not provide this information in its answer.


Answer

Despite a reduction in overall funding of £9.3m, the budget settlement for 24-25 included an increase in Capital funding to balance the reduction in Financial Transactions, this is overall sufficient to meet the demands of the Heat in Building programme in 24-25, and as a result no impact assessment was required.