Question reference: S6W-12531

  • Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
  • Date lodged: 28 November 2022
  • Current status: Answered by Neil Gray on 12 December 2022

Question

To ask the Scottish Government, further to the answer to question S6W-10754 by Neil Gray on 8 September 2022, what the (a) total cost to date and (b) estimated cost up until the contract end date is of chartering the MS (i) Victoria and (ii) Ambition.


Answer

As of 1 December 2022, the total estimated cost for the MS Victoria until the contract ends in June 2023 is £37.9 million. The total estimated costs for the MS Ambition contract until February 2023 is £26.1 million. We cannot calculate the final costs until the contracts end.