Question reference: S6W-16996

  • Asked by: Clare Haughey, MSP for Rutherglen, Scottish National Party
  • Date lodged: 12 April 2023
  • Current status: Answered by Joe FitzPatrick on 2 May 2023

Question

To ask the Scottish Government how much funding it has given to Clyde Gateway in each year since it was established, broken down by the purpose of the funding.


Answer

The Scottish Government has awarded over £205 million of regeneration funding to Clyde Gateway Urban Regeneration Company (URC) from 2007 to 2023 for the purpose of supporting the delivery of its 20-year operating plan. This includes direct support through annual capital and resource funding to develop and regenerate key sites identified in the plan, support core running costs and other activities it delivers in support of local communities.

Grant awards were made in each financial year are provided in the following table:

Financial Year

Capital funding

£000

Resource funding

Comment

2006-07

3,022

  

2007-08

5,000

  

2008-09 to 2010-11

57,000

 

Three-year funding from 1 April 2008 to 31 March 2011

2011-12

11,554

746

 

2012-13

17,725

1,525

 

2013-14

19,525

1,525

 

2014-15

9,290

1,850

 

2015-16

1,816

184

 

2016-17

3,070

500

 

2017-18

5,000

500

 

2018-19

5,000

500

 

2019-20

6,130

500

 

2020-21

6,000

1,000

£500k revenue funding provided to support COVID-19 response.

2021-22

9,000

500

 

2022-23

5,500

500

 

We understand that Clyde Gateway in delivering their strategic operational plan have since their formation in 2007 developed and delivered numerous projects to support the communities. Information on all of the grants Clyde Gateway may have received from various funding bodies supported with Scottish Government funding is not held centrally in the format requested. We can advise that information on the following grants awarded to Clyde Gateway is held:

Regeneration Capital Grant Fund

Regeneration Capital Grant Fund (RCGF): recommended projects 2014 to 2024 - gov.scot (www.gov.scot)

Vacant & Derelict Land Investment Programme

Low Carbon Fund: Vacant and Derelict Land Investment Programme projects - gov.scot (www.gov.scot)

Investing in Communities Fund

Investing in Communities Fund - round 1 2019 to 2022 : panel approved organisations - gov.scot (www.gov.scot)

The Scottish Government remains committed to supporting Clyde Gateway URC, working with local and regional partners to deliver a place-based regeneration programme that tackles inequalities, creates jobs and opportunities, and improves outcomes for local people and communities. In 2023-24 continued funding of up to £5 million capital will be made through the Place Based Investment Programme and £0.5 million resource funding to support core running costs.