Question reference: S6W-24779

  • Asked by: Alex Rowley, MSP for Mid Scotland and Fife, Scottish Labour
  • Date lodged: 24 January 2024
  • Current status: Answered by Fiona Hyslop on 1 February 2024

Question

To ask the Scottish Government, further to the answer to question S6W-23728 by Fiona Hyslop on 8 January 2024, whether it will set out details of the re-profiling of the budget for the small vessel replacement programme from 2023-24 to 2027-28, and whether it can confirm if this accounts for any capital expenditure required to upgrade shoreside refuelling facilities.


Answer

The outline business case is currently being considered by Ministers. The re-profiling of budget from 2023-24 will not impact on the timelines for delivery, with the first vessel still expected to enter service in 2026. The total capital cost of the programme, as per the outline business case, includes upgrades for the provision of shore power.