Skip to main content

Language: English / GĂ idhlig

Loading…

Chamber and committees

Question reference: S6W-07073

  • Asked by: Dean Lockhart, MSP for Mid Scotland and Fife, Scottish Conservative and Unionist Party
  • Date lodged: 4 March 2022
  • Current status: Answered by Kate Forbes on 17 March 2022

Question

To ask the Scottish Government whether it will provide an update on the (a) timetable for the delivery and (b) latest estimated overall cost of public money of the two new ferries being built for the CalMac fleet.


Answer

The CEO of Ferguson Marine is preparing an update, for the Net Zero, Energy and Transport Committee, on the delivery timetable and budget for vessels 801 and 802 which will be submitted before the end of March 2022.