Question
To ask the Scottish Government how many applications from (a) registered social landlords and (b) local authorities have been (i) received and (ii) approved for the National Acquisition Plan since it was announced on 19 July 2023.
Answer
The following table shows the number of homes approved from applications received from (a) registered social landlords (b) local authorities since the National Acquisition Plan was announced on 19 July 2023. This information is to 24 August 2023:
National Acquisition Programme | Applications for nos. of homes received | No. of homes approved |
Registered social landlord | 3 | 3 |
Local authority | 52 | 52 |
Total | 55 | 55 |
It should also be noted that, in addition, applications were also received and approved prior to the announcement on the 19 July.