Question reference: S6W-25223

  • Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
  • Date lodged: 5 February 2024
  • Current status: Answered by Mairi McAllan on 19 February 2024

Question

To ask the Scottish Government, further to the answer to question S6W-24320 by Neil Gray on 19 January 2024, what the most recent (a) total cost is of the contract for Hull (i) 801 and (ii) 802 and (b) projected operational date is for Hull 801.


Answer

The Chief Executive of Ferguson Marine provided the most recent costs for completion of the vessels to the Net Zero, Energy and Transport Committee in September 2023.

The Chief Executive also informed the NZET Committee in January that the estimated total cost to complete both vessels was being reviewed and the outcome would be notified to the Committee and Scottish Government before 23rd February.

Following a period of berthing trials and crew familiarisation the MV Glen Sannox (Hull 801) is set to be operational eight weeks after handover. The handover date is also in the process of being revised by Ferguson Marine and we expect this to be notified with the updated forecast costs.