Question

To ask the Scottish Government whether it will provide an update on the upgrading of a number of laybys on the A77.


Answer

Investigation work has been undertaken on the upgrade of 4 laybys on the A77 between Ayr and Stranraer. The designs to improve these 4 laybys will be completed by the end of this calendar year with construction anticipated early in financial year 2024/25.